12-5-11 Daily Log Report (Reddick Construction) Turner Street
12-5-11 Daily Log Report (Reddick Construction) Turner Street
Project Name : Date : Subcontractor Utility Company Excavation Company Crane Company Holder Turner St. Parking 12/5/2011 Day of Week : (Pick One)
Personnel on Site 4 10 2 2
Safety Protocals Weekly safety walkthroughs, present on all Holder sites, in which the project manager and foremen inspect the site and review potential issues for the week PPE for all employees and visitors on site includes: high visibility vests, hard hats, long pants, gloves and safety glasses for all site Fence set up around the perimeter of the site
Equipment on Site Excavators (with rock breaker) - (1) Crawler Crane - (1) Excavators - (4) Bull Dozers - (4) Caisson Drill - (1) Off Road Dump Trucks (Utes) - (2)
Temperature :
AM PM
40 57