Schedule of Fitting Out Works for expansion of Mandarin Bible Church

Person Month Jan Feb


Item Activities
to follow Period 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

1.0 Obtain information of site 2 days


2.0 Obtain user perferences 7 days
3.0 Produce design drawings
3.1 Fitting out works 3 days
3.2 Ventilation and air conditioning 3 days
3.3 Fire services 3 days
3.4 Plumbing and drainage 3 days
3.5 Electrical power and lighting 3 days
3.6 Audio visual 3 days
3.7 Telephone and internet 3 days
4.0 Calling quotations
4.1 Obtain offers 7 days
4.2 Assess quotations 2 days
5.0 Appoint Contractor
5.1 Mobilisation 3 days
6.0 Execution of Works
6.1 Construction period 30 days
7.0 Take over
Inspection of works 2 days
8.0 Apply utilities
8.1 Power supply from HKE 7 days
8.2 Phone lines from telephone company 7 days
8.3 Internet services form services provider 7 days
9.0 Direct purchase
Furniture and applicances 7 days
Phone system 10 days
10.0 Moving in
March
22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31