Chlorination Calculation: Well pump flow rate: 4.65 L/S Dosing pump flow rate: 3.7 L/hr ~ 0.

00103 L/S Sodium hypochlorite 5%: 50000 PPM Amount of residual chlorine: 1 PPM Volume of chlorination tank: 100 Lit Amount of needed chlorine in dosing pump flow rate: V1 C1 = V2 C2 4.65 L/S x 1 PPM = V2 x 50000 PPM V2 = 0.000093 L/S Ratio of Residual chlorine in the chlorinator discharge: 0.00103 L/S 100 0.000093 L/S ? = 9.03 % Amount of sodium hypochlorite 5% in the chlorinator tank: 100 L x 9.03% = 9.03 L Amount of water in chlorinator tank: 100 L 9.03 L = 90.97 L With considering 16 hour work per day for well pump, discharge of chlorinator tank will be: 16 hr/day x 3.7 L/hr = 59.33 L/day 100 L / (59.33 L/day) = 1.69 Day; so chlorinator tank will be refill in 1 2 days.