Professional Documents
Culture Documents
PMP Formulas
PMP Formulas
PMP Formulas
Explanation
IRR
Payback period
Lower is better
BCR
CBR
Program Evaluation and Review Technique is equal to (Pessimistic +(4*Most PERT Likely)+(Optimistic))/6
PV
AC
EV
CV
Cost Variance = EV - AC
SV
Schedule Variance = EV - PV
CPI
EV/AC
SPI
EV/PV
VAC
BAC - EAC
(BAC-EV)/(BAC-AC) Less than 1 is good as it means you can perform at lower efficiency
Cash flow
PV
Sigma values
Activities are nodes and in boxes linked to one another. Has 4 relationships: Finish-start, S-S, F-F, S-F
Arrow diagramming Activity on arrow, only have one relationship, Finish to start. method
1. Achievement 2. Recognition 3. Challenge of the work itself 4. Herzberg's Motivators Responsibility 5. Growth and advancement
1. Expert: Best, you earn it 2. Reward: Ability to reward. Based on your Powers of PMP position 3. Formal: Power given to your position 4. Referent: Referring to others 5. Penalty: Worst, based off ability to punish