Project name
Define
1 Pb Statement
Description of the problem (what? where? since when? based on which data? Based on which facts?) Voice Of Customer (Customer perception) Internal perception Competitors benchmark
2 Goal Statement
Develop Goal statement/opportunity or objective in clear, concise, measurable terms Demonstrate alignment of the project with the company/business strategy
Define
3 Business Case
Why to do the project? What if project not done? Financial Business Case
What Comment Cost
K Project Labor Project Materials Project Contractors Equipment investment Yearly operation cost TOTAL Costs Incremental Revenues Labor Savings Material Savings TOTAL Benefits (1 year)
ROI
Define
4 Project scope
Project: in scope Project: out of scope
5 Team
Customers: Others: Black Belt: Master Black Belt: VP Quality / Quality Manager:
6 Planning
Dates: Gantt
Define
7 (SIPOC)
Supplier = My Company
Input
Step 1
Step 2
Step 3
Output
My Customer
measurement
CTQ*
Definition Specification limit Performance targets
*Critical To Quality
Measure
Selected Project CTQ(s):
Discrete/continuous CTQ?
CTQ Operational Definition(s): What is it (measurement starting point and end point) ?
What is a defect?
Measure
Measurement system analysis
Gage R&R study discrete data: If we have a Known sample (a reference), then how was built the known sample?
Measure
CTQ data collection plan Data sample size = Date of data collection: Where data have been collected? How data have been collected?
Will you take the opportunity to collect obvious Xs when collecting your CTQ measurements? If yes, which Xs: Display an extract of the data collected:
Measure
PROCESS CAPABILITY MEASURE: NORMAL Distribution Observed DPMO= Potential DPMO= ZLT = ZST (ZLT+1.5)= Conclusion Problem with trend, variability or both?
Equable tous droits rservs. Copyrights Equable.
10
Measure
Discrete CTQ Sample size: Short term data or Long term data? Process capability Yield (%)= %defects= DPMO= Opportunities per unit= DPU= Equivalent ZLT= Equivalent ZST (ZLT+1.5)= 95% confidence interval on DPMO:
11
Analyze
Continuous CTQ Normal probability plot:
Conclusion (can we detect a true process and an unstable process?): All type of CTQ Stability over time/Run chart:
Conclusion: Pb of technology (short term common causes)? Pb of control (long term shift due to special causes)? Both pbs?
Equable tous droits rservs. Copyrights Equable.
12
Analyze
Improvement Goal Target (from benchmark) for: Trend: Variability: LT DPMO or LT %defects= Yield (%)= ZLT= ZST=(ZLT+1.5)=
6 Sigma tools necessary to meet performance objectives: Ground fruit: Logic and Intuition Low hanging fruit: Basic tools (Process Map, CE/CNX fishbone diagram, SOP, FMEA, Pareto, Histogram, Box plot) Bulk of Fruit Process Characterization and Optimization Sweet Fruit: Transform the project into a DFSS project
13
Analyze
Process (AS IS) detail analysis: Detailed process map
Conclusion Standard Operation Procedures analysis: Exist: Are applied: Incitation to apply them exist: Training has been given to operators: Policy analysis: Exist Are applied
Equable tous droits rservs. Copyrights Equable.
14
Analyze
List of potential significant Xs
Label C/N/X on your fishbone, then rate every X impact vs implementation (table below)
Fishbone diagram of my Y
Measurements Materials Men
Y/CTQ Output
Environment
Methods
Machines
1 3
2 4
Hard
Equable tous droits rservs. Copyrights Equable.
15
Analyze
Results of segmentation (continuous CTQ only) : (Box plots, Scatter plots, Distributions per X)
Conclusion:
16
Analyze
Pareto chart of the CTQ categories:
Conclusion: FMEA:
Conclusion:
Equable tous droits rservs. Copyrights Equable.
17
Analyze
Statistical Tests Performed
Test one sample or two sample T-test Annova one way Homogeneity of variance Chi square test Simple regression Non parametric data test ANOVA 2 ways GLM DOE screening Conclusion/Prioritized list of significant Xs: X Factors p value
%contribution
conclusion
18
Improve
List of Vital few Xs (screening DOE):
19
Improve
I13
X tolerance settings:
20
Control
C-step 11: Define and Validate Measurement System on Xs (if necessary)
Control on one X (yes/no): If yes, X measurement system analysis:
Data Collection plan for Repeatability & Reproductibility study: Data sample size = Date of data collection: Where data have been collected? How data have been collected? How many operators? How many repeats per operator? Gage R&R study Continuous data: -Tolerance (USL-LSL): -Short method (yes/no):
Nb of distinct categories:
Gage R&R study discrete data: If we have a Known sample (a reference), then how was built the known sample?
21
Control
C-step 12: Determine new Process Capability
Process or Product new capability: Continuous CTQ: NORMAL Distribution Observed DPMO= Potential DPMO= ZLT = ZST (ZLT+1.5)=
Non NORMAL Distribution Observed DPMO= Equivalent ZLT= Equivalent ZST (ZLT+1.5)=
Discrete CTQ: Sample size:= Short term data or Long term data? Process capability Yield (%)= %defects= DPMO= Opportunities per unit= DPU= Equivalent ZLT= Equivalent ZST (ZLT+1.5)= 95% confidence interval on DPMO
22
Control
C-step 13: Implement Process Control
Control Charts (SPC) in place/review mechanisms:
23