Scheduled Maintenance for Centrifugal Pump Gould M

Minor overhaull (6 months)

Immediate mantainence (12 months)

Overhaull (36 months)

Minor overhaull (6 months)

Scheduled Maintenance for Centrifugal Pump Gould Manufacture


Description Do renew oil lubrication Checking firmly the stability baseplate Washing the filter of the suction line Checking and cleaning the coupling Washing the heat exchange for Mechanical seal Dismantling, checking and cleaning all the parts of the mechanical seal Checking and re-alignment Dismantling the pump, checking all specification of the shaft, ball bearing, changing new ones if not met the requirement Dismantling, checking the condition diaphragm of the coupling Washing contamination inside the pump and all the relative piping system Checking balance dynamic (depending on a status of the pump)

Vertical Pump
Do renew oil lubrication Checking firmly the stability baseplate Washing the filter of the suction line Checking and cleaning the coupling Washing the heat exchange for Mechanical seal

Gould Manufacture
Period

Minor overhaull (6 months)

Immediate mantainence (12 months)

Overhaull (36 months)

Minor overhaull (6 months)