Group No. 06
Batch 2006-07
Group Members
Jahanzeb Khan Moiz Ahmed IM-21 IM-22
Usama Rehman
S.M. Abdullah
IM-27
IM-30
MAIN OBJECTIVES
DESIGN PARAMETERS
TEMPRATURE HUMIDITY FILTRATION 24 1.5 C (75 F) 45-60% RH (LOW RH = 20%) 65-90%
FILTRATION
Filters are accommodated in the AHU. Air filtration requirement is 65-90% The filters used are: G4, F6 (before coil) F8 (after coil/discharge) Filters are also applied at the registers/diffusers for higher filtration in rooms.
WORKING PROCEDURE
Data Collection Cooling Load Calculation Air Quantity
Ducting
Air Schematics
Piping
Selection of Equipments
Batch 2006-07 Dept:Industrial and Manufacturing 5
LOAD CALCULATIONS
THE AREA UNDER OBSERVATION IS DIVIDED INTO 5 ZONES.
GROUND FLOOR ZONE ZONE ZONE-1 ROOM # ZONE-3 134, 135, 136, 137 133, 138, 139, 140, ZONE-2 141, 142, 143, 144, 145, 146, 147, 148 ZONE-5 ZONE-4 244, 257, 258, 259, 260 242, 243, 251, 252, 253, 254, 255, 256, 261, 262, 263 250
6
LOAD CALCULATIONS
FLOOR
GROUND FLOOR FIRST FLOOR TOTAL SPACE COOLING LOAD
AIR QUANATITIES
ZONE ZONE 1 ZONE 2 CFM 5610 5265
ZONE 3
ZONE 4 ZONE 5
5055
7355 1500
AIR SCHEMATICS
SINGLE LINE DIAGRAM NORMALLY DESIGNED ON AUTOCAD. DETERMINES THE AIR FLOW DIRECTION AND AIR BALANCING AMONG THE ROOMS. THE LEAKAGE FROM THE DOORS IS 100 CFM SEE REFERENCE # 3 TO 7 FOR AIR SCHEMATIC DIAGRAMS FOR ZONES 1-5
BLOW THRU
Batch 2006-07 Dept:Industrial and Manufacturing
DRAW THRU
10
CONSTRUCTION
ZONE 3
ZONE 4 ZONE 5 Total
17
25.3 5.34 94 TONS
12
SCHEDULE OF AHU
COOLING COIL AHU NO.
SERVICE
UNIT TYPE
S.NO
FAN ESP
FRESH AIR
ENTERING AIR
LEAVING AIR
CAPACI TY
WATER FLOW
IN.WG 1. 1 Supply /Retur n Supply /Retur n Supply /Retur n Supply /Retur n Supply /Retur n Blow Thru Blow Thru Blow Thru Blow Thru Blow Thru Techni cal Area Techni cal Area Techni cal Area Techni cal Area Techni cal Area Grou nd Floor Grou nd Floor First Floor First Floor First Floor 3.9
CFM 5610
CFM 850
oF
DB
oF
WB
oF
DB
oF
WB
MBH 240
83.79
67.91
55
54
USGP M 40
2.
3.9
6565
1300
85.13
69.03
55
54
304
51
3.
3.9
5055
1300
91.41
58.59
55
54
61
10
4.
3.9
7255
2445
95.15
59.6
55
54
110
18
5.
3.9
1500
225
83.74
67.89
55
54
64
13
11
DUCTING
PIPING
ARRANGEMENT
TWO PIPE ARRANGEMENT
SELECTION CRITERIA
Friction per 100 ft
2 to 4 in w.g/100 FT
Velocity
2
3 4 5 Pre cooling
51
34 51 11 68
2.0
2.27 2.0 2.1 3.42
Batch 2006-07 Dept:Industrial and Manufacturing
3.42
3.25 3.42 2.36 4.56
2.5
2 2.5 1.25 2.5
16
SELECTION OF EQUIPMENTS
AIR HANDLING UNIT
AHU AHU-1 AHU-2 AHU-3 AHU-4 AHU-5 PRE-COOLING UNIT MODEL AHD2 AF 064 H M AHD2 AF 080 H M AHD2 AF 064 H M AHD2 AF 080 H M AHD2 BF 022 H M AHD2 NN 040 N N QUANTITY 1 1 1 1 1 1
17
QUANTITY
1
19
CONCLUSION
WE HAVE COVERED THE AIR CONDITIONING FOR NOT ONLY HUMAN COMFORT BUT ALSO EMPHASIZED ON PROCESS. WE HAVE GONE THROUGH THE OVERALL CONCEPT OF AIR CONDITIONING. ON THE BASIS OF OUR STUDY WE RECOMMEND OUR DESIGN TO BE FEASIBLE FROM DESIGN POINT OF VIEW.