Website Development

Initiation and planning

1.1 1.2

Business justification Scope statement

1.3

Create project charter

1.4

Funding commitment (100%)

1.5 1.6

Sign project charter Reserve resources

2 3

Project management activities Analysis

3.1

Gather requirements

3.2

Identify data sources

3.3

Sign off on requirements

3.4

Create project plan

3.5 3.6 4 4.1

Statement of work (60%) SOW signoff Design Develop test plans

4.2 4.3 4.4

Develop site hierarchy Reports

4.5

Technical design

4.5.1

Develop technology guidelines

4.5.2 4.5.3 4.5.4 4.5.5 4.5.6 4.6

Design database schema

Administration tool

Sign off on design

4.7

Update project plan

4.8 4.9 5 5.1 5.2 5.3

Statement of work (30%) SOW signoff Construction Install software Construct database

5.4 5.4.1 5.4.2 5.4.3 5.4.4 5.5 5.5.1 5.5.2 5.5.3 5.5.4 5.6 Construct pages

5.6.1

Content Templates

5.6.2

Cascading style sheets

5.6.3 5.7 5.7.1 5.7.2 5.7.3 5.7.4 5.7.5 5.7.6

Tie database to pages Reports Framework Usage report Site change report Error report

5.8

Administration tool

5.8.1 5.8.2 5.8.2.1

Framework and interface Screens Content input

5.8.2.2 5.8.2.3 5.8.2.4 5.8.3 5.8.3.1 5.8.3.2 5.9 6 6.1 6.2

Data source management User access Report

Testing System test Rework

6.3 6.4 6.5 7 7.1 7.2 7.3

User acceptance testing Rework Testing signoff Deployment Automated deploy Test Rework

7.4 7.5 8

User acceptance test Testing signoff Closure

8.1 8.2

Documentation for support Archive code

8.3

Archive documents

8.4 8.5 8.6

Turnover to support Release resources Project signoff