1.0 Readiness of Condensate & feed water system: (i) HP/IP BFP BFP-A
DMCW branch piping hydro test is pending (BFP Jacket, working oil cooler, lube oil cooler, booster pump jacket, motor air cooler). Erection of Flow Element on pump discharge line with pipe fittings. Pipe trench cleaning (filled with water/oil, unwanted material).
BFP-B
Following work pending which needs to be completed before trial run. Final alignment between BFP &Hydraulic coupling. BFP Pump foot & base plate Key block clearance check &welding. Installation of BFP Coupling with torque tightening. Boiler feed Pump base plate Key block welding. Final alignment between Booster pump & motor. Installation of Coupling b/n Booster pump & motor. Booster pump coupling bolts torque tightening. DMCW branch piping hydro test is pending (BFP Jacket, working oil cooler, lube oil Cooler, booster pump jacket, motor air cooler).
(iii) LP BFP
LPBFP-B: Mechanically ready for trial run. LP BFP- A Following pending work to be completed before trial run Motor trail run Final alignment between pump &motor Installation of coupling