The document lists 21 pending HVAC work items for the Arya Vaidya Sala project in Kottakal. Many items require ducting or piping work from external contractors, including positioning equipment, making duct and pipe connections, insulation, and testing. Commissioning of pumps, air handlers, chillers, and bringing the system online requires clearance from the client.
The document lists 21 pending HVAC work items for the Arya Vaidya Sala project in Kottakal. Many items require ducting or piping work from external contractors, including positioning equipment, making duct and pipe connections, insulation, and testing. Commissioning of pumps, air handlers, chillers, and bringing the system online requires clearance from the client.
Copyright:
Attribution Non-Commercial (BY-NC)
Available Formats
Download as XLSX, PDF, TXT or read online from Scribd
The document lists 21 pending HVAC work items for the Arya Vaidya Sala project in Kottakal. Many items require ducting or piping work from external contractors, including positioning equipment, making duct and pipe connections, insulation, and testing. Commissioning of pumps, air handlers, chillers, and bringing the system online requires clearance from the client.
Copyright:
Attribution Non-Commercial (BY-NC)
Available Formats
Download as XLSX, PDF, TXT or read online from Scribd
HVAC PENDING WORK LIST - ARYA VAIDYA SALA PROJECT, KOTTAKAL
SL.NO. ITEM DESCRIPTION REMARKS
Pending Items delivery 1 PVC drain pipe (Local purchase) PVC 1/2in pipe for AHU drain outlet Pending Installation works 1 Floor mounted AHU - HRW positioning Positioning of HRW is pending .Manpower from Zeco required 3 Pumps Installtion - 3 nos. Pump positioning and erection works are pending . 4 Fresh air Inline fans fixing Ducting manpower required from Firdose ducting systems 5 Ducting mouth connections to Ceiling mounted AHU's - 6 nos. Ducting manpower required 6 Duct droppers fixing in all the rooms - Frame work required by AVS Ducting manpower required 7 Diffusers fixing in all the rooms - False ceiling required by AVS Ducting manpower required 8 RA Grilles fixing in all the rooms - False ceiling required by AVS Ducting manpower required 9 Duct connections to Floor mounted AHU - 1no. Ducting manpower required 11 Balance Duct insulation fixing Ducting manpower required 12 Piping connections to Chillers Subbiah piping persons will complete 13 Piping connections to Pumps Subbiah piping persons will complete 14 Piping connections to AHU Subbiah piping persons will complete 15 Water filling & Piping Pressure testing Subbiah piping persons will complete 16 Pipe Insulation & Aluminium cladding Manpower required 17 Power supply by AVS Clearance required from client 18 Pumps / AHU's commissioning Clearance required from client 19 Water circulation & flushing Clearance required from client , piping persons will complete 20 Fresh water filling Clearance required from client , piping persons will complete 21 Chillers commissioning Clearance required from client , piping persons will complete