Statement of Work
08/25/2011
Version 5.0
Page 1
Contents
1.0 1.1 2.0 2.1 3.0 3.1 Introduction / Purpose...................................................................................................... 10 Avenues Site Review ................................................................................................................... 10 Functional Scope ................................................................................................................... 12 Concept of Operations ................................................................................................................ 13 Project Phases and Timeline .................................................................................................. 14 Project Phases ............................................................................................................................. 15 Phase #2: SRS Avenues Implementation......................................................................... 15 Project Management ...................................................................................................... 15 Business........................................................................................................................... 15 Technical Architecture and Infrastructure ...................................................................... 16 Content Management ..................................................................................................... 16 Document Conversion..................................................................................................... 16 Eligibility and Benefits Administration System ............................................................... 17 Business Intelligence Services and Reporting ................................................................. 17 Phase #3: LIEAP .................................................................................................................. 17 Ongoing Operations ............................................................................................................ 17 Phase #4: Virtual Contact Center ....................................................................................... 17
3.1.1 3.1.1.1 3.1.1.2 3.1.1.3 3.1.1.4 3.1.1.5 3.1.1.6 3.1.1.7 3.1.2 3.1.3 3.1.4 4.0 4.1 4.2 4.3 4.4 4.5 5.0 6.0 6.1 6.2 6.3 6.4
Project Staffing ..................................................................................................................... 19 Accenture .................................................................................................................................... 20 State ............................................................................................................................................ 23 Organization Chart ...................................................................................................................... 25 Key Personnel.............................................................................................................................. 26 Skill Sets for the SRS project ....................................................................................................... 29 Deliverable Schedule............................................................................................................. 32 Project Management and Project Administrative Services ...................................................... 36 KITO Requirements ..................................................................................................................... 36 Internal Reporting Requirements ............................................................................................... 37 Project Time Reporting and Cost Allocation ............................................................................... 38 Project Execution Tools............................................................................................................... 38 Page 2
Version 5.0
Documentation of Meetings and Decisions ................................................................................ 39 Risk and Issues Management ...................................................................................................... 39 Deliverables................................................................................................................................. 39 Governance, Change Control Process and Acceptance of Deliverables ..................................... 40 Governance ......................................................................................................................... 40 Change Control Process ...................................................................................................... 41
6.8.1 6.8.2
7.0 Requirements Validation, Business Process Design, Software Configuration, Testing, and Enhancements & Modifications ........................................................................................................ 47 7.1 7.2 8.0 8.1 8.2 Responsibility Matrix .................................................................................................................. 49 Deliverables and Work Products................................................................................................. 49 Workflow Analysis and Development .................................................................................... 51 Scope Definition .......................................................................................................................... 51 Major Activities by Phase ............................................................................................................ 56 Analyze Phase ..................................................................................................................... 56 Analyze Process Flows..................................................................................................... 56 Design Phase ....................................................................................................................... 57 General Design Documents............................................................................................. 57 Build Phase .......................................................................................................................... 58 Detailed Design Documents ............................................................................................ 58 Build and Component Test.............................................................................................. 58 Test Phase ........................................................................................................................... 58 Deploy Phase....................................................................................................................... 58
8.2.1 8.2.1.1 8.2.2 8.2.2.1 8.2.3 8.2.3.1 8.2.3.2 8.2.4 8.2.5 8.3 8.4 9.0 9.1
Responsibility Matrix .................................................................................................................. 60 Deliverables and Work Products................................................................................................. 61 Interfaces ............................................................................................................................. 62 Scope Definition .......................................................................................................................... 62 Interfaces In Scope .............................................................................................................. 63 Interfaces Not In Scope ....................................................................................................... 65
Major Activities by Phase ............................................................................................................ 66 Analyze Phase ..................................................................................................................... 66 Design Phase ....................................................................................................................... 67 Build Phase .......................................................................................................................... 68 Page 3
Responsibilities ........................................................................................................................... 69 Other Interface Considerations .................................................................................................. 70 Deliverables................................................................................................................................. 70 Data Conversion ................................................................................................................... 71 Scope Definition .......................................................................................................................... 71 Major Activities by Phase ............................................................................................................ 71 Analyze Phase ..................................................................................................................... 71
10.2.1
10.2.1.1 Conversion Analysis ........................................................................................................ 71 10.2.2 10.2.3 Design Phase ....................................................................................................................... 73 Build Phase .......................................................................................................................... 74
10.2.3.1 Build and Component Test:............................................................................................. 74 10.2.4 10.2.5 Test Phase ........................................................................................................................... 74 Deploy Phase....................................................................................................................... 74
10.2.5.1 Mock Conversions: .......................................................................................................... 74 10.2.5.2 Cutover:........................................................................................................................... 75 10.3 10.4 11.0 11.1 11.2 Responsibility Matrix .................................................................................................................. 76 Deliverables................................................................................................................................. 77 Business Intelligence Services and Reporting ......................................................................... 78 Scope Definition .......................................................................................................................... 78 Major Activities by System Development Methodology Phase .................................................. 79 Analyze Phase ..................................................................................................................... 79
11.2.1
11.2.2.1 General Design Documents: ........................................................................................... 80 11.2.2.2 Detailed Design Documents ............................................................................................ 80 11.2.3 Build Phase .......................................................................................................................... 80
11.2.3.1 Build and Component Test.............................................................................................. 80 11.2.4 11.2.5 11.3 Version 5.0 Test Phase ........................................................................................................................... 81 Deploy Phase....................................................................................................................... 81 Page 4
11.4
Deliverables and Work Products................................................................................................. 82 Automated Forms and Notices .............................................................................................. 83 Scope Definition .......................................................................................................................... 84 Major Activities by Phase ............................................................................................................ 92 Analyze Phase ..................................................................................................................... 92
12.2.1
12.2.1.1 Analyze Forms and Notices ............................................................................................. 92 12.2.2 12.2.3 Design Phase ....................................................................................................................... 92 Build Phase .......................................................................................................................... 93
12.2.3.1 Build and Component Test.............................................................................................. 93 12.2.4 12.2.5 12.3 12.4 13.0 13.1 13.2 14.0 14.1 Test Phase ........................................................................................................................... 94 Section 7 of the K-MED SOW Deploy Phase ....................................................................... 94
Responsibility Matrix .................................................................................................................. 94 Deliverables and Work Products................................................................................................. 94 Imaging and Content Management ....................................................................................... 96 Scope Definition .......................................................................................................................... 96 Deliverables and Work Products ................................................................................................ 96 Enterprise Readiness ............................................................................................................. 97 Major Activities by Phase ............................................................................................................ 97 Analyze Phase ..................................................................................................................... 97
14.1.1
14.1.1.1 Develop the Stakeholder Assessment and Stakeholder Management Plan................... 97 14.1.1.2 Create Enterprise Readiness Plan ................................................................................... 98 14.1.1.3 Create Communication Plan ........................................................................................... 98 14.1.2 Design Phase ....................................................................................................................... 99
14.1.2.1 Support Road Shows ....................................................................................................... 99 14.1.2.2 Launch Change Agent Network and Regional Implementation Leads............................ 99 14.1.2.3 Document System, Process and Role Gaps ................................................................... 100 14.1.2.4 Design Change Discussion Guides/Readiness (Business Process) Workshops ............. 100 14.1.2.5 Provide Communications /Update Communication Plan ............................................. 101 14.1.3 Version 5.0 Build Phase ........................................................................................................................ 105 Page 5
14.1.3.1 Build Change Discussion Guides/ Readiness (Business Process) Workshops ............... 105 14.1.3.2 Create Role Descriptions ............................................................................................... 106 14.1.3.3 Provide Communications / Update Communication Plan ............................................ 106 14.1.3.4 Assess and Report Readiness ........................................................................................ 106 14.1.4 14.1.5 Test Phase ......................................................................................................................... 109 Deploy Phase..................................................................................................................... 109
14.1.5.1 Assess and Report Readiness ........................................................................................ 109 14.1.5.2 Provide Communications / Update Communication Plan ............................................ 109 14.2 14.3 14.4 15.0 15.1 Responsibility Matrix ................................................................................................................ 110 Other Requirements ................................................................................................................. 110 Deliverables............................................................................................................................... 110 Training Services ................................................................................................................. 112 Major Activities by Phase .......................................................................................................... 112 Analyze Phase ................................................................................................................... 112
15.1.1
15.1.1.1 Analyze End User Training and Support Needs............................................................. 112 15.1.1.2 Training Curriculum....................................................................................................... 113 15.1.2 Design Phase ..................................................................................................................... 115
15.1.2.1 Training Tools Training .................................................................................................. 115 15.1.2.2 Training Design.............................................................................................................. 115 15.1.3 Build Phase ........................................................................................................................ 116
15.1.3.1 Build .............................................................................................................................. 116 15.1.3.2 Test ................................................................................................................................ 118 15.1.4 Deploy Phase..................................................................................................................... 118
15.1.4.1 Pilot Training ................................................................................................................. 118 15.1.4.2 Train-the-Trainer ........................................................................................................... 119 15.1.4.3 Training Facilities........................................................................................................... 120 15.1.4.4 Training Delivery ........................................................................................................... 120 15.1.4.5 Training Administration ................................................................................................ 121 15.1.4.6 Training Transition ........................................................................................................ 122 15.2 15.3 15.4 Responsibility Matrix ................................................................................................................ 123 Other Requirements ................................................................................................................. 123 Deliverables............................................................................................................................... 123 Page 6
Version 5.0
Knowledge Transfer Services ............................................................................................... 124 Scope Definition ........................................................................................................................ 124 Major Activities by Phase .......................................................................................................... 124 Analyze Phase ................................................................................................................... 124
16.2.1
16.2.1.1 Identify Roles ................................................................................................................ 124 16.2.1.2 Knowledge Transfer Plan .............................................................................................. 125 16.2.2 Design Phase ..................................................................................................................... 126
16.2.2.1 Personal Learning Plans ................................................................................................ 126 16.2.2.2 Assess Knowledge Transfer Progress ............................................................................ 127 16.2.2.3 Design Small Group Walkthrough sessions................................................................... 127 16.2.3 16.2.4 16.2.5 16.2.6 Build Phase ........................................................................................................................ 128 Test Phase ......................................................................................................................... 128 Deploy Phase..................................................................................................................... 129 Post Systems Support Phase ............................................................................................. 130
16.2.6.1 Assess Knowledge Transfer Progress Post Systems Support ..................................... 130 16.3 16.4 16.5 17.0 17.1 17.2 17.3 18.0 18.1 18.2 18.3 19.0 20.0 21.0 21.1 21.2 Responsibility Matrix ................................................................................................................ 130 Other Requirements ................................................................................................................. 130 Deliverables............................................................................................................................... 131 Technical Infrastructure Build and Operations ..................................................................... 132 Major Activities ......................................................................................................................... 132 Responsibility Matrix ................................................................................................................ 133 Deliverables............................................................................................................................... 135 SRS Quality Assurance......................................................................................................... 137 Major Activities ......................................................................................................................... 137 Responsibility Matrix ................................................................................................................ 138 Deliverables and Work Products............................................................................................... 138 508 Compliance .................................................................................................................. 140 Help Desk ........................................................................................................................... 141 Continuity of Operations and Disaster Recovery .................................................................. 142 Scope Definition ........................................................................................................................ 142 Responsibility Matrix ................................................................................................................ 143 Page 7
Version 5.0
Deliverables and Work Products............................................................................................... 143 Ongoing Operations ............................................................................................................ 145 Major Activities ......................................................................................................................... 145 Knowledge Transfer .......................................................................................................... 145 Enhancements................................................................................................................... 146
22.1.1 22.1.2 22.2 22.3 23.0 23.1 23.2 24.0 24.1 25.0 25.1
Responsibility Matrix ................................................................................................................ 147 Deliverables............................................................................................................................... 147 Print Mail ........................................................................................................................... 148 Responsibility Matrix ................................................................................................................ 149 Deliverables............................................................................................................................... 149 Post-Implementation Support ............................................................................................. 150 Major Activities by Phase .......................................................................................................... 151 Archiving (KEEP).................................................................................................................. 152 Analyze Phase ........................................................................................................................... 152 Analyze KEEP Requirements ............................................................................................. 152
Responsibility Matrix ................................................................................................................ 153 Other Considerations ................................................................................................................ 154 Deliverables and Work Products............................................................................................... 154 Virtual Contact Center......................................................................................................... 155 Major Activities by Phase .......................................................................................................... 159 Analysis ............................................................................................................................. 159
26.1.1
26.1.1.1 Virtual Contact Center Analysis .................................................................................... 159 26.1.2 26.1.3 Design Phase ..................................................................................................................... 161 Build Phase ........................................................................................................................ 162
26.1.3.1 Detailed Design Documents .......................................................................................... 162 26.1.3.2 Build and Component Test............................................................................................ 162 26.1.4 Test Phase ......................................................................................................................... 163
26.1.4.1 VCC IVR Testing ............................................................................................................. 163 26.1.4.2 Telephony / ACD Testing ............................................................................................... 164 26.1.5 Version 5.0 Deploy Phase..................................................................................................................... 165 Page 8
26.1.5.2 Telephony /ACD deployment ........................................................................................ 166 26.2 26.3 Other Requirements ................................................................................................................. 167 Deliverables............................................................................................................................... 167
27.0 Business Process Reengineering (BPR) and Business Process Improvement (BPI) Change Management ................................................................................................................................. 168 27.1 Business Process Reengineering and Business Process Improvement ..................................... 168 Perform Business Process Reengineering (BPR)/Business Process Improvement (BPI) ... 168 Business Activities and Tasks ............................................................................................ 169
Version 5.0
Page 9
1.0
Introduction / Purpose
The purpose of this SRS Statement of Work (SOW) is to document and formalize the decisions made and agreements reached during K-MED/Avenues contract negotiations. The SOW supplements the contract by providing required clarity to specific areas of the Contractors proposal. It particularly documents any item that is different from the States RFP, States RRO or the Contractors proposals. The SOW does not substitute for, nor necessarily nullify, any commitments or approaches described in the Contractors proposal or other Contractor commitments made during the procurement process. If the SOW is silent on a given item or approach, then these other documents and Contractor commitments are in full force. The SOW defines the Project phases and releases. The SOW defines requirements for project controls and project administration, including the change control process. It lists all deliverables and provides a brief description of each deliverable. The SOW identifies which party is responsible for specific Project activities. The SOW includes proposed Contractor and State staffing. The SRS SOW is an incremental work effort to the K-MED SOW and should be viewed as the work necessary to be done that is in addition to the K-MED SOW. Any consideration of the SRS SOW must include the K-MED SOW for a complete picture of the project. In many instances the SRS SOW will refer to the K-MED SOW.
1.1
The Contractor will provide a Demonstration and Training session of the K-MED/Avenues Vendors proposed system at the central development site located in San Antonio, Texas. The expectations of the session are: See a demonstration of the proposed solution and all technical aspects that support it. See a presentation and walk thru of the development center processes, procedures, standards, and guidelines for product maintenance and enhancement. Receive training in the solution architecture and practices.
The scheduled time and agenda will be determined and agreed upon by both the State and Contractor during detailed project planning. The Contractor shall be responsible for all the travel and lodging expenses, for up to 10 State agency staff to attend the session. The State will be represented by a team consisting of developer, software administration, analyst, and business staff. All travel and expense arrangements shall fully comply with the terms of K.S.A. 46-237 and travel arrangements are compliant with the State of Kansas Travel Policies, found at: http://da.state.ks.us/ar/employee/travel/.
Version 5.0
Page 10
The State team will arrive in San Antonio on the day before the session is to begin and depart from the location at the conclusion of the session. It is expected that the session will not exceed two days. The Contractor will provide the airfare and lodging arrangements for the State staff specified. The billing for these accommodations will go directly to the Contractor from the travel companies. Coverage of ground transportation will be arranged in the planning of the trip. It is expected that the State will cover the meal expenses for the staff attending.
Version 5.0
Page 11
2.0
Functional Scope
The Avenues project will implement the next generation of integrated eligibility and benefits administration information management systems that will include an Integrated Service Delivery model to better serve Kansans. Integrated service delivery that is focused on the client will require improvements to the current SRS business processes and the underlying information technology that supports them. The scope of the Avenues project is extensive and is summarized as follows. Replacement of the following legacy systems: KAECSES-AE Kan-Pay KsCares EATSS TOP LIEAP systems
As part of the project, all functionality and data from these systems will be incorporated into the new system, per the functional and conversion design, and these will be decommissioned. The following programs are in scope for Avenues: Temporary Assistance for Needy Families (TANF) SNAP (Food Assistance) Refugee Assistance General Assistance Funeral Assistance Work Programs (Includes both TANF and Food Assistance Employment & Training) Child Care Subsidy (Includes customer eligibility, benefits, and provider enrollment) Low Income Energy Assistance (LIEAP)
Version 5.0
Page 12
The following Children and Family Services programs are for payment or emergency payments only. Adoption Support Subsidy Permanent Custodianship Independent Living (Chaffee) Generic Family Services
Implementation of the new Eligibility and Benefits Administration System (Avenues). This will include all aspects of implementing a new system, such as conversion, interfaces, new business processes, and users trained in the use of the system. SRS will have the ability to consolidate service delivery, perform integrated case management, and eliminate redundant and inefficient processes. Establishment of the appropriate communication and change management methods and structure. Establishment of the core technical infrastructure to support the solution. Business Process Reengineering/Improvements. Staff business processes will be reengineered for more efficiency in meeting customer needs and use of the new solution. Implementation of a Virtual Contact Center. This will implement a new unit and the necessary system functionality to provide statewide customer support using phone and internet service channels, regardless of the staff location. Establishment of a Content Management solution that is integrated with the eligibility system. This will include the hardware, software, infrastructure, processes, rollout, and support for the establishment of a Records Management Center, in accordance with the SOW and Avenues requirements. Implementation of a new organizational structure for programs supported by Avenues. Any new organizational structures will be implemented and staff assigned to new duties.
2.1
Concept of Operations
The SRS future vision model shares many concepts of the K-MED vision. The K-MED vision provides the base for SRS with incremental aspects pertaining to the SRS program service delivery. The SRS Concept of Operations document (see Appendix) provides a description of the SRS current environment and the future vision of operations.
Version 5.0
Page 13
3.0
Deliverable/Scope
Phase 1 involves K-MED scope only. SRS work begins with Phase 2. Project Management, Business Process Reengineering/Improvement, Technical Architecture and Infrastructure, Content Management (including Document Conversion), Eligibility and Benefits Administration System, and Business Intelligence Services LIEAP Virtual Contact Center
Deployment Date
NA Month 21
Phase 3 Phase 4
Month 28 Month 31
The following chart represents the Avenues Timeline. The integrated Project Plan will contain the aligned workplan with K-MED, which will coordinate the implementation of phases.
Version 5.0
Page 14
3.1
3.1.1
Project Phases
Phase #2: SRS Avenues Implementation
Listed below are the high-level work efforts that are In Scope for Phase 2. This phase includes the following: Project Management, Business Process Reengineering/Improvement, Technical Architecture and Infrastructure, Content Management (including Document Conversion), Eligibility and Benefits Administration System, and Business Intelligence Services. It should be noted that Phase 1, which is not scope within the SRS Avenues Implementation, is K-MED scope associated with the Self Screening Portal and Presumptive Eligibility.
3.1.1.1
Project Management
Project Management will include planning, controlling, and reporting the work; identifying, tracking, and resolving problems and issues; and leading the project in cooperation with the States Project Director and staff. Other activities would include conducting project initiation, arranging and conducting status meetings, managing the quality reviews, and developing and implementing the issue and risk management programs. Accenture will work to maintain a cooperative working relationship with State staff and the States Independent Validation and Verification Vendor (IV&V) on an ongoing daily basis to design, develop, implement, maintain, and operate a system that meets the required specifications. Our approach to performing the activities surrounding Project Management involves leveraging the PMO established by the K-MED project and adding additional focus on quality. Our Project Manager is supported by a PMO Lead focused on working with your PMO and IV&V to track quality metrics and overall team performance.
3.1.1.2
Business
Business activities and tasks are necessary to plan and prepare for SRS deployment of change management staff. We are using the broad term Change Management to include the activities of Business Process Reengineering, Business Process Improvement, as well as the plans, communications and activities necessary to get your staff ready for the new processes that accompany the integrated KMED and Avenues System. Perform Business Process Reengineering (BPR)/Business Process Improvement (BPI) Using a six-step method to conducting business process improvements for the Avenues project, Accenture will provide the appropriate staff with Business Process Improvement expertise (during the initial window in the project) to research, evaluate, and identify new business processes. Accenture will provide a staff person familiar with the proposed eligibility system to work with this team in: helping to identify a plan of implementation of the new business processes. Page 15
Version 5.0
working with SRS to establish and maintain a model business process office. aiding the state in the rollout of these new processes, training, education, and any other aspects of successfully transitioning the organization to the new business processes.
3.1.1.3
The Technical Architecture and Infrastructure activities are intended to extend the K-MED architecture and scale it appropriately for the increased caseloads of Avenues. They will include the activities and tasks to deploy the infrastructure, equipment, and software for the integrated K-MED/ Avenues system. These tasks would follow a methodology that includes the processes necessary to analyze the equipment and software requirements, development of the software and equipment, development and implementation of the security, management of the procurement process for hardware and software, as well as the technical architecture support to design, build, test and deploy K-MED/Avenues. Our approach to performing the activities surrounding the Technical Architecture and Infrastructure activities involves leveraging the technical teams and resources that already exist for the K-MED project. The Tech Arch resources assigned to Avenues will be focused on adapting the architecture and infrastructure to SRS needs rather than starting from scratch.
3.1.1.4
Content Management
Accentures Content Management solution will be to build on capabilities in the existing APSP to provide a more robust solution supporting cohesive integration with the APSP Portal application and enhanced workflow capabilities. The solution will allow the State to scan documents and process images electronically. It will give SRS users the ability to store and retrieve case related documents electronically, and view the stored images online from within the Avenues System. Accentures approach to performing the activities surrounding Content Management involves leveraging the deep expertise of our teaming partner, Perceptive. Based in Kansas and experienced with public sector ECM implementations, Perceptive is well equipped to rapidly develop and deploy the standalone imaging solution. We will work with our Perceptive partners to integrate the interim solution into the Eligibility and Web Portal systems. At that point, all appropriate Avenues users will be able to benefit from ongoing ECM capabilities.
3.1.1.5
Document Conversion
Historically scanned and imaged documents (i.e., content) will be converted from the legacy system to the SRS Avenues solution by an external contractor and is not part of the Accenture scope. Accenture will, however, provide the correct file format to the external vendor so the historical documents can easily be consumed/converted by the Image now, and put the Client on a server, a desktop, or both based on what works best for the document conversion work effort.
Version 5.0
Page 16
3.1.1.6
Eligibility and Benefits Administration includes the incremental modifications to the K-MED solution to meet the Avenues functional, technical, conversion and interface requirements. Our approach to performing the activities surrounding Eligibility System and Web Portal involves leveraging the large development team that exists for the K-MED project while enhancing it with additional functional and technical resources. Accenture will add developers focused on development of the Eligibility System, Interfaces, Data Conversion as well as System Testing and Training so that the Avenues project is well represented in the combined team.
3.1.1.7
Business Intelligence Services and Reporting involves the activities and tasks necessary to implement the K-MED Business Intelligence Services architecture for the Avenues Project for use by SRS decision makers. As we perform the Design for Avenues, we will confirm that adequate storage for the incremental case load increase for SRS cases has been defined in the plan. The modifications to the KMED Business Intelligence Services design will primarily be driven by the programmatic changes for the SRS-specific programs. Our approach to performing the activities surrounding Business Intelligence Services and Reporting involves leveraging the reporting capabilities of the K-MED team with additional resources from Accenture Analytics and our San Antonio Development Center. In this way, we will make use of existing skills and capabilities while bringing additional Business Intelligence Services and Reporting experience.
3.1.2
Phase 3 will include the implementation of the Low Income Energy Assistance Program (LIEAP). This implementation will help eligible households pay for a portion of their home energy costs by providing an annual benefit. The solution will consist of registering clients, determining a clients eligibility and benefit amount, processing a payment, as well as maintaining and updating information about vendors.
3.1.3
Ongoing Operations
Accenture will provide resources dedicated to Knowledge Transfer, Enhancements, and Help Desk for a period of 12 months after the Implementation of the SRS Avenues application. At the conclusion of the Ongoing Operations phase SRS staff will have the knowledge and hands on expertise to manage and support future enhancement work without the guidance of Accenture resources.
3.1.4
The Virtual Contact Center (VCC) work effort will establish the tools, technologies, organizational structure, role definitions, and physical structure necessary to allow the SRS to improve customer service through a consolidated statewide Virtual Contact Center. Customers contacting the agency will Version 5.0 Page 17
be routed through this Virtual Contact Center in order to improve response times, customer satisfaction and improve workforce efficiency.
