Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 4

Case Study: R. C.

Coleman

Shripal Shah Case Study #2 R. C. COLEMAN Prof. Marian Reiff University of Redlands, Riverside Campus

Case Study: R. C. Coleman The Critical Path is: B-C-E-F-H-J-K The EXPECTED PROJECT COMPLETION TIME = 43 weeks The Variance of Critical path = 2.778 + 0.444 + 1.00 + 0.444 + 0.444 + 0.111 + 0.444 = 5.67 From the standard normal distribution table: Area of probability = 0.3962 P (t < 40) = 0.5 0.3962 = 0.1038 From the calculations above, there is about 10.38% chance for R.C Coleman to complete the project in 40 weeks or less. Recommendation: In case 40-week completion required, R.C. Coleman should consider crashing project activities. 2. From the standard normal distribution table, for 80% chance: z = 0.84 Also, z = 40-t5.67 = 0.84 * t = 38 weeks R.C Coleman should crash activities to reduce the expected completion time to 38 weeks , shorten by 2 weeks. 3. Using the expected activity times as the normal times to determine the crashing activity decision Let xi = the completion time for activity i

yi = the amount of crash time for activity i Min 450yA + 400yB + 600yC + 300yD + 1000yE + 550yF + 750yG + 700yH + 800yI + 400yJ + 500 s.t xA + yA > 6 xB + yB > 9 xC + yC xA > 4 xC + yC xB > 4 xD + yD xC > 12 xE + yE xC > 10

Case Study: R. C. Coleman xF + yF xE > 6 xG + yG xC > 8 xH + yH xF > 6 xH + yH xG > 6 xI + yI xD > 7 xI + yI xF > 7 xJ + yJ xH > 4 xK + yK xI > 4 xK + yK xJ > 4 xK < 38 yA < 2 yB < 2 yC < 2 yD < 4 yE < 3 yF < 2 yG < 3 yH < 2 yI < 3 yJ < 1 yK < 1 All xi,yi > 0

Case Study: R. C. Coleman Minimum-cost crashing solution Optimal crashing decisions are as follows: Activity| Time in weeks | crash | Cost | A B C D E F G H I J K |6 |7 |4 | 12 | 10 |5 |8 |6 |7 |3 |3 |0 |2 |0 |0 |0 |1 |0 |0 |0 |1 |1 || 800 |||| 550 |||| 400 | 500 | | | | | | | | | | |

| Total |

| 2250 |

The additional cost for a project goal of 40 weeks is $1200 The additional cost for a project goal of 38 weeks is $2250 A revised activity schedule based on these crashing decisions is attached.

You might also like