73-220, Summer 2005 – Solutions, Assignment 2

7–9

Min 30.95MC + 31.10MD + 30.90MN + 32.30PC + 33.45PD + 31.80PN


+ 31.55FC + 31.55FD + 32.15FN

s.t.
MC + MD + MN ≤ 400
PC + PD + PN ≤ 600
FC + FD + FN ≤ 300
MC + PC + FC = 400
MD + PD + FD = 400
MN + PN + FN = 400
PD = 0

7 – 21(a)

Min 150A1 + 210B1 + … + 230C4

s.t.
A1 + B1 + C1 ≤ 1
A2 + B2 + C2 ≤ 1
A3 + B3 + C3 ≤ 1
A4 + B4 + C4 ≤ 1
A1 + A2 + A3 + A4 = 1
B1 + B2 + B3 + B4 = 1
C1 + C2 + C3 + C4 = 1

7 – 26
5 150
8
7
300 1 5 3 5
7
3 5 6 100
4 6
100 2 4 10
7 150
Min 7X13 + 5X14 + 3X23 + 4X24 + 8X35 + 5X36 + 7X37 + 5X45 + 6X46
+ 10X47

s.t.
X13 + X14 = 300
X23 + X24 = 100
X35 + X45 = 150
X36 + X46 = 100
X37 + X47 = 150
X13 + X23 – X35 – X36 – X37 = 0
X14 + X24 – X45 – X46 – X47 = 0

8 – 14

Min 25M + 35N1 + 35N2 + 40O + 20C

s.t.
500M + 800N1 + 400N2 + 900O + 200C ≥ 900
300M + 400N1 + 800N2 + 600O + 300C ≥ 900

8 – 21

Min X1 + X2 + … + X13

s.t.
X1 + X4 + X6 ≥ 1
X6 + X8 + X12 ≥ 1
X1 + X2 + X3 ≥ 1
X3 + X4 + X5 + X7 ≥ 1
X7 + X8 + X9 + X10 ≥ 1
X10 + X12 + X13 ≥ 1
X2 + X5 + X9 + X11 ≥ 1
X11 + X13 ≥ 1
9–4

Min 3X12 + 4X13 + 3X14 + 2X24 + 4X25 + 2X34 + 4X35 + 5X36 + 2X42
+ 2X43 + 3X45 + 4X52 + 4X53 +3X54 + 5X63 + 2X65 + 3X67 + 2X68
+ 3X76 + 2X78

s.t
X12 + X13 + X14 = 1
X58 + X68 + X78 = 1
X12 + X42 + X52 – X24 – X25 = 0
X13 + X43 + X53 + X63 – X34 – X35 – X36 = 0
X14 + X24 + X34 + X54 – X42 – X43 – X45 = 0
X25 + X35 + X45 + X65 – X52 – X53 – X54 – X56 – X58 = 0
X36 + X56 + X76 – X63 – X65 – X67 – X68 = 0
X67 – X76 – X78 = 0

9 – 12

5
2
5
6 6 3 4
8
2
1 7 4 6 8
3
5
8 5 6 4

6 7
4

total distance = 29 (100’s) feet


9 – 17

Max X47 + X57 + X67

s.t.
X12 ≤ 4
X13 ≤ 3
X14 ≤ 4
X23 ≤ 2
X26 ≤ 3
X34 ≤ 3
X35 ≤ 1
X36 ≤ 2
X45 ≤ 2
X47 ≤ 5
X57 ≤ 2
X67 ≤ 3
X12 – X23 – X26 = 0
X13 + X23 – X34 – X35 – X36 = 0
X14 + X34 – X45 – X47 = 0
X35 + X45 – X57 = 0
X26 + X36 – X67 = 0

10 – 1 C F

A D G
start

B E H finish
10 – 7
A 0 3 C 3 5 D 6 11 E 11 15 F 15 18
3 1 4 2 4 6 5 6 11 4 11 15 3 15 18
3

start

finish
B 0 6 G 6 15 H 18 21
6 0 6 9 9 18 3 18 21
6

Activity ES LS EF LF slack critical?

A 0 1 3 4 1 NO
B 0 0 6 6 0 YES
C 3 4 5 6 1 NO
D 6 6 11 11 0 YES
E 11 11 15 15 0 YES
F 15 15 18 18 0 YES
G 6 9 15 18 3 NO
H 18 18 21 21 0 YES

Critical path: B–D–E–F–H


Expected completion time: 21 weeks

10 – 20 (a)

time(weeks) cost($) crash


activity normal crash normal crash cost/wk

A 3 1 900 1700 400


B 6 3 2000 4000 666.67
C 2 1 500 1000 500
D 5 3 1800 2400 300
E 4 3 1500 1850 350
F 3 1 3000 3900 450
G 9 4 8000 9800 360
H 3 2 1000 2000 1000
Min 400YA + 666.67YB + 500YC + 300YD + 350YE + 450YF + 360YG
+ 1000YH

s.t.
YA ≤ 2
YB ≤ 3
YC ≤ 1
YD ≤ 2
YE ≤ 1
YF ≤ 2
YG ≤ 5
YH ≤ 1
XA + YA ≥ 3
XB + YB ≥ 6
-XA + XC + YC ≥ 2
-XB + XD + YD ≥ 5
-XC + XD + YD ≥ 5
-XD + XE + YE ≥ 4
-XE + XF + YF ≥ 3
-XB + XG + YG ≥ 9
-XC + XG + YG ≥ 9
-XF + XH + YH ≥ 3
-XG + XH + YH ≥ 3
XH ≤ 16