Philippine PPP Program: PIPELINE OF PROJECTS

Various projects can be financed and implemented via PPPsfrom traditional infrastructure projects such as toll roads, airports, and transport systems; to non-traditional infrastructure such as ICT System and facilities; and social infrastructure like education and health facilities. Currently, there are 21 national projects in the pipeline. The government aims roll out at least 8 of said projects in 2012.

TRANSPORTATION SECTOR
PROJECT PROJECT DESCRIPTION IMPLEMENTING AGENCY
Department of Transportation and Communications (DOTC)/ Light Rail Transit Authority (LRTA)

ESTIMATED COST (USD)


1.41 B

CONTACT PERSONS

LRT Line-1 South Extension

The project involves the operation and maintenance of the existing LRT Line 1; the rehabilitation of existing light rail vehicles (LRVs); the procurement of additional LRV; the construction of the south extension with eight passenger stations, one satellite depot, and three inter-modal facilities; and the subsequent operation and maintenance of the integrated LRT Line 1 system. The proposed alignment has an approximate length of 11.7 km from its tie in point at the terminus of LRT Line 1 at the Baclaran Terminal, to the Niyog Station at Bacoor, Cavite; of which, approximately 10.5 km will be elevated and 1.2 km will be at-grade. The total length of the integrated LRT Line 1 will be approximately 32.4 km.

Mr. Rene K. Limcaoco Undersecretary, DOTC Tel. Number: (632) 725-0204 loc. 247 Atty. Jaime Raphael Feliciano Director, DOTC Tel. Number: (632) 725-0013 Mr. Juan Alberto B. Mercado Project Manager, PPP Center Tel. Number: (632) 990-0721 loc. 6201

LRT Line-2 Operation and Maintenance

The project involves the operation and maintenance of the existing LRT Line-2 and the proposed 4 km extension from Santolan, Pasig to Masinag, Antipolo. The existing 13.8 km Line-2 runs along the Recto South Station in Manila to the Santolan Station in Pasig, traversing Recto Avenue, Magsaysay Boulevard, and the Marcos Highway.

Department of Transportation and Communications (DOTC)/ Light Rail Transit Authority (LRTA)

To be determined (TBD)

Mr. Rene K. Limcaoco Undersecretary, DOTC Tel. Number: (632) 725-0204 loc. 247 Atty. Jaime Raphael Feliciano Director, DOTC Tel. Number: (632) 725-0013 Mr. Juan Alberto B. Mercado Project Manager, PPP Center Tel. Number: (632) 990-0721 loc. 6201

Operation and Maintenance of the Laguindingan Airport

The project involves the operation and maintenance of the entire facilities of the newly constructed internationalstandard airport in Laguindingan, Misamis Oriental.

Department of Transportation and Communications (DOTC)/ Civil Aviation Authority of the Philippines (CAAP)

42.85 M

Mr. Rene K. Limcaoco Undersecretary, DOTC Tel. Number: (632) 725-0204 loc. 247

Atty. Jaime Raphael Feliciano Director, DOTC Tel. Number: (632) 725-0013 Mr. Juan Alberto B. Mercado Project Manager, PPP Center Tel. Number: (632) 990-0721 loc. 6201

New Bohol (Panglao) Airport

The project will involve the construction of an internationalstandard airport to replace the existing Tagbilaran Airport within a 230-hectare spread.

Department of Transportation and Communications (DOTC)

190.47 M

Mr. Rene K. Limcaoco Undersecretary, DOTC Tel. Number: (632) 725-0204 loc. 247 Atty. Jaime Raphael Feliciano Director, DOTC Tel. Number: (632) 725-0013 Ms. Geraldine M. Santos Project Manager, PPP Center Tel. Number: (632) 990-0721 loc. 6203

Mactan Cebu International Airport Passenger Terminal Building

The project envisages complete airport operations with a new worldclass passenger terminal building in MCIA with a capacity of about eight million passengers per year. The project involves the construction of the new passenger terminal, along with all associated infrastructure and facilities; renovation of the existing terminal; installation of all the required equipment, including IT-related infrastructure and other associated facilities; and the operation and maintenance of the two passenger terminals (new and existing) and airside facilities including aprons, runways, taxiways, etc. during the concession/lease period.

