083/day Duration = 1/PN =1/(0.083x4)=3days For activity B Resources used are People=3 Machines=2 Product=t/N Assume t= 8hr N= No of resources=5 P=8/(5x24)=0.083/day Duration = 1/PN =1/(0.067x5)=3days For activity C Resources used are People=4 Instruments=6
Product=t/N Assume t= 10hr N= No of resources=10 P=10/(10x24)=0.042/day Duration = 1/PN =1/(0.042x10)=2days For activity D Resources used are People=5 Instruments=3 Product=t/N Assume t= 6hr N= No of resources=8 P=6/(8x24)=0.031/day Duration = 1/PN =1/(0.031x8)=4days For activity E Resources used are People=6 Instruments=5 Materials=5 Product=t/N Assume t= 5hr N= No of resources=16 P=5/(16x24)=0.013/day
Duration = 1/PN =1/(0.013x16)=5days For activity F Resources used are People=3 Machine=1 Product=t/N Assume t= 9hr N= No of resources=4 P=9/(4x24)=0.093/day Duration = 1/PN =1/(0.093x4)=3days For activity G Resources used are People=6 Instruments=3 Product=t/N Assume t= 4hr N= No of resources=9 P=4/(9x24)=0.0185/day Duration = 1/PN =1/(0.0185x9)=6days For activity H Resources used are People=3
Instruments=3 Materials=4 Product=t/N Assume t= 10hr N= No of resources=10 P=6/(8x24)=0.042/day Duration = 1/PN =1/(0.042x10)=2days For activity I Resources used are People=3 Instruments=3 Materials=3 Product=t/N Assume t= 4hr N= No of resources=9 P=6/(9x24)=0.044/day Duration = 1/PN =1/(0.044x9)=6days
DETERMINATION OF THE EST AND LST ESTj=Max (ESTi+dij) Where i=0N ij=Are start & finish events of an activity
Then; EST1=0 EST2=Max (EST1+d12) =0+3=3 EST3= Max (EST2+d23) or (EST1+d13) =3+2 =5 EST3=5 0+3=3
LSTj=min (LSTj-dij) Where i=0N ij=Are start & finish events of an activity Then; LST6=21 LST5=Min (LST6-d65) =21-6=15 LST4= Min (LST6-d64) or (LST5-d54) =21-2=19 =15-6=9