1.

Inner BKK Cluster Acceptance DT Schedule: DT Schedule:


Scenario A: Scenario B: 10 to 11-Jan-11 12 to 13-Jan-11 Start time from 11:00 p.m. to 06:00 a.m. (next day morning) Start time from 11:00 p.m. to 06:00 a.m. (next day morning) 14 to 15-Jan-11 (will confirm on Friday)

Spare for some special issue:

DT setup:
Scenario A: MS1 - Voice dual mode (active-120 s, idle-18 s) DC1 - Download 1G x 5 files (same time) (Attach->PDP download->Detach) MS 3 Scanner

Scenario B: MS1 - Voice dual mode (active-120 s, idle-18 s) DC2 - Upload 250 Mbyte x 10 files (same time) (Attach->PDPupload->Detach) MS3 Scanner

2. Outer BKK Cluster Acceptance DT Schedule: DT Schedule / DT setup:


Scenario 1: SAT 18 to SUN 19-Feb-11 Start time from 02:00 a.m. to 06:00 a.m.

MS1 - Voice dual mode (active-120 s, idle-18 s) DC2 - Upload 250 Mbyte x 10 files (same time) (Attach->PDPupload->Detach) MS3 Scanner

MON 18 to TUE 19-Feb-11

Start time from 02:00 a.m. to 06:00 a.m.

MS1 - Voice dual mode (active-120 s, idle-18 s) DC2 - Upload 250 Mbyte x 10 files (same time) (Attach->PDPupload->Detach) MS3 Scanner

**DATE and drivetest route will confirm by tomorrow (17-Feb-12).

Scenario 2:

Start time from 02:00 a.m. to 06:00 a.m.

DC1 - Download 1G x 5 files (same time) (Attach->PDP download->Detach) DC2 (Attach->PDP activation-> deactivation->Detach 1min break) MS 3 Scanner

FTP FileZilla Setting :


1. Edit -> Setting -> FTP -> FTP Keep-alive Send FTP keep-alive commands

2. Edit -> Setting -> Transfer -> Maximum simultaneous transfers (5 files download same time)