Version 5.0
Page 18
4.0
Project Staffing
The Project Staffing SOW is intended to identify the Contractor and State resources needed to implement the SRS Avenues Solution. Accenture and SRS staff will work together to complete General and Detailed Design documentation, Build and Unit Test (i.e., pages, database updates, interface, reports, forms, batch, etc.), System Test, and Deployment of the required work products, Deliverables, and Application Components to successfully implement the benefits system. By the very nature of integrating SRS staff with Accenture resources SRS will learn how to maintain and enhance the system. Accenture will also be leveraging the Accenture resources assigned to the K-MED project in an effort to maximize the team productivity between the two projects.
Version 5.0
Page 19
4.1
Accenture
Team Table 1 - Accenture Staffing Table Role Resource Name Location Roll On Month
M1 M1 M1 M4 M4 M5 M4 M6 M6 M13 M1 M3 M3 M1 M1 M1 M1 M1 M1 M2 M6 M4 M5
Total Months
4 21 21 18 13 1 13 15 13 7 21 15 19 10 5 3 15 21 15 20 16 18 17
Project Management Project Management Project Management Change Management Change Management Change Management Change Management Change Management Change Management Change Management Technical Architecture Technical Architecture Technical Architecture Tech. Arch. - Content Management Tech. Arch. - Content Management Tech. Arch. - Content Management Tech. Arch. - Content Management Eligibility System Eligibility System Eligibility System Eligibility System Eligibility System - Conversion Eligibility System - Conversion
Avenues Account Lead* Avenues Project Manager PMO Manager Change Management Project Manager* Business Process Reengineering Lead Business Analyst Lead Business Analyst Training Developer Training Developer Training Developer Technical Architecture and Install Infrastructure Manager* System Architect Database Administrator Content Management Manager* Imaging/Content Management Developer Imaging/Content Management Developer Imaging/Content Management Developer Eligibility and Benefits Administration System Manager* Business Functional Manager/Testing Application Developers Application Developers Application Developer Conversion Application Developer Conversion
Debora Morris Keith Salas TBD Robin Murphy TBD TBD TBD TBD TBD TBD Mel Pieper TBD TBD Kristen Parker TBD TBD TBD Jerry Nielson TBD TBD TBD TBD TBD
Topeka Topeka Topeka Topeka Topeka Topeka Topeka Topeka Topeka Topeka Topeka Topeka Topeka Topeka Topeka Topeka Topeka Topeka Topeka Topeka SADC Topeka SADC
Version 5.0
Page 20
Team
Role
Resource Name
Location
Roll On Month
M6 M6 M7 M5 M6 M24 M26 M26 M21 M13 M13 M4 M4 M4 M4 M7 M12 M7 M7 M7
Total Months
13 6 14 20 22 8 6 6 3 9 9 9 3 3 3 9 12 19 6 6
Eligibility System - Interfaces Eligibility System - Interfaces Eligibility System - Interfaces Eligibility System Eligibility System Virtual Contact Center Virtual Contact Center Virtual Contact Center Virtual Contact Center Business Intelligence Services and Reporting Business Intelligence Services and Reporting Business Intelligence Services and Reporting Business Intelligence Services and Reporting Business Intelligence Services and Reporting Business Intelligence Services and Reporting Business Intelligence Services and Reporting Business Intelligence Services and Reporting Business Intelligence Services and Reporting Business Intelligence Services and Reporting Business Intelligence Services and
Application Developer Interfaces Application Developer Interfaces Application Developer Interfaces Application Developer Forms Application Developer Forms Virtual Contact Center Project Manager* IVR/CRM Developer IVR/CRM Developer IVR/CRM Developer Business Intelligence Services and Reporting Project Manager* Reports Lead Application Developer Reports Application Developer Reports Application Developer Reports Application Developer Reports Application Developer Reports Application Developer Reports Application Developer Reports Application Developer Reports Application Developer Reports
TBD TBD TBD TBD TBD David Corey TBD TBD TBD Anthony Perez TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD
SADC Topeka Topeka Topeka Topeka Topeka Topeka Topeka Topeka Topeka SADC Topeka Topeka Topeka Topeka Topeka Topeka Topeka Topeka Topeka
Version 5.0
Page 21
Team
Role
Resource Name
Location
Roll On Month
M10
Total Months
Reporting Business Intelligence Services and Reporting Application Developer Reports TBD Topeka M18 9
NOTE: Accenture will leverage the K-MED Project Management team for SRS beyond month 21 . This team will support Project Management functions during LIEAP and Virtual Contact Center activities.
Version 5.0
Page 22
4.2
State
The table below defines the SRS Staff required to support the SRS Project teams. It highlights the Team, Role, and Roll On and Roll Off Months for each resource. For a description of Roles please refer to section 4.5 Skill Sets for both SRS and K-MED projects, below. Resources marked with an asterisk are intended to highlight those resources that would be part of the 12 month Ongoing Operations team. These resources would support the management, build and test, training, and implementation of the ongoing support and approved enhancement requests during the 12 month Ongoing Operations phase of the project.
Team
Project Management Project Management Project Management Technical Architecture Eligibility System Eligibility System Eligibility System Eligibility System Eligibility System Eligibility System Eligibility System Eligibility System Eligibility System Eligibility System Eligibility System Eligibility System Eligibility System Eligibility System - Conversion Eligibility System - Content Management
Roll On Month
M1 M1 M1 M1 M1 M1 M1 M1 M1 M1 M6 M2 M2 M6 M6 M6 M1 M6 M1
Total Months
21 39 39 21 39 39 39 39 39 39 34 38 38 34 34 34 39 16 21
Version 5.0
Page 23
Team
Business Intelligence Services and Reporting Eligibility System Eligibility System Eligibility System Enterprise Readiness Enterprise Readiness Enterprise Readiness Enterprise Readiness Enterprise Readiness
Role
Application Developer Reports Tester Tester Tester Business Process Reengineering Lead Business Process Reengineering Lead Training Developer Training Developer Training Developer
Roll On Month
M13 M6 M6 M6 M4 M4 M6 M6 M6
Total Months
13 34 34 13 13 16 16 16
Note: This table represents the minimum number of resources contractually obligated to complete the SRS Contract. Additional resources may be identified during the Analyze and Design phases of the project. There is an expectation that the State will provide business resources, technical resources and subject matter experts as needed to support the project.
Version 5.0
Page 24
4.3
Organization Chart
The proposed Avenues implementation team is shown in the Avenues Project Organization Chart. This chart shows the resources specifically identified for SRS and its requirements across all phases of the project. Accenture will leverage Perceptive to fill the roles for the Content Management while Accenture while remaining overall responsible for the overall project.
Figure 2 - Avenues Project Organization Chart
Version 5.0
Page 25
4.4
Key Personnel
Listed in the table below are the contractor resources that have been identified as key to the Avenues project. Proposed consultants should be available to staff the project, unless prevented from doing so by circumstances beyond the Proposers control.
Role
Keith Salas Avenues Project Manager Robin Murphy Sub-Project 1 Business Architecture and Change Management Project Manager
Relevant Experience
13 years experience in IT field delivering large, complex systems, ontime and on budget, and to the satisfaction of the customer 9 years of health and human services experience including 6 years eligibility determination and 2 years child support systems 7 years of project management experience
3 years experience in change management / implementation 2 years health and human services experience including Medicaid eligibility determination systems 6 years experience in training development and delivery including leading training teams 4 years experience business process development, testing and implementation 1 year experience organizational design and implementation
Mel Pieper Sub-Project 2: Update Technical Architecture and Install Infrastructure Project Manager
25 years of experience in the IT industry delivering large, complex systems, on-time and on budget, and to the satisfaction of the customer 15 years experience managing technical support/architecture teams 10 years experience in managing system architecture at the enterprise level 12 years of experience working with the proposed RDBMS-based applications
Version 5.0
Page 26
Role
Role Descriptions
and technology needs of the organization based on new and emerging technologies, and establishes priorities and strategies consistent with business goals and economic viability. Serves as an advisor to senior IT leadership on advanced technologies and evaluates the business impact through cost/benefit analysis. Recommends and incorporates technology with long-term business plans Develop and design the overall ECM storage and retrieval strategy Define a conversion strategy for existing paper case files Leads the overall design, development and implementation of the ECM and integration with Avenues
Relevant Experience
10 years of experience years of experience supporting object oriented web applications 10 years of health and human services experience including 10 years TANF, SNAP and other program eligibility determination systems
9 years experience in designing, building and managing software projects Led the design and implementation of document management solutions as a project manager for over 85 projects Led the document management team for the California Statewide Automated Welfare System (SAWS) Consortium-IV (C-IV) project. Experience marrying the unique needs of human services case management with the best practices of document management systems 7 years of experience in managing application development at the enterprise level Developed and maintained a major health and human services systems on J2EE platform 11 years of experience in IT field delivering large, complex systems, on-time and on budget, and to the satisfaction of the customer 9 years of health and human services experience including 9 years Welfare eligibility determination systems 7 years of project management experience
Jerald Nielson Sub-Project 4: Eligibility and Benefits Administration System Project Manager
Leads the technical team and oversees all technical aspects of Avenues application development including data conversion, portal and interfaces Manages technical resource allocation for the team to manage project cost and schedule Reviews all technical deliverables and would provide input to the Overall Project Manager regarding approval of technical deliverables Leads detailed design meetings to build, configure, and implement the Virtual Contact Center Defines integration of telephony systems with Avenues CRM functions Analyzes field offices and provides recommendations for new model to support the Virtual Contact Center
33 years experience in the communications industry, including wireline service (PSTN) and VoIP network configurations. 28 years experience in telecommunications infrastructure for Avaya and Cisco systems, including ancillary applications (IVR, Call Management Systems, CTI, Advanced Call Routing, Voice Messaging, Fax Server, Call Recording, Quality Monitoring, and Workforce Management applications) Development, testing, installation and maintenance of two 500+ seat
Version 5.0
Page 27
Role
Role Descriptions
Relevant Experience
call centers for health and human services clients. 7 years experience in health and human services 5 years in support of Medicaid eligibility systems, and 2 years at the Texas Welfare Modernization project. 2 years of project management experience 3 years experience in architecting and implementing eligibility system reporting components leveraging various tools and concepts; Oracle Database, SQL, PL/SQL, Oracle Reports Builder, Oracle Warehouse Builder, Extract Translate Load Design Concepts (ETL), Oracle Business Intelligence Enterprise Edition(OBIEE) and Data Warehousing Dimensional Design Concepts. 3 years experience in architecting and implementing eligibility system data conversion components leverage Oracle Database and Oracle Warehouse Builder. 2 years of development team leadership experience; leading teams of 2-3 developers to meet project milestones on time and on budget. 1 year experience in maintaining and enhancing a production Business Intelligence Services providing analytical reports from eligibility system data. 6 years experience in IT field maintaining and enhancing a large and complex eligibility system to meet customer needs
Anthony Perez Sub-Project 6: Business Intelligence Services and Reporting Project Manager
Leads the Business Intelligence Services & Reporting team, skilled in data analytics, reporting, and data mining tools & techniques
Version 5.0
Page 28
4.5
The listing below includes roles/skill sets for the SRS project. The focus is to provide a high level description with a focus on the tool and developments skills. A person can serve more than one role. It is expected that the Key Skills and Responsibilities that are highlighted in bold font are the needed skill sets that would most benefit the project.
Role
1. Project Manager 2. PMO Manager
Provides day-to-day leadership and management of the Project Management Office (PMO) team and resources.
4.
Technical Architect
Version 5.0
Page 29
Role
6. Application Developer Reports 7. Application Developer Conversion
Codes and tests conversion programs to accurately convert data from legacy systems
8.
Version 5.0
Page 30
Role
9. Tester Verifies team deliverables Interfaces with other teams
Provide expertise in the planning, constructing and execution of Avenues tests. Apply business and functional knowledge to meet the teams overall test objectives. Knowledge of SRSs business requirements and processes Works closely with Application Developers to verify the application and any identified defects Assists in the development of test conditions and test scripts Assists in the execution of test scripts Logs the necessary defects for the Avenues application related to execution of test scripts 2 to 3 years in imaging, document indexing, and scanning hardware deployment; skills in the ImageNow product Leads team to redesign SRS business processes to take best advantage of system capabilities Leads team to make organization and roles changes to align with new and revised business processes Develops in-depth knowledge of system functionality and processes Knowledge of SRSs business requirements and processes Ability to evaluate options in light of operational, management, and policy considerations Defines system requirements/configuration based on SRS business requirements Provides guidance, input and review for training and enterprise readiness materials Knowledge of SRSs organizational culture and business requirements Understanding of specialty areas (e.g. intake) Ability to articulate SRS stakeholder and customer needs Ability to communicate complex issues to technical and non-technical audiences Ability to communicate issues with technical and non-technical audiences Familiarity with Avenues Training tools: Microsoft Work, Adobe Captivate and RoboHelp Knowledge of SRSs business requirements and processes
10. Imaging/Content Management Developer 11. Business Process Reengineering Lead SRS
Provides subject matter expertise to developers, designers, training team and enterprise readiness team
Contribute to the Training Team by assisting in designing and developing the training materials.
Version 5.0
Page 31
5.0
Deliverable Schedule
The following deliverable schedule provides the agreed upon pricing for specific deliverables and the associated expected month for completion. The Project Work Plan will establish specific due dates for each deliverable, which may vary from this table, and shall govern. The holdback of deliverables will be released following the Acceptance of the deliverable, and the Acceptance of the Avenues implementation in Phase ,2 and again for Phase 3 and Phase 4. Holdback of the deliverables for the implementation of the BPR changes (Pilot, and each subsequent set of offices in deliverable list), will be released upon Acceptance of the BPR deliverables and completion of the BPR work. Other payments due to the contractor are incorporated into the contract and are detailed in the recurring payment schedule below. No. 1 2 3 4 5 6 7 8 9 10 11 SRS Deliverable Name Project Management Plan Cost Allocation/Time Reporting Detailed Project Plan (KITO Approved) Facility Management Plan Communications Plan Risk Management and Issues Management Plan Configuration Management Plan Knowledge Transfer Plan Interface Plan (P2) Reports Plan (P2) Interface Standards and Layouts (for Agencies and Business Partners) (P2) Requirements Validation (P2) Business Intelligence and Reporting Plan Enterprise Readiness Plan (P2) Conversion Plan (P2) Deliverable Month 1 1 1 1 1 1 1 9 2 2 2 Deliverable Price $80,235 $64,188 $128,376 $112,329 $112,329 $96,282 $144,423 $208,610 $481,409 $465,362 $369,080
12 13 14 15
3 3 10 6
Version 5.0
Page 32
No. 16 17 18 19 20 21 22 23 24 25 26 27
SRS Deliverable Name Application Code and Unit Test (P2) Continuity of Operations Plan (P2) Training Plan (P2) Capacity and Performance Plan (P2) Training Materials (P2) Deployment/Rollout Plan (P2) User Acceptance Test Plan (P2) Online User Guide (P2) Operating Procedures Guide (P2) Tables and Rules User Guide (P2) Data Conversion Dry-Run (P2) Knowledge Transfer Scorecards (Completed Phase 2 Personnel Assessments) Performance Test (P2) Training Delivery Complete (P2) Detailed System Design (DSD) (P2) Application Deployment (P2) System Acceptance (P2) System Test Plan (P2) Continuity of Operations Exercise (P2) System Test Results(P2) LIEAP Detailed System Design LIEAP System Test Plan
Deliverable Month 13 15 6 6 13 15 15 14 14 14 21 20
Deliverable Price $962,817 $240,704 $497,456 $465,362 $497,456 $353,033 $353,033 $240,704 $224,657 $320,939 $401,174 $112,329
28 29 30 31 32 33 34 35 36 37
20 20 10 21 21 11 15 15 23 24
$176,516 $465,362 $465,362 $561,643 $1,123,287 $320,939 $320,939 $320,939 $288,845 $240,704
Version 5.0
Page 33
No. 38
SRS Deliverable Name User Acceptance Testing Results and Resolutions Document (P3) LIEAP Application Deployment LIEAP System Acceptance LIEAP System Documentation and Knowledge Transfer Virtual Call Center Deployment Organization Design for Virtual Contact Center Virtual Call Center Detailed System Design Virtual Call Center System Test Plan Virtual Call Center System Acceptance Virtual Contact Center System Documentation and Knowledge Transfer BPR Assessment BPR Plan BPR Implementation Pilot BPR Office Implementation 2 thru 6 BPR Office Implementation 7 thru 11 BPR Office Implementation 12 thru 15
Deliverable Month 27
39 40 41 42 43 44 45 46 47
27 27 28 30 24 24 25 30 31
48 49 50 51 52 53
3 5 6 8 10 12 Total Deliverables:
*Deliverables 12, 35, 36, 38 - 46 are unique to the SRS Avenues project. All other deliverables are common to both K-MED and SRS; however, the price is only specific to SRS portions of the deliverable. Listed below are recurring payments. Service delivery billings refer to 12 months of maintenance services, following implementation:
Version 5.0
Page 34
Fiscal Year: Month: Billing Category Monthly PMO Billings Service Delivery Billings Holdback Eligible N N Total Category Price $1,570,504 $1,389,000
$2,959,504
$90,575
$77,426
$80,370
$80,370
$80,370
$80,277
$75,645
$75,645
FY2012 9 Billing Category Monthly PMO Billings Service Delivery Billings Apr-12 $75,645 $0
$75,645
FY2013 19
$65,675
FY2013 20 Mar-13 $68,345 $0
$65,675
FY2013 21 Apr-13 $68,345 $0
$65,675
FY2013 22 May-13 $10,042 $112,745
$65,675
FY2013 23 Jun-13 $10,042 $112,745
$66,392
FY2014 24 Jul-13 $10,042 $112,745
$66,392
FY2014 25 Aug-13 $10,042 $112,745
$66,392
FY2014 26 Sep-13 $10,401 $117,299
$68,359
FY2014 27 Oct-13 $0 $117,299
$68,345
FY2014 28 Nov-13 $0 $117,299
Feb-13 $68,345 $0
$68,345
$68,345
$68,345
$122,787
$122,787
$122,787
$122,787
$127,700
$117,299
$117,299
FY2014 29 Billing Category Monthly PMO Billings Service Delivery Billings Dec-13 $0 $117,299
FY2014 34 May-14 $0 $0
FY2014 35 Jun-14 $0 $0
FY2015 36 Jul-14 $0 $0
FY2015 37 Aug-14 $0 $0
FY2015 38 Sep-14 $0 $0
$117,299
$117,317
$117,317
$117,317
$116,874
$0
$0
$0
$0
$0
Version 5.0
Page 35
6.0
The Project Management Office (PMO) will be comprised of representatives from the K-MED/Avenues State and Contractor Project Teams. The PMO shall be responsible for providing project management services. The PMO will generate and provide project management analysis and information to KMED/AVENUES Project leadership, the K-MED/AVENUES Project Steering Committee and KMED/AVENUES Project Team members. The PMO will ensure that all applicable Kansas Information Technology Office (KITO) requirements, as specified in ITEC Policy 2400 Revision 1, are met. The K-MED/AVENUES State Management Team shall include the States Project Director(s), States Project Manager, as well as the Contractor Project Manager.
6.1
KITO Requirements
The Project Management Plan shall meet all requirements of ITEC Policy 2400, Revision 1, and must be approved by the CITO prior to commencement of material project activities (January 1, April 1, July 1, and October 1). The K-MED/AVENUES Project Management Plan will reflect the four major project phases for the K-MED/AVENUES project. The Detailed Project Plan, a detailed work breakdown structure completed in Microsoft Project, is one part of the overall K-MED/AVENUES Project Management Plan. For Project Phases 1 and 2, all individual tasks for the Plan and Analyze Phases of the project shall be equal to or more than eight hours and less than or equal to 80 hours of duration (unless there is a KITO exception). The tasks for later work may be greater than 80 hours but must be in sufficient detail to show all milestones, deliverables and the summary level dependent activities in sufficient detail to assess milestone and deliverable statuses. Near the completion of the preceding development phase, the Detailed Project Plan for the next development phase will be further refined. All tasks shall be resource loaded (both Contractor and State employees) and leveled. All deliverables shall be shown as milestones. Additional internal milestones/deliverables shall be established for management and reporting purposes. The projects critical path(s) shall be identified. Quarterly Reports shall be prepared in a timely manner by the Contractor so that they can be submitted by the Project Director to the KITO office on a quarterly basis. An updated version of the project plan shall be submitted by the Contractor on the 3rd business day after the end of the quarter. Quarterly reports shall show the projects progress and estimate at completion. The table below identifies the elements of the Quarterly Report and responsibilities.
KITO Quarterly Reporting
Cover Letter Transmittal Letter (including narrative) Checklist
Contractor
KDHE-HCF/SRS
Lead Lead Lead
Version 5.0
Page 36
Lead Assist
Assist Lead
If the Project encounters problems adversely affecting scope, schedule or cost, KITO reporting information and frequency may increase. Any additional reporting requirements arising during the course of the Project due to problems adversely affecting scope, schedule or cost shall be maintained and supported by the Contractor at no additional cost provided the additional reporting requirements pertain to activities the Contractor is responsible to perform or information the Contractor is responsible to manage.
6.2
The Contractor shall provide K-MED/AVENUES Project Monthly Status Reports that reflect the previous months activities. K-MED/AVENUES Project Monthly Status Reports are due by Tuesday, 10am, in the week following the end of each month. If a State holiday occurs during one of the report preparation days, a grace period of one day will be allowed for the submittal of the report. Accepted KMED/AVENUES Project Monthly Status Reports shall constitute the Deliverable that permits payment for project management services. The QARP process shall be used for these monthly deliverables. The table below identifies the elements of the K-MED/AVENUES Project Monthly Status Reports and responsibilities. In addition, for select project WBS elements earned-value reporting may be beneficial. Where the State believes that this level of granularity will provide a valuable indicator of the status of a discrete critical project scope element, the State shall request and the Contractor shall provide earnedvalue reports for the duration of the specific scope element or until the State is satisfied with the progress of the specific scope element.
Monthly Reporting
Budget-to-Actual Critical Path & Analysis Milestone Status Project Health Assessment Look ahead (upcoming activities and issues) Outreach Activities (training, risk issues and mitigation activities, communication, etc.) Progress in Knowledge Transfer Change Request Log Staff Changes (Contractor and State)
Contractor
Lead Lead Lead Lead Lead Assist Lead Assist Lead
KDHE-HCF/SRS Team
Assist Assist Assist Assist Assist Lead Assist Lead Assist
The Contractor shall provide K-MED/AVENUES Project Weekly Status Reports that reflect information for the Monday through Friday time period. K-MED/AVENUES Project Weekly Status Reports are due by Tuesday, 10am, in the week following the reporting period. If a State holiday occurs during one of the Version 5.0 Page 37
report preparation days, a grace period of one day will be allowed for the submittal of the report. The table below identifies the elements of the K-MED/AVENUES Project Weekly Status Reports and responsibilities. A template for the K-MED/AVENUES Project Weekly Status Report is provided in Attachment A.
Weekly Reporting
Accomplishments Activities for Next Reporting Period Issues/Risk Elements Status of Critical Path Budget to Actual
Contractor
Lead Lead Lead Lead Lead
KDHE-HCF/SRS Team
Assist Assist Assist Assist Assist
6.3
The Contractor shall maintain a record of hours worked per WBS element on the MS project plan. The Contractor shall provide the State access to MS Project to enable authorized personnel from the State to enter hours worked by WBS element for each employee or other updating as appropriate. Time reporting for State project personnel shall be performed on a weekly basis. The table below identifies the work elements for time reporting and responsibilities.
Time Reporting
Configure, Host, Administer MS Project Server or other time capture/allocation tool Train Appropriate Project Team Members on Time Reporting Update Project Schedule/WBS with Actual Employee Time Provide Monthly Reports on Budget vs. Actual Time per WBS Element Capture and record Contractor time Capture and record State time
Contractor
Lead Lead Lead Lead Lead Assist
KDHE-HCF/SRS Team
Assist Assist Assist Assist Lead
6.4
The Contractor shall provide all necessary training in, and access to, the Rationale Toolset for requirements management, version control of documents, internal workflow processes for defect management and testing tools for unit, system and performance testing. Training shall be held for all members of the co-located Project Team deemed necessary by the State Project Director(s). The amount of training time provided by the Contractor shall be sufficient to adequately train project team members so that they may adequately perform their project responsibilities.
Project Execution Tools Contractor KDHE-HCF/SRS Team
Version 5.0
Page 38
Contractor
Lead Lead
KDHE-HCF/SRS Team
Assist Assist
6.5
The Contractor shall utilize the following procedures for conducting and documenting meetings: Prepare agenda including meeting objectives. Conduct the meeting. Document action items, issues and decisions.
Preparing meeting agendas and documenting action items, issues and decisions may also be performed by the K-MED/AVENUES State Project Team members when deemed appropriate and mutually agreed to by Contractor and State.
