Team Leader Project Leader (ITM or above) Programmer QA Engineer CC Change Advisory Board Client Office
Provide Requirements
Propose High Level Design and Project Plan with manpower, system resources & Schedule
Review Design & Project Plan Signoff High Level Design & Project Plan
DD & Prototype QA
Signoff Prototype
System QA
Note: * UAT (User Acceptance Test) is an important process to verify that the system built has met the requirements specified by the client office. It is recommended that a test plan be developed for the task and the result of testing properly documented.