Staff scheduling:
Decision variables
x1: # of RNs on schedule 1;
x2: # of RNs on schedule 2;
x3: # of RNs on schedule 3;
x4: # of RNs on schedule 4;
x5: # of RNs on schedule 5;
x6: # of RNs on schedule 6;
x7: # of RNs on schedule 7.
Objective function
Min salary: 550x1+625x2+625x3+625x4+625x5+575x6+500x7
Constraints
Sun: x2 x3 x4 x5 x6 22
Mon: x3 x4 x5 x6 x7 17
Tue: x1 x4 x5 x6 x7 13
Wed: x1 x2 x5 x6 x7 21
Thurs: x1 x2 x3 x6 x7 16
Fri: x1 x2 x3 x4 x7 14
Sat: x1 x2 x3 x4 x5 20
Nonnegativity: x1 , x2 ,..., x7 > 0
2. Blending problem:
Decision variables
x1: tons of ore from mine 1 in each ton of the blend
x2: tons of ore from mine 2 in each ton of the blend
x3: tons of ore from mine 3 in each ton of the blend
x4: tons of ore from mine 4 in each ton of the blend
Objective function
Min cost
Min 800x1+400x2+600x3+500x4
Constraints
Element A: 10 x1 3 x2 8 x3 2 x4 5
Element B: 90 x1 150 x2 75 x3 175 x4 100
Element C: 45 x1 25 x2 20 x3 37 x4 30
Weight: x1 x2 x3 x4 1
Nonegativity: x1 , x2 , x3 , x4 0