6.6
The Contractor shall, in consultation with the K-MED/AVENUES State Management Team, develop and maintain a Risk and Issues Management Plan which shall include a Risk and Issues Tracking Document. The Plan shall identify key risk elements and rank these risks based on the product of the probability of occurrence and the impact (i.e. Qualitative Risk Analysis). The Plan shall also include mitigation measures to monitor identified risks. Using these measures, the Contractor shall update the Risk and Issues Tracking Document to report on the status of identified risks and any proposed or implemented risk mitigation activities. The updated Risk and Issues Tracking Document shall be included as a subsection of the K-MED/AVENUES Project Monthly Status Report, unless a risk element occurs, in which case that risk element shall be reflected as an issue. Issues which prevent work from being accomplished shall be reported as part of the K-MED/AVENUES Project Weekly Status Report. Risk and Issues Management Meetings will be scheduled monthly and will include members of the KMED/AVENUES State and Contractor Management Teams.
6.7
Deliverables
Version 5.0
Page 39
Project Governance is defined in the K-MED/AVENUES Steering Committee Charter and in the KMED/AVENUES Project Management Plan. Four levels of project governance are delineated below: 1) Level 4 K-MED/AVENUES State Managers (Business, Technical, Enterprise Readiness) are authorized to approve minor changes in project scope. 2) Level 3 K-MED/AVENUES State Management Team is authorized to approve moderate scope changes. 3) Level 2 K-MED/AVENUES Steering Committee is authorized to approve significant scope changes and make recommendations to the Executive Sponsors on policies and issues affecting agencies. 4) Level 1 Executive Sponsors approve recommendations from Level 2 and provide Statewide leadership and the mandate for the K-MED/AVENUES Project.
Change Request
Authority
Cost Impact
Scope Impact
Schedule Impact
Agency Impact
Level 1
ExecutiveSponsors
Would be associated with Any change affecting cost impact the Golive date -
TBD
Level 2
Steering Committee
TBD
Level 3
Any change affecting KITO milestones or other key (internal management) milestones
Level 4
Version 5.0
Page 40
6.8.2
The following process shall be used for all scope, schedule or cost changes: 1. Change Requests (CR) are submitted by the K-MED/AVENUES State Management Team to the Change Control Board (CCB). The CCB shall be comprised of the State Project Director(s), the State Project Manager, and the Contractors Project Manager. A member of the States PMO shall serve as the Secretary of the CCB. 2. All CRs must be sponsored by a K-MED/AVENUES State Manager (i.e. Functional, Technical and Enterprise Readiness). To initiate a CR, the K-MED/AVENUES State Manager shall send an email request to the CCB. The request should include a priority designation. a. Priority 1 Urgent and Major Impact b. Priority 2 Urgent and Minor Impact c. Priority 3 Not Urgent and Major Impact d. Priority 4 Not Urgent and Minor Impact 3. The K-MED/AVENUES Project Team Manager must receive authorization from the CCB to proceed with the CR. 4. CRs shall be developed using the attached template. Analysis will include impacts to business requirements, cost, schedule and State and Contractor resources. CRs will be presented to the CCB and the merits of each CR shall be discussed collaboratively among the CCB, the sponsor, the Contractor and affected stakeholders. 5. The Contractor shall not bill the State for developing CRs. Within five days the CCB shall either: a. Approve the CR b. Disapprove the CR c. Request additional information d. Present the CR to the Steering Committee (as appropriate) 6. All CRs and their disposition shall be documented in the Change Control Log. 7. Approved CRs shall become Change Orders (CO) to the SOW. The CCB shall determine if the approved CO shall be designated as: a. a fixed-price CO, Version 5.0 Page 41
b. a trade-off of hours from scope reduction, c. a time and materials CO, d. a reduction in scope CO, or e. a schedule impact CO (e.g. a time extension for a deliverable). 8. The CCB shall designate the funding source for the approved CO. In most cases CO requiring funding will come from the designated pools of hours reserved for modifications and enhancements, interfaces, conversions, workflows and reports. The Requirements Traceability Matrix shall be updated to reflect the changes in scope to the applicable requirements. 9. After the change has been implemented and accepted, the CR shall be closed and documented in the closed page of the Change Control Log.
Version 5.0
Page 42
Analysis of Change
Analyst: ________________________ Est. Cost Impact: _________________ Est. Schedule Impact: _____________ Milestones/Deliverables Impacted: __________________________________________________ Teams Impacted: Time to Complete Analysis: ______ hrs Date Completed: _________________
Version 5.0
Page 43
Level of Effort
Team Contractor State Design Hours Development Hours Testing Hours Documentation Hours Training Hours
Resource Estimate
Team Member Contractor Contractor Contractor Contractor State State State State Name Hours Rate Start Date End Date
Version 5.0
Page 44
Design Phase
Development Phase
Deliverable(s)
Risks and Issues (Identify impact to existing project risks and issues)
Supporting Documentation (Provide information relative to any documentation supporting this change request such as documents/files names, links, screen shots of applicable delivered pages, mock-ups, process flow diagrams, etc.)
Version 5.0
Page 45
K-MED Lead Send e-mail CR Request (w/ Priority) to CCB; Secretary to Initiate CR
K-MED Leadership Team Approve/Disapprove Request to Initiate CR; Leadership Team to respond w/i 3 days
Approve
Disapprove
Stop
Approve Approve
Execute CR define deliverable (DED) update project plan (as reqd) update RTM (as reqd) notify impacted team members and stakeholders Perform Additional Analysis or Provide Additional Information
Defer Disapprove
Version 5.0
Page 46
7.0
Requirements Validation, Business Process Design, Software Configuration, Testing, and Enhancements & Modifications
The project team will be responsible for analysis, design, configuration, and system testing of the SRS Avenues application, including requirements validation, business process design, software configuration, testing, and enhancements and modifications. In scope are the requirements provided in SRS Human Services Eligibility Modernization RFP. The specific requirements in scope include: 1. 2. 3. 4. Business Requirements Technical Requirements Interface Requirements Conversion Requirements
The Avenues scope is an incremental addition to the K-MED scope. The K-MED SOW in Section 7 describes the phases of the System Development Lifecycle which trace RFP Requirements through the KMED implementation. The Avenues scope follows the same process as described in Section 7 of the KMED SOW. Additional sections of the Avenues SOW have been added to supplement special scope areas (e.g. Workflows, Interfaces, etc) to the base description for the Avenues system build. Key additions not detailed in the Avenues requirements but are part of the project scope include: Report Development Described in the Business Intelligence Services and Reporting Statement of Work (SOW) Forms and Notice Development Described in the Automated Forms and Notices SOW Conversion of LIEAP Described in the Data Conversion SOW NOTE: Although Accenture will not convert from the EATSS or TOP systems, Accenture will test the ability to decommission these systems during Operational Readiness Testing, and confirm the necessary functionality is working in Avenues.
Version 5.0
Page 47
7.1
Test Phase
The SRS Test Phase will reference the K-MED Test Phase as the Avenues solution will leverage the methodologies, processes, conditions, and scripts that are defined in the K-MED Test Phase. As part of the SRS testing effort and to adequately test the Avenues scope, Accenture will supply a subset of Business Analysts and Application Development resources as an increment to the overall K-MED Test team. The result will be one integrated K-MED/Avenues Test Team. The K-MED/Avenues Testing Team, consisting of both Contractor and State staff, will design, create and execute the necessary scripts based on the defined test conditions and cycles. Test phases will build upon each other in functionality and complexity. During test execution, System Investigation Requests (SIRs) will be identified, assigned a priority, and tracked through to completion. The goal will be that critical and high priority SIRs are corrected prior to the next test cycle.
Version 5.0
Page 48
7.2
Analyze Phase
Responsibility Matrix
Scope Element Contractor
Lead Lead Lead Assist Assist Assist
SRS
Conduct Conference Room Pilot Perform Fit/Gap of APSP to K-MED Requirements Define Reports, Interfaces, Conversion, Enhancement, Forms and Workflows (RICEFW) Inventories Design Phase Design Modifications Design Security Build Phase Build Configuration Build and Unit Test Application Components Develop Test Conditions and Scripts Test Phase Plan Integration Test Plan System Test Plan UAT Execute Integration Test Execute System Test Execute User Acceptance Test
Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Assist
Assist Assist Assist Assist Assist Assist Assist Assist Assist Assist Lead
7.3
Ref. No.
29
Description
The General and Detailed Design documents the technical requirements for developing, testing, and implementing the KMED System. This deliverable describes the standards and process for making modifications to the APSP application.
NA
Design
15
Build
This deliverable represents the developed and unit tested enhancements and modifications that are ready for system test. Exception and error handling processing will be validated against signed-off program design specifications. Enhancements and modifications will be tested as standalone modules. System Test Plan describes the test strategy for K-MED including the sequence and methodology of testing. The plan addresses at a high level the test environment, the tests to be performed, and the schedule for test activities. It also includes a list of business processes per module. The System Test Plan will include objectives, entry and exit criteria, approach, schedule, script documentation, data
32
Test
Version 5.0
Page 49
Ref. No.
Phase
Description
management, assumptions, constraints, risks, and requirements traceability.
21
Test
We will include the following in the User Acceptance Test Plan: objectives, entry and exit criteria, approach, schedule, script documentation, data management, assumptions, constraints, risks, and requirements traceability. This deliverable documents the system test results of the system test conditions and scripts and the fixes or SIRs identified due to system test. It details of the test scripts executed and the number, type and status of identified SIRs during the system testing process. This deliverable provides documentation of the issue tracking and resolution during UAT. UAT testing results are reported in this deliverable.
34
Test
37
Test
Version 5.0
Page 50
8.0
The Avenues Project team, including the business analyst, will be responsible for design, configuration, and testing of the system BPM-based workflows within the Business Process Management (BPM) tool. This team will also be responsible for configuring and/or changing workflows internal to the system. Their tasks will include requirements validation, functional design, technical design, build and unit test, and system testing.
8.1
Scope Definition
APSP provides 12 BPM workflows that are shipped out of the box. These processes will be configured according to SRS need. Business processes will describe workflows for both human and system users. Business Process designs can include input data, process flows, tasks, routing (including escalation), forms, output data, invocation of external systems like rules engines, and business activity monitoring events. BPM-based workflows will be designed, built and deployed in the Oracle BPM Suite environment. Non-BPM workflows will consist of Java code for page-to-page workflows, tasks and reminders, and Java Server Pages-based portlets for forms and page elements. The following definitions were used when estimating the effort for workflows. These definitions will be used to determine complexity both during the configuration of included workflows and when implementing any contingency workflows: Process Step: A discrete, unique human task (i.e., Complete and Forward Form) or discrete, unique system operation (i.e., Get Normalized Address) that is performed during the course of the business process. The following BPM constructs are not process steps are not counted as such: Decision points (i.e., Is Address Normalized?) Routing rules (i.e., if program=Medicaid then forward to role X) Escalations (i.e., If application has been idle at this step for 24 hours, then escalate to role X) Business processes often include sub-processes. The building of these sub processes will follow the same sizing approach as any other process. Sub-processes included in master processes will be counted as 1 process step. Role: The human or system actor performing the process step. These are identified by the role headings in a typical swim lane flow design diagram. For example, the following simple process is comprised of 4 Process Steps and 2 Roles:
Version 5.0
Page 51
The following, more complex process flow has 12 process steps and 4 roles:
This count includes the following 8 Human Task Process Steps: 1. Answer Non-Financial Questions 2. Answer Financial Questions Version 5.0 Page 52
3. Submit Application 4. Provide Information (unique step called in two different contexts) 5. Request Information (unique step called in two different contexts) 6. Run Eligibility 7. Review Results 8. Complete Application This count includes the following 4 System Tasks Process Steps: 1. Assign Caseworker (calls the existing Assign a Caseworker sub process) 2. Check Business Rules 3. Mail Notices and Correspondence 4. Post Results to Self Service Portal The following scale will be used when building a new business process or configuring an existing business process.
Workflow Complexity Process Steps (Human and System)
Up to 5 6-11 12+
After general design, the number of steps and roles in the business process will be counted. The number of steps and roles will then be compared to the above scale. If both numbers fall in the same complexity range, then that complexity will be applied to the business process effort. If one of the measures falls in a higher complexity range, then the higher complexity will be assigned to the business process. The following sample workflow inventory demonstrates sizing examples:
Workflow Process Steps (Human and System)
5 5 13 3 2 4
Complexity
Version 5.0
Page 53
The following BPM-based workflows are included in the APSP solution. Process configurations to the following processes are in-scope for the Avenues solution. Configurations include modifications of business process flow, role, reminder, alert, and data changes to the base process flow that is included with the solution. Configuration also includes configuring Business Activity Monitoring events for tasks in the workflow. Configuration does not include major changes or re-purposing of the base process flow, such as extensive branching of an existing flow. Using personal learning plans (PLPs), BPM skills will be transferred to State employees for the purpose of extending and repurposing the existing workflows. Public Assistance Portal BPM Workflows
Workflow
Registration
Steps
Application Received File Clearance Worker/Clearinghouse Assignment Intake Verifications Received Application Assigned to Worker Verify/Complete Intake Eligibility Determination Supervisor Authorization Documents Generated Active Program Re-assigned (if needed) Receive Update/Re-application Process Update/Re-application Eligibility Determination (if needed) Documents Generated (if needed) Random Sample Case Identified Worker Assignment Process Review Decision/Outcome Potential Case Identified Worker Assignment Research Cost Avoidance/Recovery Action Documents Generated (if needed) Request Filed Worker Assignment Review Decision/Outcome Identification Worker Assignment Process Decision/Outcome
Complexity
Average
Determine Eligibility
Complex
Case Maintenance
Average
Quality Assurance
Average
Simple
Simple
Overpayment/ Underpayment
Simple
Version 5.0
Page 54
Steps
Application Received File Clearance Worker/Clearinghouse Assignment Intake Verifications Received Application Assigned to Clearinghouse Status Reported to Customer Questionnaire Received Possible Eligibility Determined Status Reported to Customer Demographics or Income Change Received Verifications Received Worker/Clearinghouse Assignment Status Reported to Customer
Complexity
Complex
Screening
Simple
Report a Change
Simple
The following non-BPM workflows are included in the APSP solution. Reminder, alert, and data changes to the following processes are in-scope for the Avenues solution. Public Assistance Portal Non-BPM Workflows
Workflow
Fraud Customer Activities and Progress Tracking Skills Assessment and Job Matching Needs Assessment, Supportive Services and Identification Worker Assignment Process Decision/Outcome Redistribute Persons Workload Future Date an Assignment Automatically Reassign Programs Based on Program State Captures Third Party Organization Information Manages Recruitment of New Organizations Third Party Organization Self Service Allows workers to create Action Plans to document customer concerns and issues Documented Family Plans capture customer strengths (e.g., degrees, skills) and desired outcomes and strategies (e.g., employment goals) Monitors attendance, performance, and progress of customer training activities Allows customers to enroll in training activities Training providers manage attendance for each session, minimizing training data that worker must enter. Provides job matching functionality based on customer skills documented by employment services workers and job opportunities listed in the Resource Databank. Captures information regarding customer needs and barriers (e.g., lack of transportation)
Steps
Complexity
Simple
Worker Reassignment
Average
Resource Databank and Collaborator Access Employment Services and Child Care SelfSufficiency Planning
Simple
Average
Simple
Simple
Average
Version 5.0
Page 55
Workflow
Payment Requests Child Care Foster Care
Steps
Creates Service Arrangements and authorizes Supportive Services or Referrals to Service Providers. Generates Payment Requests to repay Service Providers for their services. Determines eligibility for Child Care based on person and case data Generates Notices of Action for Child Care automatically Payments to Child Care Providers are calculated within the system based on information from the Child Care certificate Displays Child Care waiting list functionality for jurisdictions that require waiting lists. Verify/complete intake (including Foster Care specific data collection pages) Determines eligibility for Foster Care based on person and case data Generates Notices of Action for Foster Care automatically Payments to Foster Care Payees are calculated within the system based on the results of the eligibility determination and benefit calculation Verify/complete intake Determine eligibility for Adoption based on person and case data Payments for Adoption are issued
Complexity
Average
Average
Adoption
Simple
8.2
8.2.1 8.2.1.1
The Avenues Project team, including the business analyst, will work closely with the SRS business analysts to inventory and define Avenues workflow requirements. This serves to identify the nature and degree of the workflow development work. This step includes defining strategy for use of the workflows delivered with the APSP solution, the workflow capabilities of Oracle BPM Suite, and defining any additional business processes not delivered with the APSP solution. Contractor Responsibilities: Attend meetings with Business Analysts, Case Workers, and State Functional SMEs to identify BPM and non-BPM workflow requirements. Confirm an inventory of BPM processes and sub-processes to be developed including the process name, description, and type. Document high-level requirements for each BPM business process. Requirements should include system users, human users, decision points, and desired outcomes for each process. Identify and document the security roles for each BPM and non-BPM workflow. Version 5.0 Page 56
Develop high level test conditions and expected results for each BPM and non-BPM workflow. Confirm and adjust Project Plan based on the outcomes of the Analyze Phase. State Responsibilities: Provide Subject Matter Experts (SMEs) for each functional area that can efficiently and accurately document/describe required workflow requirements. Review and approve the process inventory this is important, as it defines the list of processes that will be built in subsequent activities. Rationalize workflow requirements and determine if as-is processes already exist that could be used as starting points in the Design Phase. Assist in the documentation of high-level business process requirements for each functional area. Assist in the development of high-level test conditions and expected results for each workflow. Make design decisions in a timely manner. Confirm and adjust Project Plan based on the outcomes of the Analyze Phase.
8.2.2
Design Phase
The design phase begins with specifications from the Analyze phase, and ends with a list of tasks that, once performed in Build, will deliver the future state solution.
8.2.2.1
General designs will be created for each business process that was approved at the end of the Analyze Workflows activity. Contractor Responsibilities: Produce Business Process General Design Documents for each business process defined in the Analyze Phase. Plan Assembly Test of the approved processes. State Responsibilities: Contribute to Business Process General Design Documents. Review and approve the Business Process General Design Documents.
Version 5.0
Page 57
8.2.3 8.2.3.1
Produce Detailed Design documents for the business processes approved during the Analyze Phase. Contractor Responsibilities: Produce Detailed Design documents for business processes. Unlike General (functional) Designs, these detailed (technical) designs are intended as technical specifications that can be executed by business process developers and service interface developers. State Responsibilities: Contribute to Detailed Design documents for State assigned business processes. Review and approve each of the business process Detailed Design Documents.
8.2.3.2
The Avenues Project Team shall code and unit test business processes approved in the Analyze Phase. Contractor Responsibilities: Create Assembly and System Test Scripts. Code and unit test business processes. Conduct and document unit testing as part of the development documentation. State Responsibilities: Review and approve the code, unit test-scripts and unit test results developed by Contractor. Code and unit test business processes.
8.2.4
Test Phase
8.2.5
Deploy Phase
The Avenues Project Team shall deploy the business processes approved in the Analyze Phase. Contractor Responsibilities: Deploy business processes documented through analyze/design and build activities Version 5.0 Page 58
Monitor the Deployment Readiness Checklist to prepare for business process deployment State Responsibilities: Review Readiness Checklist and attend go/no-go decision meetings.
Version 5.0
Page 59
8.3
Responsibility Matrix
Contractor
SRS Team
Version 5.0
Page 60
8.4
The table below summarizes the Business Process and workflow work products to be created during each phase:
Ref. No.
NA
Phase
Deliverable Name
Work Product
Workflow Processing Scope
Description
The inventory of in-scope, confirmed Avenues requirements for workflow processing will be included in the Workflow Processing Scope. The BPM and workflow designs for Avenues. These designs will include data inputs, system and human actors, service level agreements (if applicable), skeleton process flow diagrams, alerts and notifications, data outputs, and other desired outcomes for each workflow. The Detailed System Design documents will provide technical detail to solve the workflow- and business process-related requirements.
29
NA
Test scripts that test every aspect of the discrete unit, in this case each business process or workflow. Coverage is focused on the individual process behaving in a technically desirable manner. This includes human actors having the correct access and ability to interact with the process and the process behaving as designed in the Detailed Design documents. Test scripts that test integration with related systems. Coverage is focused on testing every system interface for the specific business process to validate that the assembly passes data as intended in the Detailed Design documents. Test scripts that test each assembled business process as part of the system as a whole. Coverage will focus on the business process and its integrated system actors delivering the business outcomes outlined in the Detailed Design documents, and, in turn, the Requirements Matrix for traceability.
NA
NA
Version 5.0
Page 61
9.0
Interfaces
The Accenture team shall be responsible for design, configuration, testing and deployment of all (inbound and outbound) system interfaces identified in section 6.1 below. These responsibilities are inclusive of requirements validation, functional design, technical design, build and unit test, and system test. The State shall provide an interface Lead to assist the Accenture team with interface activities. The state interface Lead shall be responsible for establishing Interface Partner Agreement (IPA) and coordinating interfacing activities with all state and federal agencies. State agencies receiving data via interfaces from SRS shall be responsible for: 1) mapping data elements from SRS interface layout(s) to their systems, 2) developing programs to receive and insert SRS data into their agency system(s), 3) testing interface(s) and 4) participating in deployment. State agencies will be provided specified timeframes to perform activities identified above.
9.1
Scope Definition
Section 1.1 defines the interfaces that are in scope for the SRS Avenues projects. Section 1.2 identifies the interfaces that have been reviewed by both SRS and Accenture and have determined are not in scope for the SRS Avenues projects. During the negotiating period Accenture compared the list of Interfaces that we removed and added, delta was used to cover the contingency of interfaces that may not have been identified at the time of the SOW writing. A total of 6 interfaces, which have been mutually agreed to by both SRS and Accenture, can be added to the Interface Team scope. Any additional interfaces (i.e., more than 6) will need to be approved through the projects Change Control Process.
Complexity
Simple Average Complex
Number of Interfaces
Hours
Less than 60 hours/each 60 - 100 hours/each Greater than 100 hours
Version 5.0
Page 62
9.1.1
Interfaces In Scope
The following 17 interfaces are included in the K-MED solution and will be extended or reused to meet the SRS Avenues requirements:
Table 5- Interfaces in Scope that are Included in K-MED Interfaces
Referrals to Child Support Enforcement Child Support Alerts Including Non-Cooperation Child Support Income Information Person & Program Involvement Base Wage and Unemployment Benefit Information Treasury Offset program High Level Client Index SDX Supplemental Security Income State Data Exchange BENDEX Beneficiary Earnings Data Exchange SVES State Verification Exchange Death Records Inmate Information BC/BS Premium Information Interstate Match Veterans Administration (VA) Match Federal Match Electronic Access to Social Security (EATSS) * * The following Interfaces are In-Scope for K-MED. These interfaces will need to be shared/extended with SRS: Daily SDX SSI State Data Exchange Interface with: EATSS & KAECSES-AE, SSA system Monthly BENDEX Beneficiary Earnings Data Exchange Interface with: EATSS & KAECSES-AE, SSA system Daily BENDEX Beneficiary Earnings Data Exchange Interface with: EATSS & KAECSES-AE, SSA system Daily SVES State Verification Exchange (Wire Third Party Query) Interface with: EATSS & KAECSES-AE, SSA system Daily SVES State Verification Exchange (Wire Third Party Query) Interface with: EATSS & KAECSES-AE, SSA system Daily Qualifying Work Quarters (Sent to SSA through SVES) Interface with: EATSS & KAECSES-AE, SSA system Daily Qualifying Work Quarters (Sent to SSA through SVES) Interface with: EATSS & KAECSES-AE, SSA system Daily CHIPRA (CHIP Citizenship) SVES Requests Not Active at this time Interface with: EATSS & KAECSES-AE, SSA system
The following 8 interfaces are similar to existing interfaces in the APSP Benefits System. These similar interfaces will be configured or modified to meet the SRS Avenues requirements:
Table 6- Interfaces that exists with the APSP solution Interfaces
Child Care Provider Information
Version 5.0
Page 63
Interfaces
EBT Issuance Client Benefit Information & Warrant Numbers Overpayment and Kansas Revenue Tax Data Client Status Changes Wage Information (BEERS) TANF High Performance Free and Reduced School Lunch
Version 5.0
Page 64
The following 17 interfaces are new and will be created to meet the SRS Avenues requirements:
Table 7- New Interfaces Interfaces
Kansas Job Link Public Assistance Recipient, Rehabilitation Services Recipient, and Child Care Payment Information Foster Care Issuance Low Income Energy Assistance Program (LIEAP) Interface Juvenile Justice Authority (JJA) Reports Sedgwick County Sheriffs Department Fugitive Felon Information Shawnee County Sheriffs Department Fugitive Felon Information Lifeline Auto Enrollment Adoption Subsidy SCRIPTS Background Checks ACF800 (CCDF Child Care Report) KHPOP DIFSLA Match KPERS The Work Number SAVE ACF801 (Child Care Monthly Report)
9.1.2
The following 21 interfaces were either (1) desired but not required by SRS staff or (2) are no longer active SRS interfaces. These interfaces are not in scope for the Interface work effort:
Table 8- Interfaces that are Not In Scope Interfaces
Client Address Changes Although an active exchange, all alerts from this information are currently suppressed. Defense Enrollment Eligibility Reporting System (DEERS) Currently not an active match. Kansas Department of Health and Environment Client Identification Number Exchange EVES SSN Verification with Social Security Administration. At this time, EVES is not used and this information is exchanged through SVES. VRV Online Wage, Employer, & Unemployment Benefit Information Drivers License & Vehicle Registration Level of Care Information This is a K-MED Interface; however, it is NOT identified as an Interface that is In-Scope. It is identified as a K-MED Report This is a K-MED Interface; however, it is NOT identified as an Interface that is In-Scope. This is a K-MED Interface; however, it is NOT identified as an Interface that is In-Scope.
