ID Task Name Duration Start October 2008 November 2008 December 2008 January 2009 February 2009 March

November 2008 December 2008 January 2009 February 2009 March 2009 April 2009 May 2009
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 3

1 Background Research 25 days Mon 10/6/08


2 HEV Drive Trains 3 days Fri 10/10/08
3 ADVISOR Software 8 days Tue 10/14/08
4 HEV Limitations 5 days Mon 10/6/08
5 Hybrids Cars Efficiency 7 days Mon 10/27/08
6 Optimum System Configuration 4 days Tue 11/4/08
7 Simulation and Analysis 57 days Mon 10/27/08
8 ADVISOR Familiarisation 13 days Mon 10/27/08
9 HEV Bechmark Simulation 3 days Mon 11/10/08
10 Parallel Hybrid Simulation 15 days Tue 11/11/08
11 Series Hybrid Simulation 21 days Mon 1/5/09
12 Interim Report 10 days Fri 11/28/08
13 Report Writing 9 days Fri 11/28/08
14 Submission 1 day Thu 12/11/08
15 Optimisation 31 days Mon 2/2/09
16 Drive Train Optimisation 3 days Mon 2/2/09
17 Limitation Consideration 13 days Thu 2/5/09
18 Result Analysis 7 days Tue 2/24/09
19 Efficiency Determination 3 days Thu 3/5/09
20 Hybrid Optimum Configuration 5 days Tue 3/10/09
21 Further Work 4 days Tue 3/17/09
22 Comparison to Conventional F1 Cars 2 days Tue 3/17/09
23 Real Life Implementation 2 days Thu 3/19/09
24 Final Report 10 days Fri 3/20/09
25 Report Writing 9 days Fri 3/20/09
26 Submission 1 day Thu 4/30/09
27 VIVA 10 days Fri 5/1/09
28 Poster Design 2 days Fri 5/1/09
29 Presentation Preparation 8 days Mon 5/4/09
30 Project VIVA 1 day Thu 5/14/09

Task Milestone External Tasks