Department of Transportation and Communications (DOTC)/ Mactan Cebu International Airport Authority (MCIAA)

241.66 M

Mr. Rene K. Limcaoco Undersecretary, DOTC Tel. Number: (632) 725-0204 loc. 247 Atty. Jaime Raphael Feliciano Director, DOTC Tel. Number: (632) 725-0013 Mr. Johan Martinez Project Manager, PPP Center Tel. Number: (632) 990-0721 loc. 6106

Operation and Maintenance of the Puerto Princesa Airport

The project involves the privatization of the operation and maintenance of the airport. The existing Puerto Princesa Airport will be upgraded and improved into an international gateway meeting the standards of the International Civil Aviation Organization (ICAO).

Department of Transportation and Communications (DOTC)

To be determined (TBD)

Mr. Rene K. Limcaoco Undersecretary, DOTC Tel. Number: (632) 725-0204 loc. 247 Atty. Jaime Raphael Feliciano Director, DOTC Tel. Number: (632) 725-0013 Mr. Juan Alberto B. Mercado Project Manager, PPP Center Tel. Number: (632) 990-0721 loc. 6201

Automatic Fare Collection System

This project is about the decommissioning of the old magnetic-based ticketing system and replacing the same with contactless-based smart card technology on LRT Lines 1 and 2, and MRT-3. The project also aims to introduce a centralized back office that will perform apportionment of revenues.

Department of Transportation and Communications (DOTC)/ Light Rail Transit Authority (LRTA)

42.85 M

Mr. Rene K. Limcaoco Undersecretary, DOTC Tel. Number: (632) 725-0204 loc. 247 Atty. Jaime Raphael Feliciano Director, DOTC Tel. Number: (632) 725-0013 Mr. Johan Martinez Project Manager, PPP Center Tel. Number: (632) 990-0721 loc. 6106

Integrated Transport System (ITS)

The project will establish three mass intermodal terminals at the outskirts of Metro Manilaone in the north (of EDSA) to serve passengers to and from northern Luzon, and two in the south to serve passengers to and from Laguna/Batangas side and those to and from the Cavite side.

Department of Transportation and Communications (DOTC)

To be determined (TBD)

Mr. Rene K. Limcaoco Undersecretary, DOTC Tel. Number: (632) 725-0204 loc. 247 Atty. Jaime Raphael Feliciano Director, DOTC Tel. Number: (632) 725-0013 Mr. Johan Martinez Project Manager, PPP Center Tel. Number: (632) 990-0721 loc. 6106

Cebu Bus Rapid Transit Demonstration Project

The project will restructure the main urban transport corridor from Bulacao to Ayala in Cebu City. This includes a 16-km bus rapid transit (BRT) route designed and built following international best practices and quality standardstwo mixed traffic lanes per direction, integration of the drainage system installed along the restructured corridor, and BRT terminals.

Department of Transportation and Communications (DOTC)

To be determined (TBD)

Mr. Rene K. Limcaoco Undersecretary, DOTC Tel. Number: (632) 725-0204 loc. 247 Atty. Jaime Raphael Feliciano Director, DOTC Tel. Number: (632) 725-0013 Ms. Geraldine M. Santos Project Manager, PPP Center Tel. Number: (632) 990-0721 loc. 6203

ROAD NETWORK SECTOR


PROJECT PROJECT DESCRIPTION IMPLEMENTING AGENCY
Department of Public Works and Highways (DPWH)

ESTIMATED COST (USD)


480.48 M

CONTACT PERSONS

NLEX-SLEX Road Connector

The proposed project involves the construction of a 13.4 km, four-lane elevated expressway over the Philippine National Railway (PNR) right of way which starts at Caloocan City and ends in Buendia, Makati City. The project will connect North Luzon Expressway (NLEX) and South Luzon Expressway (SLEX) to decongest traffic in Metro Manila

Ms. Maria Catalina E. Cabral Assistant Secretary, DPWH Tel. Number: (632) 304-3268 Ms. Rebecca T. Garsuta Director, DPWH Tel. Number: (632) 304-3268 Mr. Juan Alberto Mercado Project Manager, PPP Center Tel. Number: (632) 990-0721 loc.6201

NAIA Expressway Phase II

The project is a four-lane, 7.15 km elevated expressway and 2.22 km at-grade feeder road that will provide access to NAIA Terminals I, II, and III, and link the Skyway and the ManilaCavite Toll Expressway. It starts at the existing Skyway then follows the existing road alignment over Sales Avenue, Domestic Road, and NAIA Road; and has entry/exit ramps at Roxas Boulevard, Macapagal Boulevard, and PAGCOR City.

