Activities 2011 Feb Mar Apr Crucial issues which affected the project schedule
(Baseline for the project)
31-Dec-11
Base Line
15-Feb-11
Site clearance (porta cabins, plants & A/c units) Re routing of under ground Utilities Carpet floor & Raised floor system Design Changes in Precast Structures CCTV & Access Control System
28 Days Delay
15-Feb-11 14-Mar-11
Physical Execution
14-Mar-11 11-Apr-11
(Electric cables, Q-tel, chiller water, drainage lines and earth pits encountered during the foundation excavation which were not shown in the drawings. Subsequently excavation for footing and other related works delayed ) 24 Days Baseline 6-Apr-11
Execution
14-Mar-11 22-Mar-11
12 Days 17-Apr-11
43 Days Delay
29-May-11 Annexture 1
(Raised flooring material approved from China(60x60) and Floor Carpet from UK/ Nietherland (50x50) were not matching dimensionally. This items has lead delivery time of 8 weeks got finilised on 6-Jul-11)
71 Days Delay
6-Jul-11
24-Sep-11
(Changes in the precast column-beam design due to the under ground utilities as explained above. All the designs got revised many times before final approval & delayed precasting of structures. )
Submission
4-Apr-11 31-Mar-11 6-Apr-11 14-Mar-11 22-Mar-11
19 Days Delay
30-Apr-11 18-May-11 19 Days EExtension 2-Jun-11 Annexture 3 7-Aug-11
(CCTV & Access control system specification not confirmed after repeated submissions. Finally, end user kept these items on hold.)
60 Days Delay
Annexture 4
7-Dec-11
14-Jun-11
25-Dec-11
15-Feb-11
28 Days Delay
85 Days Delay
7-Aug-11
147 Days Delay 79 Days Procurement Baseline 75 Days Procurement Baseline 30-May-11 144 days delay
17-Mar-11 approved in principle
22-Jun-11
Annexture 5
29-Nov-11
36 penal days
24-Oct-11 25-Dec-11
(Due to the changes in the type, model & delay in the approval by end user. Critical activity with lead time for delivery of 16weeks after award of PO.) 17-Mar-11 UPS Relocation of fire fighting water tank & pumps
20-Jun-11
Annexture 6
20-Oct-11
72
Penal Days
6-Dec-11
(Relocation of fire fighting water tanks and pumps to new location is not possible due to area constraints. Alternat proposal submitted by contractor, which were rejected and asked to follow tender drawings. Again works hold during execution of pump foundation on 21-Jul-11)
LEGEND Baseline Schedule Submission & P Approval Client Delays due to Approval Contractor's Delay
Physical Delays due to the Client Combined Delay s Projected completion Date from Approval Date Actual Material Delivery and Physical Execution
Justifiable Extension Period Penal Days liable to by the Contractor Total Penal Days Total Extension Justifiable