COMPLETION OF THREE-STOREY NINE-CLASSROOM BUILDING AT UPPER BICUTAN NATIONAL HIGH SCHOOL

CASH FLOW BY QUARTER AND PAYMENT SCHEDULE


PARTICULAR ACCOMPLISHMENT % WT. 1ST QUARTER 12.45% 2ND QUARTER 38.75% 3RD QUARTER 32.20% 4TH QUARTER 16.60%

CASH FLOW

P 87,084.11

P 271,044.94

P 225,229.60

P 116,112.15

CUMULATIVE ACCOMPLISHMENT

12.45%

51.20%

83.40%

100%

CUMULATIVE CASH FLOW NOTE: Contract Duration =120 C.D.

P 87,084.11

P 358,129.05

P 583,358.65

P 699,470.80

Submitted By:

ROSANNO C. TAGALA (Name of the Representative of the Bidder) OWNER/GENERAL MANAGER R (Position) R.C. TAGALA CONSTRUCTION ; (Name of the Bidder)

Date:

April 27, 2011 ,