Department of Public Works and Highways (DPWH)

377.62 M

Ms. Maria Catalina E. Cabral Assistant Secretary, DPWH Tel. Number: (632) 304-3268 Ms. Rebecca T. Garsuta Director, DPWH Tel. Number: (632) 304-3268 Ms. Gladys Ochoa Project Manager, PPP Center Tel. Number: (632) 990-0721 loc. 6101

CALA Expressway (Cavite and Laguna Side)

The project involves the construction and operation of a fourlane, 46.5 km at-grade expressway composed of two sectionsCavite Section (28.4 km) from Manila-CAVITEX in Kawit, Cavite then southwards to Silang/Aguinaldo Highway; and Laguna Section (18.1 km) from Aguinaldo Highway then eastwards to SLEX through Laguna Technopark in Sta. Rosa, Laguna.

Department of Public Works and Highways (DPWH)

468.80 M

Ms. Maria Catalina E. Cabral Assistant Secretary, DPWH Tel. Number: (632) 304-3268 Ms. Rebecca T. Garsuta Director, DPWH Tel. Number: (632) 304-3268 Ms. Gladys Ochoa Project Manager, PPP Center Tel. Number: (632) 990-0721 loc. 6101

WATER SECTOR
PROJECT PROJECT DESCRIPTION IMPLEMENTING AGENCY
Metropolitan Waterworks and Sewerage System (MWSS)

ESTIMATED COST (USD)


595.23 M

CONTACT PERSONS

New Centennial Water Supply Source

The project will involve the construction of a dam, a water treatment plan and an associated main pipeline to deliver water from the project location to Metro Manila. This project will provide water supply security in the metropolis.

Mr. Gerardo Esquivel Administrator, MWSS Tel. Number: (632) 922-3757 Ms. Vangie Dacanay Project Manager, MWSS Tel. Number: (632) 920-5413 Ms. Ma. Cristina Cleofas Project Manager, PPP Center Tel. Number: (632) 990-0721 loc. 6104

Operation and Maintenance of Angat HydroElectric Power Plant (AHEPP) Auxiliary Turbines 4/5

Rehabilitation, operation and maintenance of the MWSSowned auxiliary turbines 4 and 5 installed in Angat HydroElectric Powerplant.

Metropolitan Waterworks and Sewerage System (MWSS)

38.09 M

Mr. Gerardo Esquivel Administrator, MWSS Tel. Number: (632) 922-3757 Mr. Jojo Dorado Project Manager, MWSS Tel. Number: (632) 920-5113 Ms. Ma. Cristina Cleofas Project Manager, PPP Center Tel. Number: (632) 990-0721 loc. 6104

Balara Water Hub

Construction and operationalization of an international center for water excellence located within the MWSS Balara Compound situated along Katipunan Avenue opposite UP Diliman Campus in Quezon City.

Metropolitan Waterworks and Sewerage System (MWSS)

476.19M

Mr. Gerardo Esquivel Administrator, MWSS Tel. Number: (632) 922-3757 Ms. Cecille Bautista Executive Assistant, MWSS Tel. Number: (632) 922-2969 Ms. Ma. Cristina Cleofas Project Manager, PPP Center Tel. Number: (632) 990-0721 loc. 6104

HEALTH SECTOR
PROJECT
Vaccine Self-Sufficiency Project (Phase II)

PROJECT DESCRIPTION
The project is envisioned to accelerate progress in vaccine production in the Philippines, and ensure vaccine sufficiency in the country. VSSP II is expected to reduce overall vaccine procurement costs of finished vaccines through local formulation, filling, labeling, and packaging of the following vaccines: Pentavalent (DPT-HepB-Hib, Diptheria, Pertussis, Tetanus-Hepatitis B and Hemphylus Influenza B), Tetanus Toxoid (TT), Single HepB.

