11th Street Bridge Project

Community Communications Committee Meeting 10


11th Street Bridge Project Office March 12, 2012

11th Street Community Communications Committee

Agenda:
Memorialize December Meeting Minutes Introduction: Sanjay Kumar, P.E. DDOT Program Manager AWI g g 11th Street Bridge Project Update DC Water M Street Combined Sewer Overflow Office of Planning - 11th Street Recreational Bridge Potential

Total Completed to Date: - $189,681,816 Percentage Complete Over 75%

Construction Progress

South Side

South Side

River Bridges

North Side New Inbound Flyover

Post December 12th Achieved Project Milestones

2 1 3

1. New Inbound Freeway Bridge, December 18, 2011. 2. New Outbound Freeway Bridge, January 07, 2012 3. Re-Opening of 11th Street to MLK, Jr. / Good MLK Jr Hope January 27, 2012.

2012 Upcoming Traffic Milestones

11th Street Local Bridge Interim Condition; Bridge S-1, late spring. 13th Street Bridge Ramp permanently closed; following local 11th St Bridge opening. Southbound DC-295 Ramp to 11th Street Inbound Freeway Bridge; Ramp B-1, mid-summer.
Bridge S-3 Bridge S-2

Outbound 11th Street Freeway Ramp to Northbound DC295; Ramp B-2, early fall. 11th Street Local Bridge access to DC-295

Bridge S-1

Southbound DC 295 ramp to Anacostia/Capitol DC-295 Hill; Ramp C-1, mid-fall. Anacostia/Capitol Hill ramp to Northbound DC295; Ramp C-2, mid-fall. Anacostia/Capitol Hill ramp to Southbound I-295; Ramp C-3, mid-fall. Northbound I-295 ramp to Anacostia/Capitol Hill; Ramp C-4, mid-fall.