Notes
Version 5.0
Page 65
Interfaces
Notes
(MR-36 - LIVING ARRANGEMENT/LEVEL OF CARE OF NON INDEPENDENT LIVING MEMBERS BY PROGRAM AND AGE GROUP)
Missouri Client and Benefit Information Food Stamp Fraud Disqualification Data EBT- PC Admin. Terminal EBT Web Portal Automated Standard Application for Payments (ASAP) Account Management Agent (AMA) KDHE WebIZ Enterprise Access System (EAS) Case Management System On-Line application KHPA Website KDHE - CLARIS Food Programs Reporting System (FPRS) This is a K-MED Interface; however, it is NOT identified as an Interface that is In-Scope. This is a CAPP Interface; however, it is NOT identified as an Interface that is In-Scope. This is a K-MED Interface; however, it is NOT identified as an Interface that is In-Scope. This is a K-MED Interface; however, it is NOT identified as an Interface that is In-Scope.
9.2
9.2.1
At the completion of the Analysis Phase, designated State staff will sign off on the Interfaces that will be included in Avenues. Every interface identified will be documented and defined. During the Design Phase, developers will create detailed requirements and technical specifications explaining how they will build the functionality documented in the Interfaces General Design. Contractor Responsibilities: Conduct meetings with agency system SMEs to identify interface requirements. For the interfaces that are listed above, document the high-level requirements for each inbound and outbound interface as input into an Interfaces Design document. This work product shall define: 1) the purpose of the interface, 2) source and target systems, 3) real-time or batch processing and 4) volume and frequency and 5) method for validating successful transmission. Support SRS agency interface resources in documenting the coordination efforts related to the highlevel requirements for each Interface Partner. Requirements should include direction (to/from SRS),
Version 5.0
Page 66
frequency, volume of transactions, and user roles affected. The result will be Interface Partner Agreements with all State agencies sending or receiving data via interfaces with SRS Determine transaction volumes and interface frequency and processing mode and architecture. Leads in the development of high-level test conditions and expected results for each interface. Define error handling procedures. Define interface security protocols and standards and how these will be implemented. Confirm and adjust Project Plan based on the outcomes of the Analyze Phase. Define/verify the schedule for interface activities and adjust the project plan accordingly. State Responsibilities: Approve the in-scope interface inventory and all changes to the interface inventory. Provide interface Lead and access to agency business and technical resources. Assist in the development of high-level test conditions and expected results for each interface. Review and approve the deliverable(s) from this phase.
9.2.2
Design Phase
The Design phase shall build upon the requirements and specifications from the Analyze phase. It shall result in a list of tasks that, once performed in the construction (or build) phase, will deliver the functioning, unit tested interfaces. Detailed designs will be created for each interface. The designs include data elements and data mapping for each interface into and out of SRS. Contractor Responsibilities: Produce detailed technical design documents for exchange of SRS data; These detailed (technical) designs are technical specifications that can be executed by interface configuration SMEs and developers. Define the testing approach for each interface. For interfaces that will be used to populate data into the SRS application, a data map document shall be created. The data map document will include the identification of the source system and each field, the target system and each field and the rules to convert or transform the data.
Version 5.0
Page 67
Determine how the system will be configured to create/send and receive/process interface files/messages to and from other systems. Develop interface layouts and transmission modes for each interface. Further define error handling procedures for each interface. Participate in regular meetings with state agencies to discuss interface activities, responsibilities and timelines. Participate in conference calls (related to interfaces) with federal partners. State Responsibilities: Assist Accenture with interface design activities by providing business owner input. Lead monthly meetings with state agencies to discuss interface activities, responsibilities and timelines. Lead conference calls with federal partners. Review and approve design documents. Present detailed design information to agencies.
9.2.3
Build Phase
The Interface Development Team will use the detailed technical design documents (created in the Design Phase) to code the Interface identified in the Interfaces General Design. The detailed technical design documents will be input into the Application Development phase, defining the scope of the efforts for that phase. Contractor Responsibilities: Build and unit test delivered interfaces. Build and unit test new interfaces. Create unit test procedures and scripts. Conduct and document unit testing and report test results. Compile appropriate technical documentation for each interface. State Responsibilities: Review and approve the code, unit test-scripts and unit test results developed by Accenture.
Version 5.0
Page 68
9.2.4
Test Phase
9.2.5
Deploy Phase
The Deploy phase shall deploy the necessary interfaces as defined in the requirements and specifications from the Analyze phase. Contractor Responsibilities: Deploy interfaces as documented through design and build activities Monitor the Deployment Readiness Checklist to prepare for SRS Deployment State Responsibilities: Review Readiness Checklist and attend go/no-go decision meetings.
9.3
Responsibilities
The table below summarizes the responsibilities for the Accenture, SRS and state agencies.
Interfaces
Agency Interfaces Identify required interfaces Develop interfaces, documentation and security Identify interface requirements type of interface/frequency/data elements Create data mapping Hold workshops for agencies Build interface testing environment Provide technical assistance for agencies developing interfaces Develop interface validation procedures for source/receiving systems Develop interface testing plans Code and test interfaces Develop reports/queries for validation Develop and maintain master list of all interfaces Determine interface schedule requirements and document Performance test all interfaces Develop technical documentation for each interface Lead Lead Lead Lead Assist Lead Lead Assist/Lead Lead Lead Lead Lead Lead Lead Lead Assist Assist Assist Assist Assist Assist Assist Lead (for agency) Lead (for agency) Lead Assist Assist Assist Assist Review Lead Assist Assist Assist Lead (for agency) Attend
Accenture
SRS
Agency
Version 5.0
Page 69
9.4
Addition or subtraction of interfaces shall follow the agreed-upon change control process. For a listing of interfaces defined as Not In Scope please see section 1.2.
9.5
Deliverables
The table below summarizes the interface deliverables to be created during each phase. Payment for deliverables shall be as agreed to on the Deliverable Payment Schedule.
Ref. No.
9
Phase
Phase 2
Deliverable Name
Interface Plan
Description
The Interface Plan deliverable will define the contractors approach to the Design and Build of the Interfaces that are identified as InScope for the SRS Avenues project. Interface detailed (technical) designs are technical specifications that can be executed by interface configuration SMEs and developers. Interface Standards and Layouts document will serve as the accepted file formats that SRS Agencies and Business Partners will need to agree to in order to send and receive files after the implementation of the SRS Avenues solution.
29
Phase 2
11
Phase 2
Version 5.0
Page 70
10.0
Data Conversion
The SRS Avenues Data Conversion Team will be responsible for the extraction, mapping, data cleansing, transformation, mock conversions, data validation and acceptance, and loading of data from the source systems into Avenues. The SRS Avenues Data Conversion Team will be comprised of representatives from the Contractor and SRS and its legacy system teams.
10.1
Scope Definition
The following conversion source systems are in scope. A conversion is defined as a file or database tables that needs to be converted from one source to another
Conversion Source
KAECSES-AE
Conversion*
TANF: 14,380 Cases 36,972 Total People General Assistance: 2,371 Cases 2,394 People Food Assistance: 117,752 Cases 259,609 People Refugee Assistance: 47 Cases 52 People CFS Payments are approximately 16,000 Cases
KsCares
Child Care 10,741 Cases - 20,319 Children TANF Employment Services: 12,510 People Food Assistance E&T: 157 People
* Case and Persons counts have been taking from the RFP and only represent estimates. ** The LIEAP system will be implemented in Phase 3 of the SRS Avenues project.
10.2
10.2.1 10.2.1.1
The purpose of the analysis effort is to identify and analyze the sources of data to be converted. The conversion team develops an inventory of existing data formats, data mapping, and data conversion requirements of the legacy systems to define the scope of the SRS - Avenues Project conversion effort. The analysis effort primarily focuses on analyzing the following: 1. SRS Data Sources Technical environments 2. Physical characteristics of the data processed and maintained 3. Commonality and relationships among the case management data elements Version 5.0 Page 71
4. Overall stability, accessibility and the process for maintaining the data 5. Level of data quality 6. Potential extraction point in time and or business processes for each system Contractor Responsibilities: Conduct meetings with central and SRS SMEs to identify conversion requirements. Lead Data Quality Assessment supported by SRS SMEs. Perform Gap Analysis to identify gaps between the data available in the legacy systems in comparison with the data requirements of the Avenues System. Perform analysis of the data from the various legacy systems to determine which data should be converted from which system. Development of Conversion Plan.. Develop high level test conditions and expected results. Confirm and adjust Project Plan based on the outcomes of the Analyze Phase. State Responsibilities: Provide Subject Matter Experts (SMEs) for each system that requires conversion. Provide SME support in the Data Quality Assessment. SMEs play a critical role in confirming how the source data supports the current business process. Assist in the development of high-level test conditions and expected results for each central and agency system that requires data conversion. SRS will take responsibility for the portions of these tests that deal with the legacy systems. Review and approve the Gap Analysis. This is an important activity since it serves as input in how SRS will extract data in the standard conversion templates. The SRS will take responsibility for all modifications to existing SRS systems. Make design decisions in a timely manner. Confirm and adjust Project Plan based on the outcomes of the Analyze Phase.
Version 5.0
Page 72
10.2.2
Design Phase
The defined requirements and the analysis performed to-date drives the conversion design specifications of the data cleansing, extract, transformation, and load modules. The conversion Detailed Design Documents will: 1. Confirm that the data elements (automated or manual) are included in the Conversion Data Dictionary. 2. Refine the initial Gap Analysis and document processes to address each data gap. 3. Define Detailed Source to Target Data Maps and translation rules. 4. Confirm that the historical data elements are accounted for in the new system. 5. Confirm modules are reused where possible. 6. Confirm validation of data relationships from disparate data sources. 7. Baseline the control totals in order to measure the completeness of the conversion modules. 8. Confirm data cleansing processes. Contractor Responsibilities: Provide Conversion Data Dictionary and lead mapping of legacy data elements to Avenues source element. Collect transaction and balance volumes to be used in planning the Mock Conversion Test. Lead design of automatic conversion routines. Existing conversion routines are configured for loading of data into Avenues. Design Manual Data acquisition processes with support from SRS SMEs. Produce Detailed Design Documents for data upload work units. Review State developed Detailed Design Documents for legacy conversion work units. State Responsibilities: Evaluate the source data for conversion. Document its structure and schedule availability for conversion activities. Ensure that it has been cleansed in time for the conversion process. Assist the Contractor with the development of the Design Documents.
Version 5.0
Page 73
Develop the extract specifications and file specifications for the legacy system from which data will be extracted to load into APSP standard conversion templates. Approve the data-maps including default logic in the data mapping documents, and may approve the rules to convert or transform the data. Review and approve each of the Detailed Design Documents. Develop Detailed Design Documents for legacy extracts.
10.2.3 10.2.3.1
The SRS Avenues Data Conversion Team shall code and unit test modifications. Contractor Responsibilities: Develop/modify data upload routines. Develop/modify test conversion reports. Configure APSP delivered data upload and extract routines. Create unit test-scripts. Conduct and document unit testing as part of the development documentation. State Responsibilities: Code and component test the extract and reconciliation files and reports from the legacy systems. Review and approve the unit test-scripts and unit test results developed by Contractor.
10.2.4
Test Phase
10.2.5 10.2.5.1
The SRS Avenues Data Conversion Team will execute a minimum of three Mock Conversions. The goal of the mock conversions will be to verify that the delivered conversion templates can be used to load information for the integration testing and subsequent go live. If additional conversion modifications are identified during the Analyze Phase, these conversion routines will also be included in the Mock Conversion Testing. Version 5.0 Page 74
Contractor Responsibilities: Coordinate, advise and support the State in their data cleansing activities. Prepare a schedule of mock conversion activities that outlines the tasks and timeframes for the mock conversions. Execute mock conversions. A mock conversion is an iterative process of executing conversions, performing validation and verification and correcting conversion programs that are built by the project team until the data is sufficiently usable for Integration Testing. Support SRS as it executes data cleaning by identifying data to be cleansed and providing recommendations on data clean-up approaches. Validation and reconciliation report(s) will be created as part of each scheduled mock conversion that documents data discrepancies. The reports shall also include summary count information that SRS can use to help measure its progress related to data cleansing. Prepare a mock conversion results document after each mock conversion, which summarizes the results of that conversion execution and the action items for both Contractor and the SRS in light of those results. Provide overall input into the Go-Live cutover plan for Conversion. State Responsibilities: Correct all System Investigation Requests (SIRs) for extract programs that arise from mock conversions. Complete the data cleansing and purification of data contained in the legacy systems as required to support the data conversions, including if necessary manually or programmatically correcting the data. Produce the source data files required to support each mock conversion. Such files will comply with the extract and file specifications. Verify and validate the results of the mock conversions. Review and approve the mock conversion results document including delineation of responsibilities for actions resulting from the mock conversions. Decommission in scope Legacy Systems.
10.2.5.2
Cutover:
The SRS Avenues Conversion team will execute all of the cutover activities defined in the Cutover Plan. This Cutover Plan will define the dependency and successor activities necessary to successfully convert data from the KAECSES-AE, KsCares, and LIEAP legacy sources into the SRS Avenues solution. Version 5.0 Page 75
Contractor Responsibilities: Execute the Go-Live cutover plan for Conversion activities. State Responsibilities: Produce the source data files required to support Phase 2 Go-Live. Such files will comply with the extract and file specifications.
10.3
Responsibility Matrix
Contractor
Assist Assist Lead Lead Lead Assist Assist
SRS Team
Version 5.0
Page 76
10.4
Deliverables
The table below summarizes the data conversion deliverables/work products to be created during each phase:
Ref. No. Phase
Analyze 14
Description
The Eligibility Data Conversion Plan documents the requirements, manual and automatic procedures, and programs needed to extract data from the current applications. Existing data is formatted and cleansed prior to loading it into the new application. The plan will include itemized tasks, required resources, conversion strategy and required certification. The Conversion Data Dictionary (CDD) identifies and documents (in one repository) the SRS target data elements from the base APSP software. It is updated with mappings from the source data. The Data Conversion Design defines the manual and automatic procedures and programs needed to extract data from the current applications, cleanse it, and load it into the new application. Coordination with all involved parties, conversion timeline and possible issues and risks will be specified. Conversion tools and infrastructure requirements will be also be included. This deliverable is the conversion of data in a test environment. Data will be processed via the conversion process to format it to the standards of the new system. Conversion loads and manual updates are executed prior to data validation. The System Test Plan will include a Conversion Test Plan that documents the requirements needed to test Avenues requirements with converted data in an effort to deliver the required business functionality to the SRS users. Working in collaboration with SRS personnel, this deliverable will document the results of the final mock conversion. Each mock conversion will be executed in a production-size environment to simulate the actual cutover event, including schedule, resources and production data, and timings to best predict the length of time the conversion cutover will take.
NA
Design
NA
Design
NA
Build
Test 32
Deploy 25
Version 5.0
Page 77
11.0
The SRS Business Intelligence Services and Reporting team will be responsible for the design, configuration, testing, and deployment of reports as defined in the SRS scope. These tasks will include requirements validation, functional design, technical design, build and unit test, and system testing of the reports counts described in Section 11.1 Scope Definition. In addition, the team will leverage the Business Intelligence Services implemented for K-MED to support more advanced reporting features not achievable from the transactional application database like dashboards, drillable reports, and longitudinal analysis.
11.1
Scope Definition
The reports scope includes development of the 58 (fifty eight) undefined report complexities listed below in the reporting tool library. During the Analyze phase of the Avenues project SRS staff will have the opportunity to review reports that come with the system and determine which, if any, could (1) be modified as part of the reports scope/development effort., or (2) configured in an effort to make the report titles and headings specific to Kansas (i.e., SRS). Reports that require modifications would count against the 58 undefined reports; whereas, reports that are configured would not. The following reports complexities are in scope. During the Analysis Phase, the report inventory will be defined and confirmed.
Complexity
Simple
Examples
Report Count
17
Medium
Complex
A report containing one detailed list with no summary section. Totals may be included after the section. A report containing a summary and detail listing on the same report layout. The details may be broken into sections on a single grouping (example by Worker or by Program). Totals are included after each section, with the possibility of a grand total at the end. The same criteria as medium, except there could be many groupings/sections included on the report. An example of this is a report which breaks down by Recovery Account Type, and further subdivides by status, aid code, benefit month, etc.
34
Version 5.0
Page 78
11.2
11.2.1 11.2.1.1
The SRS Business Intelligence Services and Reporting team will work closely with the SRS Business Analysis team to define, validate, and confirm SRS reporting requirements. This serves to refine the requirements of the reports in scope. This step also includes defining strategy for use of the different reporting capabilities of SRS, and will describe the strategy for using the reporting database or Business Intelligence Services for reporting purposes. The reporting database is a copy of the Online Transactional Processing (OLTP) database which is used for canned reports and ad-hoc queries. The Business Intelligence Services provides a flattened data model to expand reporting capabilities which cannot be addressed in the OLTP data structure. Contractor Responsibilities: Attend meetings with State Functional SMEs to validate and elaborate reporting requirements. Define the types of reports and the purpose for the reporting and online analytical tools. Document high-level requirements for each report. Requirements should include intended use, frequency, and volume of transactions. Identify and document the roles for each report. Develop high level test conditions and expected results. Confirm and adjust Project Plan based on the outcomes of the Analyze Phase.
State Responsibilities: Provide Subject Matter Experts (SMEs) for each functional area that can efficiently and accurately define/describe required reporting requirements. Review and approve the report inventory. Review and approve documentation of high-level reporting requirements for each functional area. Review and approve high-level test conditions and expected results for each report. Make design decisions in a timely manner. Page 79
Version 5.0
Confirm and adjust Project Plan based on the outcomes of the Analyze Phase.
11.2.2
Design Phase
The Design Phase begins with specifications from the Analyze Phase, and ends with a list of tasks that, once performed in Build, will deliver the future state solution.
11.2.2.1
General designs will be created for each reporting work unit that was approved at the end of the Analyze Reports activity. Contractor Responsibilities: Produce General Design Documents for work units identified in the State-approved Reports inventory. General designs will be documented in a format which can be used in user manuals, system documentation and training materials. Plan Assembly Test of the approved reports. State Responsibilities: Review and approve the General Designs.
11.2.2.2
Produce Detailed Design documents for the reporting work units approved during the Analyze Phase. Contractor Responsibilities: Produce Detailed Design documents for Reporting work units. Unlike General (functional) Designs, these detailed (technical) designs are intended as technical specifications that can be executed by report developers. State Responsibilities: Review and approve each of the Detailed Design Documents.
11.2.3 11.2.3.1
The Reporting Team shall code and unit test reports approved in the Analyze Phase. Contractor Responsibilities: Leads in the coding of reports assigned to the Contractor. Version 5.0 Page 80
Leads in the creation of unit test scripts. Leads in the documentation of unit testing as part of the development documentation. State Responsibilities: Assists in the coding of reports assigned to the Contractor. Assists in the creation of unit test scripts. Review and approve unit test-scripts and unit test results developed by Contractor. Assists in the documentation of unit testing as part of the development documentation.
11.2.4
Test Phase
11.2.5
Deploy Phase
The Deploy phase shall deploy the necessary reports as defined in the requirements and specifications from the Analyze phase. Contractor Responsibilities: Deploy reports as documented through design and build activities Monitor the Deployment Readiness Checklist to prepare for SRS Deployment
State Responsibilities: Review Readiness Checklist and attend go/no-go decision meetings.
Version 5.0
Page 81
11.3
Responsibility Matrix
Contractor
SRS Team
11.4
11.4.1
Other Requirements
The SRS Business Intelligence Services will leverage the Warehouse Architecture and Warehouse Report Development scope from the K-MED implementation. The Incremental SRS Business Intelligence Services requirements include adding 17 (seventeen) extracts that are added as an Extract, Transform, and Load (ETL) to the Business Intelligence Services.
11.5
The table below summarizes the Business Intelligence Services and Reporting work products and deliverables to be created during each phase:
Ref. No.
10
Phase
Analyze
Deliverable Name
Reports Plan
Description
The Reports Plan is the primary deliverable resulting from the Analyze Phase. The Reports Plan consists of the report inventory and high level requirements defining data source, intended use, frequency. For each report a General and Detailed Design is completed. The designs for each report include the following: report layout, parameters, data access logic.
29
Design
Version 5.0
Page 82
12.0
The Avenues Automated Forms and Notices team is a sub-team of the development team. They work closely with the business analysts and will primarily be responsible for the conference room pilot, configuration, and testing of automated forms and notices as defined in the SRS Avenues scope. Their tasks will include requirements validation, mapping current APSP Notice of Action (NOA) snippets, forms, and notices to SRS Avenues forms and notices during conference room pilot. Then they configure and build forms and notices, execute unit test, and provide system testing support. This team includes resources from the SRS and the Contractor who work collaboratively to develop the forms and notices. The Contractor provides technical support in using the Adobe LiveCycle tool and the development of the forms and notices. This includes use of the Adobe LiveCycle tool, identifying database mapping to dynamically populate the forms and notices in accordance with requirements, and integration with other elements of the SRS Avenues application, such as the rules engine to populate Notice of Actions (if required). SRS will provide forms analysts/developers to assist in the development and testing of the forms and notices. This includes the provision of static content and text snippets that are dynamically pulled together through Adobe LiveCycle to create forms and notices. SRS staff are also responsible for the translation of text on forms in Non-English languages. The SRS Automated Forms and Notices Statement of Work (SOW) will reference the K-MED Automated Forms and Notices SOW as the SRS Avenues solution will be designed, built, tested, and implemented leveraging the technical infrastructure, methodologies, business processes, designs, and development phase activities that are defined in the K-MED Automated Forms and Notices SOW. There are, however, two differences between the K-MED and SRS Automated Forms and Notices solutions: The Forms and Notices listed in section 12.1 Scope Definition are specific to the SRS programs and business processes and not other agencies. Not only will dedicated SRS staff, assigned to the Forms and Notices team, be expected to provide (1) the static content and text snippets, and (2) the translation of text on forms in Non-English languages, they will also be responsible for the development of approx. 25% of the Forms and Notices listed in the section X.1 Scope Definition
Version 5.0
Page 83
12.1
Scope Definition
The scope for automated forms and notices include the forms and notices listed in the table below. The following are assumed related to the scoping of Automated Forms and Notices. Table 9 - Estimating Assumptions
Complexity
Simple
Definition
A static form that requires no data populations and is static. This is a form that is available via the K-MED application and is mailed out Form with 1- 5 fields populated with no complex calculations or interaction/content generated by the rules engine or a complex static form A complex form is one that includes either one or more complex calculation, interaction with the rules engine, or more than 5 fields populated. It also would include multiple snippets.
