Daily Site Report 02-04-12

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

AAA - RAK, JOINT VENTURE MCB IT Centre, Lahore

Work Report
S.No. 1 2 3 Carpenter Steel Fixer Scaffolder TOTAL Skilled Labour 20 19 38 77 Unskilled Labour Carpenter Helper Steel Fixer Helper Scaffolder Helper TOTAL 11 14 25 Date: 02-04-12

S.No. 1 2 3 4 5 6 7 8

Activity Description Retaining Wall at North Side/West Side/East Side Ramp Columns Stair Basement Slab 5 Formwork Removal Basement Slab 4 Basement Slab 3 Material Shifting/Steel yard/Platform/Pump Line Total

Carpenter 3 2 2 2 2 9 20

Carpenter Helper 2 1 2 2 2 2 11

Scaffolder 7 2 6 4 8 7 4 38

Scaffolder Helper 2 2 2 4 2 2 14

Formwork Total 14 7 0 12 8 16 20 6 83

Steel Fixer 5 3 5 6 19

Equipment
S.No. 1 2 3 4 5 6 7 8 9 10 11 12 Description Transit Mixer 1 Transit Mixer 2 Transit Mixer 3 Tractor with Shovel Tower Crane Batching Plant Generator Generator Generator Bar Bending and Cutting Total Station + Auto Level Concrete Pump SCM 1.5 ton tip load 0.5 m3 50 KVA 150 KVA 200 KVA Model/Capacity Orange 5 m3 Blue 5 m3 2 m3 On-Site 1 1 1 1 1 1 1 1 1 1+1 1+1 1 Remarks

13 14 15 16

Cylinder Testing Machine Roller Compactor Plate Compactor Jumping Jack Compactor

1 -

You might also like