HVAC PENDING WORK LIST - ARYA VAIDYA SALA PROJECT, KOTTAKAL

SL.NO. ITEM DESCRIPTION REMARKS


Pending Items delivery
1 PVC drain pipe (Local purchase) PVC 1/2in pipe for AHU drain outlet
Pending Installation works
1 Floor mounted AHU - HRW positioning Positioning of HRW is pending .Manpower from Zeco required
3 Pumps Installtion - 3 nos. Pump positioning and erection works are pending .
4 Fresh air Inline fans fixing Ducting manpower required from Firdose ducting systems
5 Ducting mouth connections to Ceiling mounted AHU's - 6 nos. Ducting manpower required
6 Duct droppers fixing in all the rooms - Frame work required by AVS Ducting manpower required
7 Diffusers fixing in all the rooms - False ceiling required by AVS Ducting manpower required
8 RA Grilles fixing in all the rooms - False ceiling required by AVS Ducting manpower required
9 Duct connections to Floor mounted AHU - 1no. Ducting manpower required
11 Balance Duct insulation fixing Ducting manpower required
12 Piping connections to Chillers Subbiah piping persons will complete
13 Piping connections to Pumps Subbiah piping persons will complete
14 Piping connections to AHU Subbiah piping persons will complete
15 Water filling & Piping Pressure testing Subbiah piping persons will complete
16 Pipe Insulation & Aluminium cladding Manpower required
17 Power supply by AVS Clearance required from client
18 Pumps / AHU's commissioning Clearance required from client
19 Water circulation & flushing Clearance required from client , piping persons will complete
20 Fresh water filling Clearance required from client , piping persons will complete
21 Chillers commissioning Clearance required from client , piping persons will complete