%
40%
Medium
40%
Complex
20%
Form Type
Form #
Form Title
Version 5.0
Page 84
Program
KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares
Form Type
Child Care Client Child Care Client Child Care Client Child Care Client Child Care Client Child Care Client Child Care Client Child Care Client Child Care Client Child Care Client Child Care Client Child Care Client Child Care Client Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs
Form #
C404 C502 C806 C807 C810 C811 C888 C899 C911 C912 C913 C914 C915 W001 W002 W006 W007 W101 W102 W103 W104 W106 W107 W108 W201 W202 W205 W206 W207 W251 W351 W353 W354 W355 W402 W404 W405 W407 W451 W452 W454 W455 Mass Case Transfer Termination Notice
Form Title
Child Care - Additional Benefits Child Care - Restoration of Benefits Child Care Service Plan Direct Pay Review Eligibility Notice EBT Child Care Parents Printer Family Plan - Remail Overpayment Claim Initiation - Repayment Agreement Overpayment Claim Change - Reduction Overpayment Claim Deletion Overpayment Claim Addition Overpayment Repayment Plan 1st Orientation Letter 2nd Orientation Appointment Letter 2nd Appointment Letter Education Activity Letter Training/Vocational Education Activity Letter Training/Vocational Education Approval - Denial Participation Review Request Non-attendance Notice General Correspondence Notice Of Taf Months/Schedule Review Work Experience Appointment Letter Work Experience 2nd Appointment Work Experience Assignment Letter Work Experience Evaluation Orientation to the World of Work Letter Life Skills Letter Job Search Letter Job Search Verification Job Contact Disallowance Job Club Letter Employment Letter Transitional Service Expiration Employment Follow-up Transitional Service Offer Self-sufficiency Plan Review 1st Letter Self-sufficiency Plan Review 2nd Letter Kansas Competency Assessment Letter Referral Letter
Version 5.0
Page 85
Program
KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares KsCares GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices
Form Type
Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Work Programs Child Care Provider Child Care Provider Child Care Provider Child Care Provider Child Care Provider Child Care Provider Child Care Provider Child Care Provider Child Care Provider Child Care Provider Child Care Provider Child Care Provider Child Care Provider Child Care Provider Child Care Provider Child Care Provider Approval Notice Approval Notice Approval Notice Approval Notice Approval Notice Approval Notice Approval Notice Approval Notice Approval Notice Approval Notice Approval Notice
Form #
W501 W502 W503 W504 W506 W507 W802 W806 W808 W888 W901 W911 W912 W913 P101 P102 P103 P104 P105 P201 P202 P304 P400 P502 P888 P901 P911 P912 P913 P914 G101 G104 G105 G106 G107 G113 G114 G115 G191 G192 G193 Notice of Change Notice of Closure
Form Title
1st Request for Information 2nd Request for Information Repayment - 1st Letter Repayment - 2nd Letter Check Enclosed Work Program Payment Work Experience Reimbursement Allowance EBT Mass Notice Returned Payment Repayment Agreement Overpayment Claim Reduction Overpayment Claim Deletion General Notice Rate Modification Request - CCC Rate Modification Request - Lic - Reg Rate Change Completed - CCC Rate Change Completed - Lic - Reg Denial or Termination Notice Eligibility Notice Review Eligibility Notice Child Care Time Sheet - Local Issue Provider Notice - Case Closed EBT Child Care Notice - Provider Returned Warrant Overpayment Claim Initiation - Repayment Agreement Overpayment Claim Change - Reduction Overpayment Claim Deletion Overpayment Claim Addition GA - APPROVAL FOR ONE MONTH ONLY DENIAL 1ST MONTH APPROVAL FOR 2ND MONTH DENIAL OF 1ST MO, APPROVAL OF 2ND & 3RD GA REVIEW COMPLETE GARN APPROVAL GA HARDSHIP APPROVAL FOR AGE OR GARN GA-TIER I HARDSHIP APPROVAL GA HARDSHIP APPROVAL - VR GA & FS APPROVAL FOR ONE MONTH ONLY GA AND FS APPROVAL FOR 1ST AND 2ND MONTH GA/FS APPROVAL 1ST, 2ND, & 3RD MONTHS
Version 5.0
Page 86
Program
GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices
Form Type
Approval Notice Denial Notice Denial Notice Denial Notice Denial Notice Denial Notice Denial Notice Denial Notice Denial Notice Denial Notice Denial Notice Denial Notice Denial Notice Denial Notice Denial Notice Denial Notice Denial Notice Denial Notice Denial Notice Denial Notice Denial Notice Denial Notice Denial Notice Denial Notice Denial Notice Denial Notice Denial Notice Closure Notice Closure Notice Closure Notice Closure Notice Closure Notice Closure Notice Closure Notice Closure Notice Closure Notice Closure Notice Closure Notice Closure Notice Closure Notice Closure Notice Closure Notice
Form #
G196 G200 G201 G202 G203 G204 G205 G207 G208 G209 G210 G211 G212 G214 G220 G221 G240 G290 G291 G292 G293 G294 G295 G296 G297 G298 G299 G400 G401 G402 G403 G404 G406 G407 G408 G409 G410 G411 G412 G413 G414 G417
Form Title
GA & FS REVIEWS COMPLETE GA - FAILURE TO PROVIDE INFORMATION GA - FAILURE TO COOPERATE RESIDENCY REQUIREMENT NOT MET GA - LOSS OF CONTACT TO THE FAMILY OF THE DECEASED GA - INCOME EXCEEDS MAXIMUM GA - RESOURCES EXCEED MAXIMUM GA DENIAL - OTHER REASONS GA - APPLICATION WITHDRAWN GA - INELIGIBLE ASSISTANCE UNIT GA - CITIZENSHIP/ALIEN STATUS GA DENIAL - 24 MONTH TIME LIMIT FAILURE TO MEET VULNERABILITY CRITERIA GA DENIAL - NON COOP WITH PMDT G221 GA DENIAL NON-COOP POST 45 DAYS GA - FAILURE TO APPLY FOR POTENTIAL BEN. GA & FS DENIAL\FAILURE TO PROVIDE INFO. GA AND FS DENIAL/FAILURE TO COOPERATE GA/FS DENIAL/RESIDENCY REQUIRMNT NOT MET GA & FS DENIAL LOSS OF CONTACT TO THE FAMILY OF THE DECEASED GA & FS DENIAL/INCOME EXCEEDS MAXIMUM GA & FS DENIAL/EXCESS NET INCOME GA AND FS DENIAL/RESOURCES EXCEED MAX. GA AND FS DENIAL/OTHER REASONS GA & FS DENIAL/APPLICATIONS WITHDRAWN GA FAILED TO PROVIDE/VERIFY INFORMATION GA FAILURE TO COOPERATE RESIDENCY REQUIRMENT NOT MET GA-LOSS OF CONTACT TO THE FAMILY OF THE DECEASED CLOSURE EXCESS NET INCOME CLOSURE RESOURCES EXCEED MAXIMUM GA CLOSURE - OTHER REASONS GA - CLOSURE AT CLIENT'S REQUEST GA-INELIGIBLE ASSISTANCE UNIT CLOSURE/NO LONGER GA VULNERABLE GA CLOSURE - 24 MONTH TIME LIMIT GA HARDSHIP CLOSURE GA/MEDIKAN CLOSURE 18 MTH LIMIT -TIER II GA CLOSURE - SSI APPROVAL
Version 5.0
Page 87
Program
GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices GA Notices FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES
Form Type
Closure Notice Closure Notice Closure Notice Closure Notice Closure Notice Closure Notice Closure Notice Closure Notice Closure Notice Closure Notice Closure Notice Closure Notice Reinstatement Notice Reinstatement Notice Reinstatement Notice Change Notice Change Notice Change Notice Change Notice Change Notice Change Notice Change Notice Change Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice Approval Notices Approval Notices Approval Notices Approval Notices Approval Notices Approval Notices
Form #
G420 G440 G450 G452 G490 G492 G493 G494 G496 G497 G498 G499 G600 G601 G602 G701 G702 G703 G704 G706 G713 G751 G753 G801 G827 G828 G830 G831 G832 G834 G850 G851 G852 G853 G854 F101 F102 102F F103 103F F104
Form Title
GA CLOSURE -NON COOP W/PMDT FAILURE TO APPLY FOR POTENTIAL BENEFITS FAILURE TO COMPLETE REVIEW TIME LIMITED PROGRAM - GARN GA & FS CLOSURE-FAILURE TO PROVIDE INFO CLOSURE/RESIDENCY REQUIREMENT NOT MET GA AND FS CLOSURE/LOSS OF CONTACT TO THE FAMILY OF THE DECEASED GA AND FS CLOSURE/EXCESS NET INCOME GA AND FS CLOSURE/EXCESS RESOURCES GA AND FS CLOSURE/OTHER REASONS GA AND FS CLOSURE/CLIENT REQUEST GA-REINSTATE AFTER SUSPENSION ERRONEOUS DISCONTINUANCE BENEFITS PAID PENDING HEARING DECISION CHANGE IN BENEFITS - OTHER REASONS SUPPLEMENTAL BENEFITS CHANGE IN HOUSEHOLD MEMBERS GA - CHANGE IN BENEFITS/INCOME CHANGE CHANGE IN BENEFITS/LIVING ARRANGEMENTS GA CHANGE IN BENEFITS-RECOUPMENT GA/FS CHANGE IN HOUSEHOLD MEMBERS GA/FS CHANGE IN BENEFITS-RECOUPMENT CASELOAD TRANSFER GA FRAUD DISQUALIFICATION - NONRECIPIENT GA FRAUD DISQUALIFICATION - PERMANENT GA FRAUD DISQUALIFICATION--RECIPIENT GA REPAY AGREEMENT - FRAUD - RECIPIENT GA REPAY AGREE.-AGENCY/CLIENT RECIPIENT GA-REPAYMENT AGREEMENT-NON RECIPIENT GA-SOCIAL SECURITY APP NEEDED GA-SOCIAL SECURITY APP NEEDED GA-SSA APP NEEDED-NEW CLIENT GA-SOCIAL SECURITY APP PENDING GA - TIME LIMIT INFORMATION FS - APRVL FOR ONE MONTH ONLY FS APRVL FOR 1ST & 2ND MONTHS APROB. DE FS PARA EL 1ER Y 2DO MES FS APPRVL 1ST, 2ND AND 3RD MOS. APROB. DE FS PARA EL 1ER, 2DO Y 3ER MES FS DENY 1ST MONTH/APPR. 2ND MO.
Version 5.0
Page 88
Program
FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES
Form Type
Approval Notices Approval Notices Approval Notices Approval Notices Approval Notices Approval Notices Approval Notices Approval Notices Approval Notices Approval Notices Approval Notices Approval Notices Approval Notices Approval Notices Approval Notices Approval Notices Approval Notices Approval Notices Approval Notices Approval Notices Approval Notices Denial Notices Denial Notices Denial Notices Denial Notices Denial Notices Denial Notices Denial Notices Denial Notices Denial Notices Denial Notices Denial Notices Denial Notices Denial Notices Closure Notices Closure Notices Closure Notices Closure Notices Closure Notices Closure Notices Closure Notices Closure Notices
Form #
F105 F106 106F F107 107F F111 F112 F113 F114 F115 F120 F121 F130 F131 F132 F133 F134 F135 F137 F138 F139 F200 F201 F202 F203 F205 F207 F208 F209 F210 F211 F216 F221 F230 F400 F401 F402 F403 F404 F405 F407 F408 FS REVIEW COMPLETE
Form Title
FS DENIAL 1ST MO., APPRVL 2/3 MOS REVISIN DE FS COMPLETA FS REVIEW COMPLETE - IR REQUIRED FS REVISIN COMPLETA - SR REQUISITOS FS APRVL FOR ONE MONTH ONLY + IR REQ FS APRVL FOR 1ST/2ND MOS + IR REQ FS APPRVL 1ST/2ND/3RD MOS. + SR REQ. FS DENY 1ST MO./APPR. 2ND MO. + IR. REQ. FS DENY 1ST MO./APPR 2/3 MOS + IR REQ. FS APPROVAL FOR 1ST/2ND MOS.- REMOTE PIN EXPEDITED FS - POSTPONED VERIFICATION FS DISASTER ASSISTANCE APPROVED FS APRVL FOR ONE MONTH ONLY - NO IR REQ FS APRVL FOR 1ST/2ND MOS - NO IR REQ FS APPRVL 1ST/2ND/3RD MOS. - NO IR REQ FS DENY 1ST MO./APPR. 2ND MO.- NO IR REQ FS DENY 1ST MO. APPR 2/3 MOS.- NO IR REQ FS REVIEW COMPLETE - NO IR REQUIRED FS APPR. 1/2 MOS SI/24 MO REV PER FS APPROVAL FOR 1/2 MOS - NO REPORTING REQUIREMENT FAILURE TO PROVIDE INFO./REACTIVATE APP. FS - FAILURE TO COOPERATE RESIDENCY REQUIREMENT NOT MET FS - LOSS OF CONTACT FS DENIAL-INCOME EXCEEDS STANDARDS FS - RESOURCES EXCEED MAXIMUM FS DENIAL - OTHER REASONS FS - APPLICATION WITHDRAWN FS - DOES NOT MEET HOUSEHOLD REQUIREMENT FS DENIAL - CITIZENSHIP/ALIEN STATUS FS DENIAL - ABAWD REQUIREMENTS NOT MET FS STUDENT ELIGIBILITY CRITERIA NOT MET FS DISASTER PROGRAM DENIAL FAILURE TO PROVIDE OR VERIFY INFORMATION FS CLOSURE - FAILURE TO COOPERATE FS - RESIDENCY REQUIREMENT NOT MET LOSS OF CONTACT TO THE FAMILY OF THE DECEASED INCOME EXCEEDS STANDARDS FS - RESOURCES EXCEED MAXIMUM FS CLOSURE - OTHER REASONS
Version 5.0
Page 89
Program
FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES
Form Type
Closure Notices Closure Notices Closure Notices Closure Notices Closure Notices Closure Notices Closure Notices Closure Notices Closure Notices Closure Notices Reinstatement Notices Reinstatement Notices Reinstatement Notices Reinstatement Notices Reinstatement Notices Change Notices Change Notices Change Notices Change Notices Change Notices Change Notices Change Notices Change Notices Change Notices Change Notices Change Notices Change Notices Change Notices Change Notices Change Notices Change Notices Change Notices Change Notices Misc. Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice
Form #
F409 F410 F412 F416 F421 F422 F424 F426 F448 448F F600 F601 F602 F604 604F F701 F702 F703 F704 704F F705 F706 F707 F708 F709 F711 F712 F713 F716 F744 F745 745F F746 F801 F827 F828 F830 F831
Form Title
FS - CLOSURE AT CLIENT REQUEST NO LONGER MEETS HOUSEHOLD REQUIREMENT FS CLOSURE - WORK PENALTY FS CLOSURE - ABAWD REQUIREMENTS NOT MET FS STUDENT ELIGIBILITY CRITERIA NOT MET FS - RESIDING IN AN INSTITUTION FS - 1 PERSON HH DISQUALIFIED FOR FRAUD FS - ADDED TO ANOTHER ACTIVE CASE FS - IR NON-RECEIPT NOTICE FS - IR AVISO DE NO RECIBO FS - REINSTATE AFTER SUSPENSION FS - ERRONEOUS DISCONTINUANCE BENEFITS PAID PENDING HEARING DECISION FS IR REINSTATEMENT NOTICE FS IR AVISO DE REINCORPORACIN FS - CHANGE IN BENEFITS/OTHER REASONS FS - SUPPLEMENTAL BENEFITS FS - CHANGE IN HOUSEHOLD MEMBERS FS - CHANGE IN BENEFITS/INCOME CHANGE CAMBIOS EN INGRESOS/BENEFICIOS DE FS CHG IN BENEFITS/INC CHG NO DEP CARE VERI FS INTERIM REPORT REVIEW COMPLETE FS-SSI 12 MONTH REPORT REVIEW COMPLETE CHANGE IN BENEFITS/CHANGE IN HH DEDUCTS. FS CHANGE - WORK PENALTY FS CHANGE - CITIZENSHIP/ALIEN STATUS FS-CHANGE TO ZERO BEN./INFO. PENDING FS CHANGE IN BENEFITS-RECOUPMENT FS CHG IN BENEFITS - ABAWD REQUIREMENTS CHANGE DUE TO COOPERATION/WORK PROGRAMS FS - MASS CHANGE/BENEFIT CHANGE MODIFICACIN EN LOS BENEFICIOS FS - CHANGE IN BENEFITS - 2 MONTHS CASELOAD TRANSFER FRAUD DISQUAL.-NONPARTICIPATING INDIVID. FRAUD DISQUALIFICATION - PERMANENT FRAUD DISQUAL.-PARTICIPATING INDIVIDUAL REPAY AGREEMENT - FRAUD - PARTICIP. HH
Version 5.0
Page 90
Program
FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES FS NOTICES Collateral Contact Notices Collateral Contact Notices Collateral Contact Notices Collateral Contact Notices Collateral Contact Notices Collateral Contact Notices Collateral Contact Notices Collateral Contact Notices Collateral Contact Notices Collateral Contact Notices
Form Type
Misc. Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice Misc. Notice
Form #
831F F832 832F F833 833F F834 834F F835 835F F839 F841 F842 F843 843F F844 F845 F846 F847 847F F849 F850 I001 I002 I003 I004 I005 I010 I011 I012 I013
Form Title
ACUERDO DE REPAGO - FRAUDE - PARTICI. HH REPAY AGREE. - AGENCY/CLIENT PART. HH ACUERDO DE REPAGO - AGENCIA/CLIENTE PART REPAY AGREE. AGENCY/CLIENT NONPART HH ACUERDO DE REPAGO - AGENCIA/CLIENTE NO P REPAY AGREEMENT -FRAUD - NONPARTICIP. HH ACUERDO DE REPAGO - FRAUDE - NOPART. HH REPAYMENT AGREEMENT ACUERDO DE REPAGO FS - NOTICE OF LOST BENEFITS NOTICE OF LOST BENEFITS WITH OFFSETTING ELIGIBILITY FOR FREE SCHOOL MEALS FS INTERIM REPORT FORM FS FORMULARIO DE INFORME PROVISIONAL FS - NOTICE OF RESTORED BENEFITS FS-IMPORTANT INFORMATION (ABAWD) CHANGE REPORT FORM INTERIM REPORT INCOMPLETE NOTICE AVISO DE INFORME PROVISIONAL INCOMPLETO FS-IMPORTANT INFORMATION - ABAWD/ICT FOOD STAMP ADJUSTMENT NOTICE EMPLOYER LETTER LANDLORD LETTER BANK LETTER LIFE INSURANCE LETTER GENERAL CORRESPONDENCE TO COLLATERALS REPAY LETTER TO TREATMENT CENTER FIELD NOTICE-EXPUNGED FS/CASH CLAIM CHG FUNERAL AGREEMENT REFERRAL ANNUITY REFERRAL
NOTE: This list of forms represents the current forms used by SRS, and a scope of 299 forms to be developed as part of the Avenues Solution. During the analyze and design phase, these forms may change, or different forms/notices may be used to accomplish the same thing. These changes will be captured in the design documents. Once Detailed Design is complete, the forms will be locked and any future changes must follow the Project Change Management procedures .
Version 5.0
Page 91
12.2
12.2.1 12.2.1.1
The Automated Forms and Notices Team will work closely with the SRS - AVENUES Business Analysts to validate and confirm SRS - AVENUES forms and notices requirements. This serves to refine the requirements of the forms in scope. This step also includes reviewing the forms available in the APSP application to map, where appropriate, to the existing SRS - AVENUES forms and notices. Contractor Responsibilities: Attend meetings with SRS Functional SMEs to validate forms and notices. Setup and configure the Adobe LiveCycle and provide on the job training support. Document existing in scope SRS - AVENUES forms and notices. Lead review and mapping of in scope SRS - AVENUES forms and notices to existing templates in APSP. Confirm and adjust Project Plan based on the outcomes of the Analyze Phase.
State Responsibilities: Provide copies of all existing forms and notices that are currently in scope. Attend and participate in forms and notices review. Provide Subject Matter Experts (SMEs) for each functional area that can efficiently and accurately document/describe required forms and notices requirements and population. Review and approve the forms and notices inventory. Make design decisions in a timely manner. Confirm and adjust Project Plan based on the outcomes of the Analyze Phase.
12.2.2
Design Phase
The Design Phase begins with specifications from the Analyze Phase, and ends with a list of tasks that, once performed in Build, will deliver the future state solution.
Version 5.0
Page 92
Forms and notices designs will be created for each form or notice that identifies the static content, the definition of the dynamically populated fields if required for the form or notice, and the identification of corresponding APSP template where applicable. Contractor Responsibilities: Produce General Design Documents for Contractor assigned forms identified in the Stateapproved RICEFW inventory. Plan Integration Test of the approved forms and notices.
State Responsibilities: Produce General Design Documents for Contractor assigned forms identified in the Stateapproved RICEFW inventory. Plan Integration Test of the approved forms and notices. Review and approve the General Designs.
12.2.3 12.2.3.1
The Forms Team shall configure, modify and unit test forms approved in the Analyze Phase. Contractor Responsibilities: Configure, modify and/or develop, and unit test forms assigned to the Contractor. Conduct and document unit testing as part of the development documentation. Provide technical support on Adobe LiveCycle for team. State Responsibilities: Configure, modify and/or develop, and unit test forms assigned to the Contractor. Conduct and document unit testing as part of the development documentation. Provide technical support on Adobe LiveCycle for team. Review and approve the forms and notices, unit test-scripts and unit test results developed by Contractor.
Version 5.0
Page 93
12.2.4 12.2.5
The SRS Project Team shall deploy the forms approved in the Analyze Phase. Contractor Responsibilities: Deploy the forms documented through design and build activities Monitor the Deployment Readiness Checklist to prepare for SRS Deployment State Responsibilities: Review Readiness Checklist and attend go/no-go decision meetings.
12.3
Responsibility Matrix
Contractor
SRS Team
12.4
The table below summarizes the Forms and Notices work products and deliverables to be created during each phase:
Ref. No.
NA NA
Phase
Analyze Design
Work Product
Forms and Notices Inventory Forms Design
Deliverable
Description
A listing of forms and notices in scope with a mapping to templates if any in APSP. The General Design lists the forms static content, the definition of the dynamically populated form fields if
Version 5.0
Page 94
Ref. No.
Phase
Work Product
Deliverable
Description
required for the form, and the identification of corresponding APSP form/template where applicable.
15
Build
Delivery of the forms and notices source code, unit test scripts and execution results.
Version 5.0
Page 95
13.0
The SRS Imaging and Content Management Statement of Work (SOW) will reference the K-MED Imaging and Content Management SOW as the SRS solution will be designed, built, tested, and implemented leveraging the technical infrastructure, methodologies, business processes, designs, and development phase activities that are defined in the K-MED Imaging and Content Management SOW. There is, however, one difference between the K-MED and SRS Imaging and Content Management solutions and that is the document types that are scanned by eligibility workers. These document will be identified during the analysis and design phases of the SRS project. In addition to the scope defined in the Imaging and Content Management sections below, Accenture will also support SRS staff in the establishment of Central Records Center. Support will include planning discussions during the Analyze and Design as well as guidance during the Build and Deployment phases of the Central Records Center. Both SRS and Accenture agree that SRS will take the lead in the operations of the Central Records Center.
13.1
Scope Definition
The necessary document types (i.e., documents that will be scanned, categorized, and accessed through the Avenues system) will be identified during the analyze and design phases of the SRS project.
13.2
The table below summarizes the Imaging and Content Management work products and deliverables to be created during each phase:
Ref. No.
29
Phase
Deliverable Name
Detailed System Design
Work Products
Description
The Functional and Detailed Design Document details the functional and technical requirements for developing, testing, and implementing the Content Management solution for SRS.
NA
The ECM Interim Solution involves rapidly developing and deploying the standalone imaging solution. The ECM Eligibility Integration occurs after Document Conversion has competed (or reached an acceptable level). This deliverables marks the integration of the interim solution into the Eligibility and Web Portal systems.
NA
Version 5.0
Page 96
14.0
Enterprise Readiness
The Enterprise Readiness Team prepares SRS users for the transition to the new integrated KMED/Avenues system and business processes. Because the K-MED implementation affects SRS workers, the K-MED Scope of Work includes enterprise readiness and communication initiatives aimed at supporting SRS personnel through the transition. The readiness activities in the K-MED Scope of Work, such as identifying process and role gaps, producing Change Discussion Guides to explain new processes, and conducting Readiness Workshops with Change Agents are targeted toward SRS users who use K-MED for medical eligibility. Activities in the SRS Scope of Work are an incremental add to the K-MED SOW to address the Avenues-specific processes. The Enterprise Readiness team will be comprised of representatives from the State project team and Contractor.
14.1
14.1.1
Analyze Phase
During the Analyze Phase, the team produces the Stakeholder Assessment and Stakeholder Management Plan, Enterprise Readiness Plan and Communication Plan that define the scope and contents of the Enterprise Readiness activities for the project.
14.1.1.1
An input into the Enterprise Readiness Plan is the Stakeholder Assessment and Stakeholder Management Plan. The Stakeholder Assessment document identifies internal and external (e.g. customer) stakeholders and assesses the type and extent of impacts they will experience from the Avenues implementation. The Stakeholder Management Plan outlines how the project will develop support among the key stakeholders by involving them in project activities. The results of the assessment will feed into the Communication Plan. Contractor Responsibilities: Work with the State to identify key internal/external stakeholders and the key impacts for each group Define initiatives to keep key stakeholders involved throughout the project Develop the Stakeholder Management Plan
Version 5.0
Page 97
State Responsibilities Provide information to the Contractor regarding key internal/external stakeholders and impacts, including organization charts Coordinate meetings with any groups necessary to complete the assessment and plan Provide input into the Stakeholder Management Plan Review and approve the Stakeholder Management Plan content that will become a part of the overall Enterprise Readiness Plan deliverable
14.1.1.2
The Enterprise Readiness Plan describes the overall approach to conducting readiness activities for SRS. It describes the Enterprise Readiness tools and processes and provides a high-level schedule. The Enterprise Readiness Plan also describes how the SRS Enterprise Readiness initiatives build on and integrate with K-MED change activities. Contractor Responsibilities: Using input from the State, develop the Enterprise Readiness Plan State Responsibilities Coordinate meetings with any groups necessary to complete the plan Provide input into Enterprise Readiness Plan Review and approve the Enterprise Readiness Plan deliverable
14.1.1.3
The Enterprise Readiness Team will create the Communication Plan. The plan will identify stakeholders, information needs, key messages, methods, senders, and schedule. It will also describe methods for collecting feedback on the effectiveness of the communication initiatives. Because there is a great deal of overlap between the K-MED Communication Plan and the Avenues Communication Plan, the document will address how to coordinate communication methods and timing to provide the most effective communication for SRS employees. Contractor Responsibilities: Create the Avenues Communication Plan and define the messages and delivery methods
Version 5.0
Page 98
State Responsibilities: Assist the Contractor in the development of the Communication Plan. Assistance would include identification and input regarding stakeholders, messages, and delivery methods. Review and approve Communication Plan deliverable Review and approve communication materials
14.1.2
Design Phase
During the Design phase, the Enterprise Readiness Team designs the readiness tools, methods and materials to facilitate readiness and transition for stakeholders, as identified in the Enterprise Readiness Plan. They also support Road Shows to kick off Phase 1 and 2 for system users.