IMPLEMENTING AGENCY
Department of Health (DOH)

ESTIMATED COST (USD)


11.29 M

CONTACT PERSONS
Mr. Teodoro Herbosa Undersecretary, DOH Tel. Number: (632) 711-6075 Dr. Remigio Olveda Department of Health Tel. Number: (632) 809-7599 Ms. Jan Irish Villegas Project Manager, PPP Center Tel. Number: (632) 990-0721 loc. 6105

Modernization of the Philippine Orthopedic Center

Construction and upgrade of hospital buildings and facilities purchase and supply of modern hospital equipment, furniture and fixtures and the installation of a comprehensive hospital IT system.

Department of Health (DOH)

128.31 M

Mr. Teodoro Herbosa Undersecretary, DOH Tel. Number: (632) 711-6075 Dr. Remigio Olveda Department of Health Tel. Number: (632) 809-7599 Ms. Jan Irish Villegas Project Manager, PPP Center Tel. Number: (632) 990-0721 loc. 6105

EDUCATION SECTOR
PROJECT PROJECT DESCRIPTION IMPLEMENTING AGENCY
Department of Education (DepEd)

ESTIMATED COST (USD)


239.05 M

CONTACT PERSONS

PPP for School Infrastructure Project

The project will involve the design, financing and construction of about 9,300 one storey and two-storey classrooms, including furniture and fixtures, in various sites in Regions I, III, & IV-A. The project aims to supplement the current program of the Department of Education in reducing classroom backlog.

Mr. Francis Varela Undersecretary, DepEd Tel. Number: (632) 633-9342 Mr. Mark Nimeno Project Manager, PPP Center Tel. Number: (632) 990-0721 loc. 6105

AGRICULTURE SECTOR
PROJECT PROJECT DESCRIPTION IMPLEMENTING AGENCY
Department of Agriculture (DA)

ESTIMATED COST (USD)


29.76 M

CONTACT PERSONS

Grains Central Project

The project will establish grains bulk handling systems with corn grains processing centers and transshipment stations in major corn producing areas and selected sea ports by upgrading, expanding and enhancing the existing operations in at least fifteen (15) corn postharvest processing and trading centers.

Mr. Antonio Fleta Undersecretary, DA Tel. Number: (632) 920-4085 Ms. Zenaida Villegas Project Development Service, DA Tel. Number: (632) 920-1407 Ms. Jan Irish Villegas Project Manager, PPP Center Tel. Number: (632) 990-0721 loc. 6105

Establishment of Cold Chain Systems Covering Strategic Areas in the Philippines

Construction and operationalization of Cold Chain Centers to be located in major production and consolidation areas of agri-fishery products. The Centers will be equipped with the required facilities and machineries for minimal processing of livestock, fisheries and high value crops.

Department of Agriculture (DA)

121.19 M

Mr. Antonio Fleta Undersecretary, DA Tel. Number: (632) 920-4085 Ms. Zenaida Villegas Project Development Service, DA Tel. Number: (632) 920-1407 Ms. Jan Irish Villegas Project Manager, PPP Center Tel. Number: (632) 990-0721 loc. 6105

Logistics Support on the Agri-fishery Products Supply Chain: Transportation of Agrifishery Products Utilizing the South Rail Main Line

The project will involve the (i) development of railway infrastructure (procurement of train locomotives, wagons, flatbeds, container vans) and (ii) establishment of consolidation centers, transport and storage facilities (construction of consolidation centers and loading/unloading terminals in selected project sites near train stations and rehabilitation of train cargo stations and warehouses equipped with cold rooms/storages, refrigerated transport and other equipment).

Department of Agriculture (DA)

34.9 M

Mr. Antonio Fleta Undersecretary, DA Tel. Number: (632) 920-4085 Ms. Zenaida Villegas Project Development Service, DA Tel. Number: (632) 920-1407 Ms. Jan Irish Villegas Project Manager, PPP Center Tel. Number: (632) 990-0721 loc. 6105