14.1.2.1
The Enterprise Readiness team supports the Road Show effort by providing communication materials such as a PowerPoint presentation to be used during the meetings. Contractor Responsibilities: Work with the State to plan the agenda for the Road Shows Create Road Show materials State Responsibilities: Provide input and review for Road Show materials Determine Road Show locations Conduct Road Shows
14.1.2.2
During this phase, Accenture will support the State in identifying KDHE-HCF and SRS personnel who will serve as Change Agents and Regional Implementation Leads. Change Agents are staff who help their local offices adapt to changing business processes and prepare for implementation, and who support their peers in the days and months following implementation. Change agents can represent any area of the business affected by the upcoming process changes. Each local office will identify one or more Change Agents who will assist their offices with K-MED and Avenues changes. Also during this phase, State Enterprise Readiness team members identify Regional Implementation Leads who will monitor readiness at a regional level. The Regional Implementation Lead is the person responsible for supporting, monitoring and reporting on production transition readiness for all locations Version 5.0 Page 99
in the region. The ER team works with the Regional Implementation Leads to conduct readiness reviews at 90, 60, and 30 days prior to go-live, and weekly during the month prior to deployment. The effort to organize and manage the Change Agent program and work with the Regional Implementation Leads is included in the K-MED Scope of Work. Please refer to the K-MED Scope of Work for details and responsibilities.
14.1.2.3
Accenture and State Enterprise Readiness team members document the major functional differences between the current systems and the integrated K-MED and Avenues system. In addition, the team facilitates business process reviews (as-is versus to-be) to define the differences between the current environment and the future environment. The project will define up to four to-be business process models that align with the different types of local offices. The SRS SOW includes the incremental work to analyze the gaps for Avenues-related functionality and business processes. Contractor Responsibilities: Use information from fit gap activities and other project documentation to document functional differences Conduct business process reviews (work with business analysts, state personnel, etc. to receive the appropriate input) Document the future business processes Document gaps between the current and future processes State Responsibilities: Provide existing as-is analysis Participate in documenting functional differences Participate in process reviews Participate in documenting revised business processes and gaps Review and approve the process and role gap documentation
14.1.2.4
Enterprise Readiness Team members develop Change Discussion Guides that describe the changes that affect job functions and roles. They then conduct Readiness Workshops with the Change Agents to explain the information in the guides and prepare the Change Agents to deliver the material back in their own areas. The workshops provide an overview of the new business processes and provide tools Version 5.0 Page 100
and aides to facilitate the local offices in identifying impacts and specific actions to prepare for implementation. Change Agents use the guides to generate discussion among managers, supervisors and staff in their locations about how business processes and job roles would change with the new system. Contractor Responsibilities: Design the Change Discussion Guides and other workshop content and material using baseline materials as input. Other workshop materials include PowerPoint presentations to present the new enterprise business processes, as well as checklists or desk aides to provide assistance, tools, and templates to help offices assess impacts and document actions. (NOTE: The Enterprise Readiness team creates desk aids that refer specifically to the tools and procedures that would help local offices plan for the upcoming business process changes and prepare for implementation these documents will not be needed after post implementation support. The training team, however, creates job aids that relate to tasks users perform in the system these documents persist over time) State Responsibilities: Participate in the design of the materials. This would include providing content and/or development of specific portions of assigned workshops. Review and approve Change Discussion Guides and workshop materials
14.1.2.5
The Enterprise Readiness team creates and delivers specific communication messages, materials and events as outlined in the updated Communication Plan. The team reviews and updates the Communication Plan quarterly to include specific stakeholder information and specific communications messages, timing, and events. This task is repeated for each phase. Contractor Responsibilities: Work with SRS to update the Communication Plan on a quarterly basis to address stakeholder feedback and to reflect new information regarding specific stakeholders and specific communications messages, timing, and events Implement communication initiatives specified in the Communication Plan State Responsibilities: Produce/deliver communications with help and guidance from the Contractor Provide input and review for communication materials and initiatives Version 5.0 Page 101
14.1.2.6
Scope Description to Develop an Office of the Future Demonstration Accenture will develop a demonstration for state staff to show them the types of business process and functional changes that they will implement with Avenues. This demonstration will be a prototype of the Office of the Future. This is a description of the scope for the development of the Office of the Future prototype. Purpose of the Office of the Future Demonstration The purpose of the Office of the Future demonstration is to: Visually demonstrate to state staff the changes to work processes that they will experience with the implementation of Avenues. Allow staff time to view the prototype from their workstations, at their convenience, and to generate ideas and questions for discussion with their supervisors and teams Demonstrate the interaction of business processes with new functionality, including selfservice portals, document imaging, interactive voice response, Call Center, and data interfaces Replace the use of Change Discussion Guides (included in our original proposal) with this visual, self-paced, hands-on change management tool.
Approach to Creating the Office of the Future Demonstration During the Analysis and Design Phases of the Project, Accentures change management staff will facilitate sixteen sessions with users to develop the To-Be business processes. The purpose of these sessions is to identify the transitions required to move from the As-Is business processes to the To-Be business processes. Using the To-Be processes, we will develop a Avenues demonstration that will replace the need for creation and deployment of Change Discussion Guides. We will show the prototype during a Conference Room Pilot (CRP). The state team will verify the Avenues system implements state processes correctly and meets requirements, as they see those processes. By actually seeing the business process changes and the relation to the Avenues system, state users will get a clear demonstration of how the changes will work. The Office of the Future demonstration will be used by each group of staff, at their workstations, prior to Pilot and prior to each Phase, to prepare them for the business process changes that will occur. The Office of the Future will be flexible, in that individuals can view it as many times as they like, then teams Version 5.0 Page 102
could watch portions of it and discuss how they see it working in their office locations. The use of the prototype should reduce the demand on line staffs time to attend meetings. We will develop the Office of the Future Demonstration using portions of the Avenues prototype and a variety of other multi-media sources. We will develop the Demonstration using Adobe Captivate software (which is already included in our proposal as the training development tool). We will develop video presentations of new process flows in an office-like environment, by setting up a model office which will be recorded at the Project site. Members of the Project team will walk through the new business processes, showing integration of new system features into the business flows. A voice-over will unify the presentation, as workers move from viewing the video, to looking at Avenues pages (screens), and learning about the changes from As-Is to the To-Be processes that are relevant to their roles. The end product will be a richly layered web-based module that Avenues system users can launch at their workstations. Workers will be able to select and view clips of the demonstration directly relevant to their worker roles. It will include information about To-Be processes that was formerly to be included in the Change Discussions Guides, but with the added features of visual and graphic demonstrations. The Office of the Future will address the following change management and readiness needs: Creating a shared language (new Avenues system terminology) and vision among leaders and staff from different agencies, programs and locations Introducing business process changes and new functionality in a visual and engaging manner Supporting users as they transition to a new way of working which may include unfamiliar technology (such as Interactive Voice Response, Imaging, and call centers) Building support for changing job roles and skill needs among staff from KDHE, SRS, and other organizations Meeting the complex logistical and project management requirements of a phased Enterprise Readiness implementation the size and scope of Avenues
Readiness team members will work with state subject matter experts and members of the Accenture functional/business teams to document how new business processes and the Avenues system will affect the various Avenues user groups. Information from this analysis helps inform several activities, including skills and gap analysis, as well as role mapping. As a part of the role mapping process, the team will complete following tasks, as they would have done to create Change Discussion Guides: Identify current roles within the organizations affected by the Avenues implementation (SRS locations, provider locations, etc.) Page 103
Version 5.0
Map existing roles to current (As-Is) business processes and events Identify future (To-Be) business processes Identify the changes in roles that are required to support the new business processes Analyze relationships between roles and how those relationships will be affected by the Avenues implementation Revise roles which support new business processes as required The Enterprise Readiness team will integrate information about revised roles into the Office of the Future demonstration.
Additional Option for Business Process Improvement Change and Innovation Agency As we develop the Office of the Future demonstration, we also offer an added feature of Business Process Improvement (BPI). We have successfully delivered BPI with state agencies across the nation and other government institutions around the globe, working with our clients to fit their business to the capabilities of solutions. We would tailor our approach to the specific needs of the Avenues project by leveraging our teams experience in implementing human services solutions in 37 states in the U.S. The tailored methodology also leverages our experience implementing integrated human services solutions to provide a more focused methodology for the K-MED Project. Business Process Improvement is a key focus of our successful record in Accentures Public Service Operating Group. With our BPI approach, we have helped numerous public service clients to streamline and re-engineer business processes. We also team with the Change and Innovation Agency, which is a company based in Kansas City, and a leader in bringing process improvements to state agencies. Change and Innovation Agency (CIA) provides leadership consulting and practical process guidance to help teams be more productive. They have worked in agencies in all 50 states to change behaviors, preconceptions, and to drive innovative changes to process. They help teams re-imagine the work that they do and the outcomes they generate and eliminate the kinks in the pipe that limit productivity. As an added feature of the Office of the Future, we propose that we leverage CIA in the Analysis Phase of the Avenues project to conduct several workshops. The purpose of these workshops would be to help set project mindset in the direction of positive process changes and to engage leadership in the possibilities. Systems automate processes; and Kansas has the opportunity to automate the most efficient and supportive processes. CIA can help achieve that outcome. We will incorporate the outcomes of these workshops into the Design Phase for developing the To-Be processes for the Office of the Future demonstration. Impact on Project Timelines
Version 5.0
Page 104
The development of the Office of the Future demonstration and prototype can be accomplished within the existing Project timeframes, to keep all Phases on schedule as planned. This can be done by modifying the timing for some of the previously planned cultural change management work and inserting a prototype development effort. The additional effort for this work is estimated to be 6 person months of Accenture staff (2 people for 3 months). This work will be scheduled to begin during the Design phase and complete during the Build phase of the Project. The prototype will then be ready for use in the field by Avenues system users, supervisors, SRS offices, providers, and Central office staff in time to prepare for implementations. Impact on Project Cost: The Office of the Future would cost $199,397. This includes the addition of two Accenture resources for 3 months to develop the Office of the Future demonstration during the Analysis and Design Phases, and 3 workshops conducted for state leadership and management during the Analysis Phase of the Project. However, this cost is potentially offset by a savings in the need for as many state staff for change readiness activities as was originally anticipated. Because the Office of the Future could replace the need for change agents in each location to train staff on Change Discussion Guides, the amount of time needed for each of the States local change agents could be reduced by potentially as much as 50%.
14.1.3
Build Phase
During the Build phase, the Enterprise Readiness team continues to interact with users and change agents in support of the readiness activities outlined in the Enterprise Readiness Plan. The team defines roles and conducts role mapping, defines the tools and metrics to measure readiness, conducts the first readiness assessments, develops workshop content and continues developing and delivering detailed communication messages.
14.1.3.1
The Enterprise Readiness Team will develop the Change Discussion Guides and workshop materials. Contractor Responsibilities: Develop the Change Discussion Guides and other workshop content and material. Other workshop materials include PowerPoint presentations to present the new enterprise business processes, as well as checklists or job aides to provide assistance, tools, and templates to help offices assess impacts and document actions. State Responsibilities: Support the Contractor in the development of the materials. This could include providing content and/or development of specific portions of assigned workshops. Version 5.0 Page 105
Help local offices identify the appropriate representatives to attend sessions Review and approve Change Discussion Guides and workshop materials
14.1.3.2
The Enterprise Readiness team documents detailed descriptions of new and/or revised roles. Role descriptions include a role definition, description of responsibilities, skill/knowledge requirements, relationships to other roles, and a summary of change impacts associated with the role. Once role descriptions are complete, the team uses the role mapping process defined during Design phase to implement the role mapping activities. Contractor Responsibilities: Define and document descriptions for each role Provide the tools, templates and processes defined in the Role Mapping approach Support the State in role mapping activities by helping to troubleshoot the process and/or answer rolerelated questions Coordinate the receipt of the role mapping information with the Security team State Responsibilities: Use the Role Definitions and Role Mapping processes and tools to map end-users to appropriate roles within the timeframe suggested Designate functional SMEs to review the role descriptions for accuracy and alignment to the new business processes
14.1.3.3
The Enterprise Readiness team continues to create and deliver specific communication messages, materials and events as outlined in the updated Communications Plan (see above for responsibilities).
14.1.3.4
During the Build phase, the K-MED Enterprise Readiness team creates the tools and templates to use for readiness assessment and tracking. The Assess and Report Readiness effort is included in the K-MED Scope of Work. The following templates are samples for a Personal Learning Plan and Scorecard. As mentioned above, the actual templates used for Avenues will be developed by the K-MED Enterprise Readiness team.
Version 5.0
Page 106
Describe key features and functions of Oracle Policy Automation Small Group Walkthrough (OPA) Understand OPA Components and Architecture Small Group Walkthrough
Ben to ask follow-up questions as needed Ben to ask follow-up questions as needed Ben to ask follow-up questions as needed
N/A Matt Berry TBD TBD Not Started N/A N/A TBD TBD Not Started N/A
Version 5.0
Page 107
Scorecard
During this phase, the ER Team will orient the Regional Implementation Leads who will monitor readiness at a regional level. The team will work with the Regional Leads to conduct a readiness review at 90, 60, and 30 days prior to go-live, and weekly during the month prior to deployment. The team will track readiness in an overall tracking tool that contains each location and the readiness status. Readiness results are used as input into deployment go/no-go decisions. Go/no-go meetings will review these regional readiness assessments, along with application readiness, environment readiness and support readiness. Contractor Responsibilities: Create and distribute readiness checklist Conduct readiness assessments Analyze, summarize and report on readiness assessment results State Responsibilities: Participate in reviews Version 5.0 Page 108
Review and approve readiness checklist Assist contractor in the review of assessment results and the preparation of the summary report
14.1.4
Test Phase
During the Test phase, the Enterprise Readiness team delivers specific communication messages as defined in the updated communication plan and will continue to support readiness tasks, assess and report readiness, and provide outreach and support to users as they prepare for implementation.
14.1.5 14.1.5.1
During the Deploy phase, the Enterprise Readiness team conducts the readiness assessments, analyzes the results and prepares a report of the assessment findings. The team will conduct a readiness review at 90, 60, and 30 days prior to go-live, and weekly during the month prior to deployment. Contractor Responsibilities: Create and distribute the applicable readiness checklists for this phase Conduct readiness assessments Analyze, summarize, and report on the readiness assessment results State Responsibilities: Review and approve the readiness checklists for this phase Participate in readiness reviews Assist the Contractor in the review of the assessment results and the preparation of the summary report
14.1.5.2
The Enterprise Readiness team continues to create and deliver specific communication messages, materials and events as outlined in the updated Communications Plan (see above for responsibilities).
Version 5.0
Page 109
14.2
Responsibility Matrix
The table below summarizes the responsibilities associated with Enterprise Readiness and Communication:
Scope Element
Create Stakeholder Assessment and Stakeholder Management Plan Develop Communication Plan & Delivery Methods Create communication tools and delivery Create Enterprise Readiness Plan Meeting Logistics Identify System, Process and Role Gaps Develop Change Discussion Guides Readiness Workshop Development (who, when, how, how many) Readiness Workshop Presentation Role Definition Role Mapping using above definitions Create readiness assessments Lead Lead Lead Assist Lead Lead Lead Lead Lead Lead Lead
Contractor
Assist Assist Assist Assist Lead Assist Assist Assist Lead Assist Assist Assist
State
14.3
Other Requirements
None identified.
14.4
Deliverables
The table below summarizes the Enterprise Readiness deliverables to be created during each phase:
Ref. No.
NA
Phase
Analyze
Deliverable Name
Stakeholder Assessment and Stakeholder Management Plan (work product not a paid deliverable)
Description
The Stakeholder Assessment document identifies internal and external stakeholders and assesses the type and extent of impacts they will experience from the Avenues implementation. The Stakeholder Management Plan outlines how the project will develop support among the key stakeholders by involving them in project activities. The Communication Plan describes the communication approach, structure, and methods that will be used on the project. The Plan includes such information as: Communication Goals and Objectives Stakeholders Communication methods Anticipated messages and timeline Feedback mechanisms Suggested communication process, tools and templates; including process for quarterly updates
Analyze
Communication Plan
Version 5.0
Page 110
Ref. No.
13
Phase
Analyze
Deliverable Name
Enterprise Readiness Plan
Description
The Enterprise Readiness Plan details the approach for preparing the State for implementation and the associated changes. The Plan will include such information as: Enterprise readiness goals, objectives, and overall approach Initial impacts, initiatives to address, and timeline Change Agent Network description and associated roles and responsibilities Approach for assessing readiness
NA
Build
Change Discussion Guides that describe the process changes that affect job functions and roles. They also include key decisions the local offices need to make in order to prepare for implementation of the new processes.
Version 5.0
Page 111
15.0
Training Services
The Training team will be responsible for End User Training for the SRS users identified in Appendix 8 of the K-MED RFP. This includes analyzing the training needs, confirming the training curriculum, designing and building the training materials, coordinating the training environment with the technical team, testing training materials, conducting train-the-trainer, and supporting training administration. SRS may identify additional staff (approximately 500 to 600) to be trained during the course of the Avenues project. SRS will lead the effort, with assistance from Accenture, and in conjuction with K-MED training delivery, to make sure the appropriate staff receive the necessary training within the constraints of the Accenture staff. The training services for Avenues discussed in this Statement of Work is an increment of work added to the K-MED training. The Training team will be comprised of representatives from the State SRS project team and the Contractor. The Statement of Work reflects that Accenture will coordinate closely with SRS on the training program. Five SRS personnel and a State Training Lead from SRS will serve on the Training Team and will be involved in day-to-day training analysis, design, development, and testing activities. Accenture will be responsible for Train-the-Trainer, and Training Delivery, while SRS will provide the staff to assist in Training Delivery. ITS Training will be accomplished through side-by-side knowledge transfer and other knowledge transfer methods as outlined in the Knowledge Transfer section of the SOW.
15.1
15.1.1 15.1.1.1
Within the Analyze phase, the Training team confirms training needs for each audience affected by the new business processes. When conducting a needs analysis, the team identifies roles and their corresponding tasks/responsibilities, which then drive the required skills, training needs and training schedule for that role. At the end of the Analyze Phase, the Training team develops the Training Plan that describes the key elements of the training program, and includes course outlines for each Webbased Training (WBT) and Instructor-Led Training (ILT) course. The SRS Training Plan will be a separate deliverable from the K-MED Training Plan. Contractor Responsibilities: Review the Enterprise Readiness Assessment Report Define the skills required for new and revised roles. Contractor will leverage the impact analysis that has already been conducted on the project.
Version 5.0
Page 112
Create the Training Plan which will document the overall scope and strategy for the SRS training program Refine the preliminary curriculum using results from the audience analysis data State Responsibilities: Review the Enterprise Readiness Assessment Report Provide State context and content and assist in the preparation and development of the Training Plan Review, provide revisions and corrections, and approve the Training Plan Review, provide revisions and corrections, and give final approval for all course outlines
15.1.1.2
Training Curriculum
Using the results from the audience analysis, the Training team will refine the preliminary training curriculum for the End User Training Program. The preliminary training curriculum listed below includes courses already in scope for the K-MED project, as well as the courses that cover the additional functionality for Avenues.
Anticipated Course
Avenues and K-MED Phase 1 Customer Self Assessment Online Intake Application for Customers and Community Partners Online Intake Application for KMED/Avenues users System Navigation Presumptive Eligibility Avenues and SRS Phase 2 Eligibility Instructor-led Training 4 days for medical only; 5 days with additional program content integrated throughout course 4 hours 4 hours 4 hours 3 hours 3 hours 1 hour 2 hours 2.5 hours Baseline On line Demo On line Demo < 15 min < 15 min Baseline Baseline
Type
Length
Clerical Roles Hearings and Appeals Office Administration Security Rights Administration Cost Avoidance and Recovery Calendaring Administrative Tools Data Synchronization
Web-based Training Web-based Training Web-based Training Web-based Training Web-based Training Web-based Training Web-based Training Web-based Training
Version 5.0
Page 113
Anticipated Course
Workload Reassignment Quality Assurance Avenues-Only Employment Services Child Care Resource Databank Overpayments Issuances Collections Additional Training Imaging/Content Management (development of course plus training for ITS Staff and Trainthe-Trainer) LIEAP Training Material and Delivery: Accenture will extending training materials (previously developed) to cover the additional LIEAP scope. Accenture will also provide joint responsibility to roll the delivery LIEAP of the Training Materials to the appropriate LIEAP staff. Virtual Contact Center (Development of course detailed design plus mentoring of Staff to complete the course)
Type
Web-based Training Web-based Training Web-based Training Web-based Training Web-based Training Web-based Training Small Group Walkthrough Small Group Walkthrough Instructor-Led Training 1.5 hours 4 hours 6 hours 6 hours 4 hours 3 hours 1 day 1 day
Length
1 day
Baseline
Instructor-Led Training
1 day
New
Instructor-Led Training
1 day
New
*Note: Baseline courses reflect existing APSP system functionality and will be modified by the Training team to reflect Kansas-specific changes. New courses will be designed and developed from scratch as no baseline course materials exist. Small group walkthroughs are expert-led sessions with a flexible format. When appropriate, walkthroughs occur using the sandbox or a test version of the software, instead of the more structured training database, to provide the participants more flexibility to practice scenarios. For Issuances and Collections, the smaller training audience supports using this approach. Walkthroughs would be conducted in a central location such as the Central Training Lab. Additional information about small group walkthroughs and knowledge transfer activities for ITS and project roles (network administrator, business rules personnel, developer, business analyst, etc.) can be found in the Knowledge Transfer section of the Scope of Work.
Version 5.0
Page 114
Contractor Responsibilities: Confirm the training curriculum, which lists the training courses, anticipated delivery method, and length for each course Produce a high-level outline for each course for each SRS-specific course State Responsibilities: Assist the Contractor in defining the curriculum, which includes providing State context and content, providing input regarding methods, and assisting in the development of the course outlines Review and approve all inputs, standards, and templates used by the Contractor
15.1.2
Design Phase
Using the Training Plan and course outlines as input, the Training team creates detailed specifications for the end user training courses and support tools that will be developed during the Build phase. The team builds on the outlines for each course identified in the Training Plan, identifying specific exercises that illuminate and reinforce the course objectives.
15.1.2.1
The Accenture Training team members will conduct informal knowledge transfer for the State Training team members on the tools and methodology that will be used to design and build the end user training.. Web-based Training will be developed in Adobe Captivate; Online Help will be developed in Adobe RoboHelp. Contractor Responsibilities: Teach the State training team members the use of the tools and methods used for designing and building the end user training State Responsibilities: Ensure State training team members attend and participate in the informal meetings
15.1.2.2
Training Design
Training designs will contain information regarding learning objectives, suggested content, and estimated duration, and validate the suggested deployment method. Training designs consider the to-be business processes, as well as SRS-specific configurations and customizations to the system. During Design, the team will also identify changes required to the inventory of standard, delivered online help procedures that support Avenues functionality. The Avenues Scope of Work includes the effort to evaluate online help for Avenues functionality. Version 5.0 Page 115
Contractor Responsibilities: Produce design documents for each instructor-led course, web-based course or online demonstration Produce an inventory of online help procedures Provide methods, tools, and guidance in the training design process State Responsibilities: Produce training and online help design documentation, using the same inputs, standards and templates as the Accenture team members Provide the necessary State content and context to the training materials Review and approve all inputs, standards, and templates used by the Contractor Review and provide confirmation of each training design to minimize rework during the Build phase Confirm the inventory of online help procedures Evaluate the look and feel of the baseline instructor-led products and implement design changes Identify additional classroom and online help custom job aids Provide revisions, corrections, and give final approval for all training materials
15.1.3 15.1.3.1
The Build Phase includes developing training material. During this phase, the Training team develops SRS-specific training materials, online help procedures, WBTs, and training exercises based on the approved designs. They coordinate with the project technical staff to create a training environment and a training sandbox. The team will use baseline materials plus project deliverables (standards, templates, etc.) as a starting point for SRS training materials and online procedures. Once developed, SMEs review the materials and provide feedback. Once the feedback has been addressed, the materials are tested and revised prior to Training Deployment. Contractor Responsibilities: Work with the K-MED/Avenues training development team to develop a combined Eligibility course that reflects both K-MED and Avenues functionality. The K-MED scope of work includes developing the equivalent of 4 days of training. The SRS scope of work includes developing the equivalent of 1 day of additional training content. This content will be integrated into the full course so that SRS users see relevant scenarios and data throughout. Version 5.0 Page 116
Work with SRS to create the paper-based and online components of the Eligibility course. Paper materials consist of a slim user guide that contains course objectives, background information, information on how to utilize user support tools after training and after implementation (online help, help desk, etc.), guidelines and suggestions for using the sandbox to reinforce their skills after training, and a place for taking notes. Develop written training materials in accordance with 508 compliance regulations. Build new web-based training courses. WBT courses consist of text pages, simulated system pages with user interactivity, and skills assessments. The WBTs will be JAWS compliant. Modify existing baseline courses to reflect SRS-specific system configurations and customizations, as well as agency-specific items such as logo, terminology, etc. Identify scenarios and training data needed to support the instructor-led course objectives Establish the training database environment and set up training data. Training for K-MED and Avenues will use the same training environment, with data specific to each. Establish the training sandbox environment and define processes and procedures for the sandbox environment. K-MED and Avenues will use the same sandbox environment. Develop course evaluations Modify existing online help content and job aids to reflect SRS-specific configurations and customizations, as well as create new procedures where necessary Contractor shall designate functional SMEs to review the training materials for system accuracy Address the SME-reviewer feedback and update the training materials accordingly State Responsibilities: Develop training materials using the same tools and templates as the Accenture team Provide input to the training materials and support tools. The input will include State content and context to the materials Review and approve all tools and templates used by Accenture Assist in defining exercise scenarios and data used in the training database Designate SMEs to review the training materials for State context, content and process accuracy Address the SME-reviewer feedback and update the training materials accordingly Create any SRS-specific training content required to supplement the training program Version 5.0 Page 117
Provide revisions, corrections, and give final approval for all training materials as well as support tools
15.1.3.2
Test
The Test Phase includes testing training materials prior to deployment. During this phase, the Training team tests SRS-specific training materials, online help procedures, WBTs, and training exercises. Contractor Responsibilities: Test instructor-led training exercises Test new and modified web-based training courses Work with the technical team to confirm sandbox readiness for deployment Test online help State Responsibilities: Conduct testing on training exercises, web-based training, and online help using the same tools and methods as the Accenture team Designate SMEs to review the training materials for State context, content and process accuracy Provide revisions, corrections, and give final approval for all training materials as well as support tools
15.1.4
Deploy Phase
During the Deploy Phase, the Training team conducts a training pilot, delivers Train-the-Trainer, and deploys web-based training and online help. Accenture will be responsible for Train-the-Trainer and Training Delivery, while SRS will provide the staff to assist in Training Delivery.
15.1.4.1
Pilot Training
The Training team conducts a mock delivery of each training course, to confirm the course duration and to validate that the objectives of the course are met as designed. Each pilot (a.k.a mock training delivery) will include the respective training developer conducting one practice session of each course to the trainers who are being prepared for training delivery and/or to other selected participants such as State subject matter experts. Observers from the Training team will validate course duration and identify any issues. Comments and observations will be captured throughout the delivery. Results will be summarized, analyzed, and prioritized. Recommended changes will then be made to correct issues where training did not perform as designed or where content was incorrect. Other changes mutually agreed upon by the State and the Contractor will be made prior to the training deployment to end users.
Version 5.0
Page 118
Contractor Responsibilities: Create the pilot schedule Prepare the Central Training Lab for pilot courses Conduct pilot courses Review the pilot training results and prioritize changes Apply approved changes
State Responsibilities: Provide input to the development of the Pilot Training Plan and schedule Review and approve the Pilot Training Plan as well as all training courses associated with it Identify pilot training participants Participate in the review of the pilot training results and work together with Contractor to prioritize changes Review, provide revisions and corrections, and give final approval for the post-pilot version of the training materials
15.1.4.2
Train-the-Trainer
The Train-the-Trainer program will prepare the SRS trainers for training delivery to the end users. The Accenture team will conduct the train-the-trainer program which includes four sessions a project overview, a mock session of the trainers assigned course, at least one training practice run, and a supported session where the trainer conducts a session or portion of an actual training session with support from a project team member. Trainers who complete train-the-trainer receive certification to deliver training. These trainers will conduct any additional train-the-trainer sessions needed to train other personnel with training responsibilities. Accenture will conduct 8 Train-the-Trainer sessions. This represents two full conducts of the Train-theTrainer program. Contractor Responsibilities: Develop and conduct the train-the-trainer program, which shall be used to prepare the States trainers Prepare constructive feedback for each trainer in the train-the-trainer program and provide that information to the State Version 5.0 Page 119
State Responsibilities: Recruit the State trainers who will conduct the end user training Assist the Contractor in the development and delivery of the train-the-trainer program, which includes providing State content and context input to the materials Review, provide revisions and corrections, and give final approval for the train-the-trainer material and courses Ensure availability and attendance of the State trainers
15.1.4.3
Training Facilities
Training facilities consist of one Central Training Lab, located at the main project site, and temporary training facilities. Eligibility training will take place in the Central Lab and regional facilities identified, secured and managed by the State. Contractor Responsibilities: Configure and test Central Training Lab per required specifications Provide guidance to the state on the requirements for regional training facilities to aid in identifying and establishing the sites Work with the State to confirm site readiness State Responsibilities: Provide final approval of Accentures plans for the Central Training Lab Identify and coordinate setup of regional training facilities considering requirements guidance provided by Accenture Test training sites to confirm preparedness for training delivery
15.1.4.4
Training Delivery
Training delivery includes conducting instructor-led courses and deploying web-based training courses and online help for the State end users identified in Appendix 8 of the RFP. The Accenture team will deploy WBT and online help, as well as compile results from training evaluations. Accenture will lead Instructor-Led Training, while the State will provide the staff to support the delivery of instructor-led training. This includes the following: 1. The SRS-specific content for the integrated Eligibility course. Because the SRS-specific information is integrated throughout the Eligibility course, training delivery will be accomplished Version 5.0 Page 120
by team teaching the Eligibility course with a K-MED/Avenues instructor. This helps confirm users gain an integrated view of the system, provides support from both agencies when users have questions, and also provides extra help in the classroom for assisting users as they complete their online exercises. 2. Imaging/Content Management training 3. Virtual Contact Center training Contractor Responsibilities: Deploy web-based training courses and online help Compile and report on training evaluation results weekly Provide Lead Instructor during teaching of Eligibility course State Responsibilities: Ensure user availability to attend the required training
Provide support Instructor for instructor-led training courses Administer evaluations in the classroom
15.1.4.5
Training Administration
Training administration will involve the activities associated with managing and administering the end user training program. It includes for example, training registration, reproduction of materials, collecting training evaluation results, scheduling courses and scheduling trainers. It also includes administering, collecting, analyzing and reporting the training evaluations. The Project Training Lead would manage the coordination of training facilities, as well as training administration tasks including training scheduling and rescheduling, course completion/attendance tracking, and administering course evaluations. SRS will help confirm successful delivery of training by assisting with administration and analyzing training evaluation results. In addition, Accenture will execute a one-time data extract from Moodle to Pathlore. Contractor Responsibilities: Run training reports Assist in the analysis of the training evaluation results and recommendations for remediation Schedule training facilities Perform scheduling and rescheduling of training participants
Version 5.0
Page 121
Track course/completing and attendance Administer course evaluations Coordinate the scheduling of instructors Complete a one-time data extract from Moodle to Pathlore.
State Responsibilities: Assist in scheduling training facilities Assist in performing scheduling and rescheduling of training participants Assist in tracking course/completing and attendance Assist in administering course evaluations Assist in coordinating the scheduling of instructors Ensure appropriate and timely completion of training registration for their users (local offices) Review training evaluations and work with Accenture to make adjustments to training presentations and/or materials for future instructor-led training sessions; provide final approval on all changes and adjustments
15.1.4.6
Training Transition
Accenture would develop and implement the Training Delivery Transition Plan that would address the approach and implementation for transitioning training roles, training responsibilities, and training materials to SRS Training staff. Contractor Responsibilities: Work with the State Training Lead to perform knowledge transfer activities Provide electronic versions and any appropriate paper-based training materials to SRS Hold work session with SRS trainers and training developers to answer questions that they may have about the training materials and/or their development process
Version 5.0
Page 122
15.2
Responsibility Matrix
Accenture
Assist Lead Assist Assist Assist Lead Lead
State
15.3
None
Other Requirements
15.4
Deliverables
The table below summarizes the training deliverables to be created during each phase:
Ref. No.
17
Phase
Analyze
Description
The Training Plan describes the end user training approach and high-level curriculum. The training plan will provide training course recommendations, estimated duration, training methods and tools, and the training development and delivery approach and schedule. Training Designs contain information regarding learning objectives, suggested content, and estimated duration, and validate the suggested deployment method. The Training Materials consist of the instructor-led and web based content developer for end user training, as well as online help procedures and job aids as defined by the Training Designs. Describes the approach for transitioning training roles, training responsibilities, and training materials to SRS Training staff.
NA
Design
19
Build
NA
Deploy
Version 5.0
Page 123
16.0
16.1
Project Management Leadership is ultimately responsible for confirming effective knowledge transfer takes place on the project. Other responsibilities will be divided as follows: Enterprise Readiness Team (also referred to as the Change Management Team): The Enterprise Readiness team will be responsible for facilitating the activities that occur between the Accenture team and SRS personnel that prepare SRS to support the system long term. The ER team will create the templates used for knowledge transfer activities, track overall knowledge transfer progress and report to the State. Individual Team Leads: The individual Accenture team leads are responsible for documenting and monitoring knowledge transfer activities on their teams to confirm that it is taking place to the expected level and within the expected timeframes. Teams use Personal Learning Plans to document and track knowledge transfer for each SRS individual who needs to maintain and operate the system after implementation. The Knowledge Transfer services activities described in this section will be completed in the described phases, with a target completion of post-implementation of Phase 4. Activities will begin per the project plan
16.2
16.2.1
Analyze Phase
During the Analyze Phase, the Accenture team works with the SRS to confirm the list of roles targeted for knowledge transfer and the knowledge transfer tools and templates to be used for the project .
16.2.1.1
Identify Roles
The final list of roles will be confirmed by the SRS Project Manager. Examples of specialized roles that will participate in knowledge transfer include the following: Configuration Team Member Configuration Manager Security Analyst Infrastructure Lead
Version 5.0
Page 124
Network Administrator System Administrator Developer Business Analyst Tester Policy Analyst Help Desk/support personnel The Enterprise Readiness team works with the specific team leads and the State to determine the right mix of formal training, small group walkthroughs, and informal knowledge transfer for each role. In some cases, side-by-side informal knowledge transfer alone is appropriate for the role. In others, the team leads will need to conduct small group walkthrough sessions. The approach will depend on the complexity of the material and on the number of people who need to receive knowledge transfer for the particular topic. The ER team will seek input and review from ITS when completing the analysis. Contractor Responsibilities: Work with the State to document final list of roles Determine the appropriate knowledge transfer techniques for the roles Coordinate input with ITS State Responsibilities: Provide input into the roles analysis Review and approve the Knowledge Transfer Plan
16.2.1.2
The Enterprise Readiness team develops the Knowledge Transfer Plan. The Knowledge Transfer Plan includes information regarding the ongoing support organization, roles, and skills and capabilities needed by each role. The Plan will also include knowledge transfer methods, key milestones, the preliminary Personal Learning Plan template, and the preliminary knowledge transfer scorecard template. The Plan will also include the processes and tools used to conduct and assess the knowledge transfer activities.
Version 5.0
Page 125
Contractor Responsibilities: Document the Knowledge Transfer Plan, including the methods to be used for knowledge transfer, such as peer programming, shadowing, role sharing, and small group walkthrough training. Include preliminary knowledge transfer templates. Assist in defining the post-go live organization structure State Responsibilities: Define the Post Go-Live organizational structure (technical and functional) Identify the State resources targeted to fill roles in the Post Go-Live organization Address all personnel-related communications and interactions with candidates and their transition to the Post Go-Live organization Review and approve the Knowledge Transfer Plan
16.2.2
Design Phase
During the Design Phase, the Enterprise Readiness team refines the templates and confirms their final format with SRS stakeholders. They also orient the Project Team to the Knowledge Transfer and PLP processes. If the functional and technical leads require support in creating outlines or planning for their small group walkthroughs, the ER Team will coordinate with the Training team or other resources.
16.2.2.1
Each individual working on the Avenues project creates a Personal Learning Plan (PLP). A Personal Learning Plan is a document that lists the activities, skills, or knowledge that a person needs in order to complete their post-implementation job tasks. These plans document the individuals current skill level for a certain topic, the desired skill level, the Accenture mentor assigned to the PLP, the reference materials, the time frame, the percentage completion, the signoff, and any next steps for the transferor/mentor or transferee. During the Design Phase, the Enterprise Readiness team will confirm the PLP template with the State and orient the project team on how to use the PLPs. Contractor Responsibilities: Identify mentors for each of the personnel targeted for knowledge transfer Develop the templates and processes to support the knowledge transfer program and confirm with the State. This consists of the Personal Learning Plan template, the Knowledge Transfer scorecard and the small group training walkthrough template Orient the team on how to use the template to create PLPs for their team members Version 5.0 Page 126
16.2.2.2
The Enterprise Readiness team will initiate and facilitate assessment of the knowledge transfer progress, as outlined in the Knowledge Transfer Plan. The team will compile the results and summarize the information in the Knowledge Transfer Scorecard. Contractor Responsibilities: Support the State in its assessment of knowledge transfer progress Compile the results and prepare the Knowledge Transfer Scorecard State Responsibilities: Assess the progress of the knowledge transfer activities and progress as defined in the Knowledge Transfer Plan Ensure State candidates participating in knowledge transfer are available, actively participate, and update their PLPs accurately and in a timely manner Provide input to creation of the Knowledge Transfer Scorecard
16.2.2.3
Using the small group walkthrough template as input, the Accenture team leads will work with the State to create the design documents for any small group walkthrough sessions needed for their areas. An example is a Rules Maintenance walkthrough. The template consists of a simple outline listing the learning objectives, topics to be covered, length, hands-on exercises, etc. Contractor Responsibilities: Develop design documents, including exercise scenarios, for small group walkthroughs State Responsibilities: Provide input into the walkthrough designs Review and approve the walkthrough designs Begin knowledge transfer/track on PLPs
Version 5.0
Page 127
16.2.3
Build Phase
During the Build Phase, the Enterprise Readiness team will continue to facilitate assessment of the knowledge transfer progress, as outlined in the Knowledge Transfer Plan. The team will compile the results and summarize the information in the Knowledge Transfer Scorecard. The functional and technical teams will prepare to deliver walkthrough sessions. Contractor Responsibilities: Support the State in its assessment of knowledge transfer progress Compile the results and prepare the Knowledge Transfer Scorecard Organize the necessary materials and data needed to facilitate the small group walkthrough sessions Continue knowledge transfer/track on PLPs State Responsibilities: Assess the progress of the knowledge transfer activities and progress as defined in the Knowledge Transfer Plan Ensure State candidates participating in knowledge transfer are available, actively participate, and update their Personal Learning Plans (PLPs) accurately and in a timely manner Provide input to creation of the Knowledge Transfer Scorecard
16.2.4
Test Phase
During the Test Phase, the Enterprise Readiness team will continue to facilitate assessment of the knowledge transfer progress, as outlined in the Knowledge Transfer Plan. The team will compile the results and summarize the information in the Knowledge Transfer Scorecard. Individual team leads will confirm the environments and data are in place to conduct their walkthroughs or other knowledge transfer sessions. Contractor Responsibilities: Support the State in its assessment of knowledge transfer progress Compile the results and prepare the Knowledge Transfer Scorecard Confirm the technical environments and data needed to facilitate the small group walkthrough sessions Continue knowledge transfer/track on PLPs
Version 5.0
Page 128
Lead the knowledge transfer of testing tools (e.g. logging a defect) and procedures (e.g. steps to take to resolve a defect) through mentoring and shadowing activities with State staff State Responsibilities: Assess the progress of the knowledge transfer activities and progress as defined in the Knowledge Transfer Plan Ensure State candidates participating in knowledge transfer are available, actively participate, and update their Personal Learning Plans (PLPs) accurately and in a timely manner Provide input to creation of the Knowledge Transfer Scorecard Participate in mentoring and shadowing activities with Accenture staff
16.2.5
Deploy Phase
The Enterprise Readiness team will initiate and facilitate assessment of the knowledge transfer progress, as outlined in the Knowledge Transfer Plan. The team will compile the results and summarize the information in the Knowledge Transfer Scorecard. Individual team leads will conduct small group walkthroughs or other knowledge transfer sessions. Contractor Responsibilities: Monitor knowledge transfer progress Compile the results and prepare the Knowledge Transfer Scorecard Continue knowledge transfer/track on PLPs State Responsibilities: Assess the progress of the knowledge transfer activities and progress as defined in the Knowledge Transfer Plan Monitor and maintain knowledge transfer tools such as blogs and chat rooms Ensure State candidates participating in knowledge transfer are available, actively participate, and update their PLPs accurately and in a timely manner Review the knowledge transfer scorecard
Version 5.0
Page 129
16.2.6 16.2.6.1
Post Systems Support Phase Assess Knowledge Transfer Progress Post Systems Support
The team will facilitate assessment of the knowledge transfer progress, as outlined in the Knowledge Transfer Plan. The team will compile the results and summarize the information in the Knowledge Transfer Scorecard. Contractor Responsibilities: Support the State in its assessment of knowledge transfer progress Compile the results and prepare the Knowledge Transfer Scorecard Continue knowledge transfer/track on PLPs State Responsibilities: Assess the progress of the knowledge transfer activities and progress as defined in the Knowledge Transfer Plan Monitor and maintain knowledge transfer tools such as blogs and chat rooms Ensure State candidates participating in knowledge transfer are available, actively participate, and update their PLPs accurately and in a timely manner Provide input to creation of the Knowledge Transfer Scorecard
16.3
Responsibility Matrix
The table below summarizes the responsibilities associated with Knowledge Transfer services:
Scope Element
Define Post Go-Live organizational structure (functional & technical) Develop Knowledge Transfer Plan Develop Personal Learning Plans for Post Go-Live Team Member (quarterly then monthly) Develop Knowledge Transfer scorecards Assess Personal Learning Plans Assist Lead Lead Lead Assist
Contractor
Lead Assist Assist Assist Lead
16.4
Other Requirements
None identified.
Version 5.0
Page 130
16.5
Deliverables
The table below summarizes the Knowledge Transfer deliverables to be created during each phase:
Ref. No.
8
Phase
Analyze
Deliverable Name
Knowledge Transfer Plan
Description
The Knowledge Transfer Plan deliverable will define the approach used to prepare the designated Project Team resources for roles in the Post Go-Live Organization. The Plan will include: Overall project approach to knowledge transfer and milestones etc Methods, tools, and processes used to facilitate knowledge transfer Description of the Post Go-Live Support Organization structure, roles and capabilities needed Personal Learning Plan template Knowledge transfer scorecard template and processes used to conduct and assess the knowledge transfer activities
26
Phase 2 Eligibility LIEAP Knowledge Transfer Scorecard VCC Knowledge Transfer Scorecard
This deliverable summarizes the results of the knowledge transfer progress to date, against the plan. Results are summarized in a scorecard format as defined in the Knowledge Transfer Plan. This deliverable summarizes the results of the knowledge transfer progress to date, against the plan. Results are summarized in a scorecard format as defined in the Knowledge Transfer Plan. This deliverable summarizes the results of the knowledge transfer progress to date, against the plan. Results are summarized in a scorecard format as defined in the Knowledge Transfer Plan.
26
26
Version 5.0
Page 131
17.0
The SRS Technical Infrastructure Statement of Work (SOW) will reference the K-MED Technical Infrastructure Build and Operations SOW as the SRS solution will be managed and executed to leverage the same technologies, methodologies, and activities that are defined in the K-MED Technical Infrastructure Build and Operations SOW.
17.1
Major Activities
The Contractor shall provide technical leadership and mentoring in planning, designing and building the technical infrastructure for the project. The Contractor will work with State personnel and synthesize the information to estimate the hardware required to support the required number of environments used during implementation. During implementation, the Development Environment will be built and maintained by the Contractor. The other 8 environments will be built and maintained by the Contractor with technical input from the State. In addition, the Contractor, with input from State personnel, shall be responsible for estimating the hardware requirements for the production system. It is envisioned that the equipment originally used for the User Acceptance Test (UAT) Environment will be used for the Disaster Recovery (DR) system. The Contractor shall assist the State in the planning and building of the off-site DR infrastructure. The Contractor shall lead the effort in developing a Disaster Recovery Plan. The Contractor will assist the Hosting Provider who will be responsible for overseeing a DR exercise 1-2 months prior to go-live. The Contractor shall provide maintenance and operational support of the Projects K-MED/Avenues technical infrastructure. This will include, but will not be limited to: keeping the operating system current, performing periodic backups and restores, creating and maintaining new instances of KMED/Avenues, as required, and applying patches and fixes to all instances of K-MED/Avenues. To expedite the Conference Room Pilots and Fit/Gap sessions, the Contractor shall furnish a Reference Environment. The Reference Environment is an off-site, hosted instance of the Worker Portal and the Self-Service Portal, with all commercial products from Oracle installed and configured. The State must provide the commercial product license keys prior to the installation of these products on the Contractors hosted servers. This instance shall be available 24/7 except for routine environment maintenance activities. The Contractor will communicate the planned down-time schedule to the State in advance. Prior to production cutover, the Contractor shall apply all available service packs and updates such that the Worker Portal, the Self-Service Portal, commercial products, applications, databases, OS, and virtualization technologies shall be in their most current status unless both parties mutually agree that the risk and potential impact to go-live activities is greater than the impact of refraining from applying the latest service pack updates.
Version 5.0
Page 132
17.2
Responsibility Matrix
Roles and responsibilities for managing the technical infrastructure and related activities are delineated in the table below. It is assumed that all applicable scope elements listed below apply to all instances of the hardware, databases and applications without specifying each.
Scope Element
Build & Design Install Oracle Database Setup Oracle Database Implement Load Balancer Establish firewalls Apply fixes, patches and bundles as needed (when provided & available from APSP, Oracle, etc. and in consultation w/ team) Install commercial middleware software Configure commercial middleware software Install Master Data Management software Configure Master Data Management software Install APSP architecture and portal software Install Business Intelligence Services/BI software Setup Business Intelligence Services/BI software Install Conversion software Setup Conversion software Install Batch scheduler software Setup Batch scheduler software Apply security to the DB level Document strategy for building and maintaining environments Create production system database administration procedures Create technical readiness document Evaluate WAN capacity as it relates to the K-MED implementation Create the standard technical infrastructure configuration Create database instances: Production Reference Integration Development Interface Testing Conversion Testing UAT System Testing Training
Contractor
Hosting Provider
Lead Lead Assist Assist Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead
Lead Lead
Assist Assist Assist Assist Assist Assist Assist Assist Assist Assist Assist Assist Assist
Version 5.0
Page 133
Scope Element
Emergency Fix Performance tuning: Databases Application servers Web servers Batch processes Online processes Develop software patches and fixes methodology Create backup and recovery plan Test and validate backup and recovery procedures in all environments (instances) Develop Database change policies Harden the web infrastructure components; install security patches, turn off unused services, etc Establish remote access to Kansas development environment in accordance to DISC policies Develop hardware installation strategy & plan Install & configure hardware (Development) Install & configure operating system software (Development) Install & configure hardware (Non-Development) Install & configure operating system software (Non-Development) Setup SAN drives Install SAN drivers Install backup system Develop configuration migration procedures Develop Standard technical infrastructure configuration and change management methodologies Document technical architecture Document infrastructure design Develop and document standard technical infrastructure configuration Create the business continuity plan (Disaster Recovery) Develop DR procedures, providing detail steps necessary to bring DR site to Production Status Conduct DR development meetings Create DR Execution Plan for the DR test exercise Architect, implement and test a disaster recovery process Identify technical requirements Define application architecture Define technical architecture Assess technical architecture gaps Confirm technical architecture analysis and deliverables
Contractor
Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Assist Assist Lead Lead Lead Assist Assist Lead Lead Lead Lead Lead Lead Lead Lead Lead Assist Assist Assist Assist Lead Lead Lead Lead Lead
Hosting Provider
Assist Assist Assist Assist Assist Assist
Assist
Lead Lead
Version 5.0
Page 134
Scope Element
Transition technical architecture analysis deliverables Design batch processing Plan & conduct component test Build and test application components Size hardware for implementation Size hardware for production Operations Define long term production support strategy Create a production system operational model Create production System Administration procedures Create production system operation procedures Establish criteria and plan for applying software upgrades from APSP, Oracle and other commercial vendors. Service Packs Application Bundles Patches & Fixes Apply software upgrades Updates & Fixes Establish plan for applying database upgrades from Oracle Perform Nightly Operations Operating System backups Database backups Web backups Other server backups Performance tuning (continuously): Databases Application servers Web servers Batch processes Online processes Cutover Create production cutover plan Create detailed task lists and work plans for Cutover Create production cutover staffing schedule Create production cutover roles and responsibilities
Contractor
Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead Assist Assist Assist Assist Assist Lead Lead Lead Lead Lead Lead Lead Lead Lead Lead
Hosting Provider
Assist Assist Assist Assist Assist Assist Lead Lead Lead Lead Lead Assist Assist Assist Assist Assist Assist Assist Assist Assist Assist
17.3
Ref. No.
NA
Deliverables
Phase Work Products
Technical Architecture Plan
Description
Analyze
Version 5.0
Page 135
Ref. No.
NA NA
Phase
Build Deploy
Work Products
Web Portal Functional and Technical Designs Technical Architecture Installation and Knowledge Transfer
Description
Version 5.0
Page 136
18.0
The Contractors Quality Assurance (QA) approach shall include the following: 1. Contractor QA representatives will meet periodically with K-MED/AVENUES Project Leadership to assess and review progress, recommend courses of action and help verify that quality is a focus for the outcome of the Project. The QA Review provides objectivity, independence, broad subject matter experience and a careful assessment of all viewpoints. The external QA Review also includes inspection of deliverables to assess technical quality, an evaluation of QA program metrics and interviews with managers from the K-MED/AVENUES Project. 2. Contractor will prepare a work product (Client Satisfaction Survey), the summary of which when completed, will be included in the QA Review. The findings of the QA Review will be documented. 3. Use of standard quality methodologies and performance metrics, e.g. rates of defect identification and fixes. 4. Layers of quality review. 5. Compliance with CMMI Maturity Level 4. 6. Adherence to quality guidelines and standards. 7. Work with an IV&V contractor that will be on-site to provide an independent assessment of project health. The Contractor shall provide the selected IV&V contractor all Project information they request and access to Project personnel for interviews.
18.1
Major Activities
The Quality Assurance approach includes the following major activities: 1. Develop quality guidelines for development and testing. 2. Conduct quarterly Quality Assurance (QA) Reviews that include the establishment and evaluation of stakeholder expectations. 3. Conduct annual Client Satisfaction Surveys. 4. Work with involved agencies and business partners to ensure adoption of and adherence to Project QA standards. 5. Review and adopt recommendations of an IV&V Contractor.
Version 5.0
Page 137
Contractor Responsibilities: 1. Development of a Quality Assurance Plan. 2. Provide QA awareness and training to the Project Team. 3. Conduct Quality Assurance Reviews per the Project Plan. State Responsibilities: 1. Ensure Project activities are executed in adherence to quality standards. 2. Make the appropriate client stakeholders available for periodic meetings. 3. Respond to the annual Client Satisfaction Survey. 4. Assist involved agencies and business partners in meeting Project QA standards.
18.2
Responsibility Matrix
Contractor
Lead Lead Lead Lead Lead Assist Assist
KDHE-HCF-SRS Team
Assist Assist Assist Assist Assist Lead Lead Assist Assist Assist Assist Assist
IV&V
Attend n/a
18.3
Phase
All
Deliverable Name
Quality Assurance Plan (work product not a paid deliverable)
Description
The Quality Assurance Plan will outline processes, activities, roles, and monitoring practices fundamental for the implementation of a sound and robust Quality Assurance approach. Two 2-hour training classes for the Project Team on quality control guidelines and processes.
NA
All
Version 5.0
Page 138
Ref. No.
NA
Phase
All
Deliverable Name
a paid deliverable) Quarterly Quality Assurance Review Findings (work product not a paid deliverable)
Description
Accenture requires that every project conduct formal, quarterly reviews, known as Quality Assurance Reviews. An Accenture Senior Executive, external to the KMED/AVENUES engagement, conducts the review. The programs foundation and success begins with an objective, quality Executive Sponsor for the State of Kansas. This executive meets quarterly with K-MED/AVENUES Project Leadership to assess and review progress, recommend courses of action, and help verify that quality is a focus for the outcome of the project. The QA review provides objectivity, independence, broad subject matter experience and a careful assessment of all viewpoints. The external QA review would also include inspections of deliverables to assess technical quality, an evaluation of QA program metrics, and interviews with managers from the K-MED/AVENUES project. The findings and recommendations are documented. Annual Client Satisfaction Survey provided to key Project Management and stakeholders.
NA
All
Version 5.0
Page 139
19.0
508 Compliance
The system delivered by the Contractor shall comply with State of Kansas Accessibility requirements. For additional details regarding the scope of work for 508 Compliance, please see Section 24 - Web Accessibility Compliance of the K-MED SOW.
Version 5.0
Page 140
20.0
Help Desk
The Avenues Help Desk is the single point of contact for support and online services to manage and resolve incidents and problems. For the purposes of this section, any reference to Help Desk refers to the Business Help Desk unless stated otherwise.
Scope Definition
The SRS Avenues Help Desk will be an increment to the K-MED Help Desk. As per the SRS Ongoing Operations contract with the Contractor, the Contractor will provide the Help Desk support for the SRS increment along with the K-MED portion. The K-MED SOW will be the basis for the SRS increment. At the conclusion of the Ongoing Operations contract and as part of the implementation of the Virtual Contact Center, it is expected that the Contractor will assist the State in transitioning this functionality into the Virtual Contact Center solution. Contractor Responsibilities: 1. Assist in the transition of the Help Desk functionality into the Virtual Contact Center solution. State Responsibilities: 1. Lead the transition of the Help Desk functionality into the Virtual Contact Center solution.
Responsibility Matrix
The table below summarizes the responsibilities.
Help Desk Develop the Help Desk Transition Plan Contractor Assist SRS Lead
Version 5.0
Page 141
21.0
21.1
The Contractor shall develop and test Business Continuity of Operations and Disaster Recovery (DR) Plans as defined in RFP Sections A6.3.2.2.6.1 and A6.3.2.2.6.2, the RRO request, and in the Contractors proposal. The Contractor will coordinate plan development with the State (KDHE and SRS) and the hosting vendor. Each plan will be developed and tested prior to Phase 1, Phase 2, Phase 3, and Phase 4 releases. For each subsequent release, the plans and the tests will be built on earlier versions. The Disaster Recovery Plan and periodic DR simulations must be executed to the satisfaction of the State to constitute acceptance. Test results must be available for review by State or Federal officials upon request. After a release to production, the Disaster Recovery Plan must be tested every 12 months, and a written report of the outcome, corrective action plan, and revisions, if any, must be available within 90 calendar days of the completion of the test. This report, including test results, must be filed with the State Project Directors and any other agency authorized by the State or the Federal government.
Contractor Responsibilities: 1. Review applicable State requirements for Business Continuity, i.e. ITEC Policy 5300R1 Business Contingency Planning and ITEC Policy 5310R1 - Business Contingency Planning Implementation. http://www.da.ks.gov/kito/itec/Policies/ITECITPolicy7310.htm 2. Develop Business Continuity of Operations and Disaster Recovery Plans for the scope of the technical architecture and Contractor operations of the Avenues System. 3. Conduct Disaster Recovery simulation exercises in cooperation with the State, the hosting vendor (if different), and State business partners as applicable. Draft corrective actions and provide debrief to the State and applicable business partners. State Responsibilities: 1. Review draft and final Plans. 2. Assist with Disaster Recovery simulation exercises. 3. Coordinate activities involving State agencies and State business partners. 4. Review results of simulation and participate in debrief.
Version 5.0
Page 142
21.2
Responsibility Matrix
Contractor
Lead Lead Lead Lead
Hosting Vendor
Assist Assist Assist Assist
KDHE-HCF/SRS
Assist Assist Assist Assist
Agency/Business Partner
Assist Assist Assist Assist
Lead Lead
Assist Assist
Assist Assist
Assist Assist
Lead Lead
Assist Assist
Assist Assist
Assist Assist
Lead Lead
Assist Assist
Assist Assist
Assist Assist
21.3
Version 5.0
Page 143
Ref No #
16
Phase
Design
Deliverable Name
Continuity of Operations Plan
Description
The Business Continuity of Operations Plan details the Contractor core business processes and contingency plan in case of an emergency. The plan will identify triggers for activating plans and an establishment of a Business Resumption Team. Additionally the Disaster Recovery section details the retention and storage of back-up files, hardware and networks. It also includes a staff chart and back-up procedures and support to accommodate the loss of online communications.
33
Test
A simulated test of a disaster is completed with a switchover to the DR environment. The test is focused on procedures for the switchover, restart of the application, and verification of critical application functions.
Version 5.0
Page 144
22.0
Ongoing Operations
The Ongoing Operations statement of work includes the tasks associated with the design/build/test/release of enhancements for SRS. The state is responsible for managing the enhancement process, and Accenture will provide six resources to assist/support this process. The operations team will follow the Change and Release Management process as defined by the state. In addition, Accenture will continue to provide knowledge transfer to SRS staff throughout the duration of ongoing operations, and support Help Desk operations. The Ongoing Operations effort begins with the implementation/go-live of SRS and continues for 12 months. (NOTE: Production Support is handled through K-MED. This entails ongoing operation of a computer application allowing effective system maintenance. This includes monitoring performance and uptime, security issues, utilization of the system, transaction volumes, and related activities to monitor the production application.)
22.1
Major Activities
The Ongoing Operations effort is led by SRS and supported by six Accenture staff. During Ongoing Operations, Accenture is responsible for managing knowledge transfer activities, and supporting the enhancement process (as described below).
22.1.1
Knowledge Transfer
Knowledge Transfer is a two-way effort starting from project initiation through the duration of the contract. During Ongoing Operations our team will build on the knowledge transfer activities that have occurred throughout the project. These activities are made possible by creating a work environment where SRS and Accenture staff can work side-by-side to complete their tasks. By co-locating, and coordinating efforts, we create an environment where shadowing becomes inherent. This will remain true for the SRS Operations Team. During the course of the SRS project, the Enterprise Readiness (ER) team will be responsible for facilitating the activities that occur between the Accenture team and SRS personnel that prepare SRS to support the system long term. The ER team will create the templates used for knowledge transfer activities, track overall knowledge transfer progress and report to the State. We will continue to use these templates, processes and status reporting during the Ongoing Operations phase. Knowledge transfer activities will focus on the following areas: Documentation of enhancement designs Identifying system-wide impact assessments
Version 5.0
Page 145
Build activities Test activities Release Management General Configuration of APSP (See Section 16.0-Knowledge Transfer Services of this document for more information on Accentures approach to knowledge transfer.)
22.1.2
Enhancements
Enhancements entail modifying existing applications in response to new or changing business requirements. Enhancements will be submitted through the change management process and approved by SRS. Beginning with the implementation/go-live of SRS, the State managed operations team will perform enhancements. The capacity for Accenture resources is set at six resources for 12 months. The six Accenture roles will provide technical and functional support for the SRS enhancement effort, and will provide expertise across functional areas (such as forms/reports, online, rules, BPM, etc). SRS will be responsible for managing and executing the enhancements. It is suggested that the SRS team consist of at least the following thirteen resources:
Team
Proj Mgmt App Dev App Dev App Dev App Dev App Dev App Dev Functional Functional Functional Functional Functional Implementation
Role
Project Manager* App Dev Team* App Dev Team* App Dev Team* App Dev Team* App Dev Team* App Dev Team* SNAP/TANF BA* SNAP/TANF BA* Subject Matter Expert* Tester* Tester* Bus Intel Dev*
Resource Name
State Deputy Mgr 1 State Developer 1 State Developer 2 State Developer 3 State Developer 4 State Developer 5 State Developer 6 Business Analyst 4 Business Analyst 5 State SME 4 State Tester 2 State Tester 3 State Bus Intel Dev
Location
State State State State State State State State State State State State State
Roll On Month
M1 M2 M2 M6 M6 M6 M1 M1 M1 M1 M6 M6 M13
Total Months
39 38 38 34 34 34 39 39 39 39 13 34 9
Version 5.0
Page 146
The capacity for SRS resources can grow at the discretion of SRS, according to the quantity/complexity of enhancements desired. Unless a change order is requested to provide additional support of the enhancement process, the Accenture capacity will remain at six.
22.2
Responsibility Matrix
The table below summarizes the responsibilities associated with Ongoing Operations services:
Scope Element
Define Post Go-Live organizational structure (functional & technical) Identify, document, prioritize and implement desired SRS enhancements Perform knowledge transfer activities Obtain stakeholder agreement
Update use cases Define/Update RICEFW inventories Analyze integration solution
Contractor
Assist Assist Lead Assist Assist Assist Assist Assist Lead Lead Assist Lead Lead Lead Lead Lead
22.3
Deliverables
The work product for the Operations team will provide SRS with a status report of results of the team activities.
Ref. No.
NA
Phase
On-going Operations
Work Product
Operations Status Report
Description
The monthly operations status report includes status for each area of responsibility of the Ongoing Operations team. This includes enhancement support and knowledge transfer. This report is submitted monthly and is tied to the monthly maintenance ebilling.
Version 5.0
Page 147
23.0
Print Mail
SRS will be handling print mail on their own. This document is intended to present how the solution will deliver the appropriate information (i.e., documents) to the SRS preferred print mail vendor. The SRS Avenues printing solution is designed to effortlessly handle the maximum load of bulk printing. The central print architecture is split into a series of specific tasks, each task being executed by a batch module. The modules run in the proper sequence resulting in the print documents being sent to the Departments bulk printing facility using their preferred mode of transfer, e.g. FTP. The central print process involves taking document files from the document storage repository that are marked for central printing, organizing them into envelopes based on their destination, and generating PDF files known as print bundles that are sent to the central printing facility to be printed, folded, stuffed into envelopes, and mailed out to the customers. The central print batch jobs are organized by the mailing priority of the documents to be printed; priority 0 means top priority, 1 means same day, 2 means next day, and 3 means seven day. This way all documents that will be mailed with the same priority are put in the same bundle and it is easier for the printing facility to identify the bundles and organize their print schedules accordingly, thus reducing printing and mailing errors. The United States Post Office (USPS) handles envelopes without a zip code suffix differently than those with a zip code suffix. For this reason, our central print architecture has separate modules for handling addresses with and without the zip code suffix. The bundler modules sort the documents with the same priority code first by zip code, then by zip code suffix, address and finally customer name. This ensures that two customers living at the same address do not receive their documents in the same envelope. The combination of an address and a customer name creates a unique destination and the central print batch jobs process one destination at a time rather than one record at a time. The SRS Avenues solution incorporates smart cost saving features in the way it generates the print bundles. All printed documents addressed to the same destination are placed into one or more envelopes. Documents that require return envelopes are placed in the same envelope if they fit. So, if a destination is supposed to receive two separate documents, and each of the documents is required to come with a prepaid return envelope, only one return envelope is sent, thus reducing mailing costs. There exists a hierarchy to the return envelope type, and since only one return envelope can be placed in an envelope, the organization of print documents into envelopes includes logic to consolidate the documents A final step in the print bundle generation is the barcoding of documents. A special vertical barcode is added to the top left corner of each page of the document. This barcode is used by the folding and stuffing machines to sort the documents and stuff them into the right envelopes. The simple barcode Version 5.0 Page 148
identifies the envelope number, page number, last page and a new zip code indicator. Since the documents sent to the central print facility are already sorted by zip code, the USPS gives a discount on the postage.
23.1
Responsibility Matrix
The table below summarizes the responsibilities associated with Print Mail:
Scope Element
Deliver the appropriate information (i.e., documents) to the SRS preferred print mail vendor
Perform Print Mail functions
Contractor
Lead Lead
23.2
Deliverables
There are no deliverables or work products for the Avenues Print Mail solution.
Version 5.0
Page 149
24.0
Post-Implementation Support
Post-implementation needs for the SRS-Avenues project will be addressed through implementation of the planned K-MED support approach. The K-MED approach includes support for users during deployment of the system and for a period of six months after Phase 2 implementation. Postimplementation support includes both onsite support and centralized support functions. Field staff can access multiple types of help easily and quickly, which helps minimize disruption to business functions and keep error rates and processing times low. Post-Implementation support includes: Central Support Team The Central Support team coordinates onsite support during deployment and for six months after deployment. They will be located in the Topeka project site, and will perform the following activities: Monitor deployment issues and coordinate support and communications as the issues are resolved Answer direct questions from Regional Support teams/provide answers for questions not resolved onsite Coordinate data clean-up efforts Forward issues and questions to the Help Desk as needed Identify trends and report to project management about consistent areas of concern Inform Training and Enterprise Readiness resources of areas that may need additional or different training or online help content to address user support needs
Regional Support Teams Regional Support Teams, comprised of enterprise readiness, conversion, business analyst, and developer project team members, will travel across the state during deployment and in the 30 days after deployment to support users. They will provide direct support to users by answering questions, conducting system demonstrations, delivering ad hoc target topic training sessions, and helping users obtain support from other sources when needed. They will maintain regular contact with the Central Support Team to report status and receive the latest information on trends, project communication, and issue resolutions. Change Agent support Change Agents will support their assigned users by answering questions, assisting users in obtaining additional help, working with Regional Support Teams and the Central Support Team to report and resolve user issues, and keeping their local leadership aware of deployment and post-implementation support schedules and plans. Help Desk The Help Desk will take direct calls from users, record incidents, and track them to completion. Information about the Help Desk facet of post-implementation support can be found in the Version 5.0 Page 150
Help Desk section of the Statement of Work. Accenture will work to develop a strategy to incorporate the Help Desk into the Post-Implementation Support activities.
24.1
Please refer to the K-MED Statement of Work for details on the Post-Implementation Activities by Phase.
Version 5.0
Page 151
25.0
25.1
25.1.1
Archiving (KEEP)
Analyze Phase
The Contractor will determine how to accomplish the results defined in the KEEP interface requirements and the feasibility of implementing the KEEP interface functions during Phase 2 or 3 of the KMED/AVENUES implementation. The results of the analysis may include the recommendation of specific functions to be implemented in separate phases if needed. The Contractor will lead an analysis of this change, and document the necessary plan to make implementation a success. Contractor Responsibilities: 1. Confirm stakeholders and adhere to project governance and communication strategies. 2. Meet with State resources and obtain necessary knowledge and assistance from these resources to identify KEEP requirements and confirm business processes. 3. Document requirements and applicable use cases and business processes resulting from KEEP analysis meetings. 4. Define the conceptual data model required to support the solution plan. 5. Confirm Solution Scope required for successful data exchange between K-MED/AVENUES and the KEEP and the feasibility of implementing during one of the four phases of the KMED/AVENUES implementation. 6. Confirm and adjust the Project Plan based on the outcomes of the Analyze Phase and the defined Solution Plan. 7. Develop the analysis document describing how to accomplish the results defined in the MMIS Member Beneficiary Subsystem requirements. State Responsibilities: 1. Provide technical assistance and expert knowledge to Contractor. 2. Make State Archives, Kansas State Historical Society and K-MED/AVENUES staff available for analysis and work sessions and meetings related to K-MED/AVENUES records analysis, KMED/AVENUES-to-KEEP ingest plans, and K-MED/AVENUES to KEEP interface development. 3. Provide Accenture with the technical specifications and KEEP System architecture.
Version 5.0
Page 152
4. Provide technical and business Subject Matter Experts (SMEs) for KEEP that can efficiently and accurately document/describe K-MED/AVENUES to KEEP requirements. 5. Assist in defining the requirements and applicable use cases and business processes resulting from KEEP analysis meetings. 6. Assist in defining the Solution Scope required for successful data exchange between KMED/AVENUES and KEEP. 7. Assist in identifying adjustments to the Project Plan based on the outcomes of the Analyze Phase and the defined Solution Plan. 8. Make decisions in a timely manner. 9. Review and approve the analysis document describing how to accomplish the results defined in the KEEP requirements. Joint State and Contractor Responsibilities: 1. Comply with the states Government Records Preservation Act (K.S.A. 45-401 through 45414) and Public Records Act (K.S.A. 75-3501 through K.S.A. 75-3520) http://www.kshs.org/government/records/stategovt/recordslaw.htm 2. Contractor will comply with legal, regulatory or operational requirements to providing public access to the records.
25.2
Responsibility Matrix
Contractor
SRS
Version 5.0
Page 153
25.3
Other Considerations
Depending on the results of the analysis and design choices, additional scope may be required as a result of this analysis. Specific performance expectations, deliverables, and other applicable items required to implement the solution will be determined following the analysis to support an appropriate contract Change Order. An initial estimate of implementation costs for the interfaces to KEEP are itemized below:
Deliverable Name Complex Mapping with a Complex Adapter Complex Mapping with a Custom Adapter Total Work Units 1 1 Cost per Work Unit $81,912 $163,824 Payment Amount $81,912 $163,824
25.4
Ref. No.
NA
Description
Consolidation of analysis artifacts including requirements, use cases and solution plan.
Analyze
Version 5.0
Page 154
26.0
The SRS Avenues Virtual Contact Center (VCC) team will be responsible for the design, development and deployment of a virtual contact center using Avenues workers in SRS identified locations statewide. The VCC will use SRS provided telephony and Interactive Voice Response (IVR) platforms built to deliver intelligent call routing, IVR customer self-service functionality, and K-MED CRM reporting resulting from Customer Service Representative (CSR) use of the APSP Communications Tab, and Voice over IP (VoIP) call handling with Quality of Service (QoS) tagging. The SRS Avenues Virtual Contact Center team will be comprised of representatives from the Contractor, SRS, and SRS- IT teams. The following high level responsibilities are defined for the Contractor and SRS and are further defined in the remainder of the virtual contact center section. Component Provided By
SRS, IVR Vendor
Function
Integration Responsibility
Accenture / IVR and Telephony Vendors
Dependencies
IVR
The IVR provides Avenues customer/program centric information to inbound callers. It collects caller provided information like SSN, Case Number, Language preference, etc. for further call processing The Telephony Platform receives caller provided information collected by the IVR, and uses it to route calls using Automatic Call Distribution (ACD) software. The Telephony Platform
Telephony Platform. Integration enables passing of caller provided information from the IVR to the Telephony Platform.
Telephony Platform
Siebel CRM. Integration enables retrieval of caller demographics or other data elements associated with caller provided information. The integration is also has the capability to enable screen pop functionality.
The Telephony Platform integrates with Siebel CRM through a Vendor provided Computer Telephony Integration (CTI) Application Server or Application Interface (API). This integration is essential for CSR screen pop functionality
Version 5.0
Page 155
also passes selected caller provided information to Siebel CRM. This information is used to retrieve caller demographics, case information or other data used for CSR screen pop
Once ACD routing is determined by the Telephony Platform, the information gathered is sent to Siebel CRM which in turn sends caller data to the computer screen of the CSR receiving the ACD call. The computer / telephone association is made through the Siebel Desktop User Interface, described below. APSP. Integration provides retrieval of caller demographics, case information or other data to be used for CSR screen pop functionality. Oracle/ SRS/ Accenture Siebel CRM/ APSP integration required for caller demographics and case information retrieval
Siebel CRM
SRS, Oracle
Siebel CRM uses the caller provided information (passed from the Telephony Platform) to extract caller data from Avenues. This data is coordinated with ACD call routing and appears in the Siebel Desktop User Interface when the call is delivered to the CSR. Establishes link between phone and computer on CSR desktop through CSR login in the Desktop User Interface
Oracle
Siebel CRM. The integration allows Siebel to determine the associated desktop for data delivery once an ACD destination has been provided by the Telephony Platform through the CTI link
Oracle
ACD identification (CSR ID) must be a passed between the Telephony Platform and the Siebel CRM for the CSR phone/computer association to be made
Version 5.0
Page 156
Contractor Responsibilities: Facilitate all VCC detailed design meetings for the build, configuration and implementation of the VCC Develop, test, and deploy call routing strategies aligned with SRS business process decisions Integrate the IVR with back-end database systems to support customer self-service capabilities Modifications to the APSP Communications Tab, reflecting the collection and reporting of SRSAvenues required CRM data, if different from K-MED Development and execution of test plans for call routing, IVR self-service functions, and Communications tab data collection and reporting Develop the organization structure, transition plans and training plans for VCC staff, including the creation of CSR and VCC Supervisor/Manager Role descriptions. Analysis of Toll Free voice network facilities to accommodate consolidated VCC call load Mentor SRS testing staff on the development of test plans for future functionality. Document all VCC detailed designs for review with SRS-IT staff Assist with Data Network Analysis/Sizing for VoIP test and deployment Assist SRS staff with recommendations for office reconfiguration to accommodate VCC
State Responsibilities: Providing direction for the development of call routing strategies. This includes determination of functional CSR groupings that include; program type, call type, and customer language selection Providing base IVR and telephony systems Providing the Contractor with administrative access to VCC base systems, IVR, Telephony, and associated databases or other SRS systems, as required Staff the VCC team with State personnel that are qualified in their area of participation (IVR, VoIP Telephony, Voice and Data Networks, Automatic Call Distribution (ACD)). Acquisition of necessary hardware, software, and network facilities required for the build out of the VCC. This includes change orders with suppliers and vendors of existing VCC infrastructure Provide training staff for instruction of VCC Customer Service Representatives Page 157
Version 5.0
The following VCC implementation steps are in scope. An implementation step is defined as a functional component required for the deployment of the Avenues Virtual Contact Center.
VCC Platform Implementation Steps
10 Simple Call Routing Patterns 2 5 Moderate Complexity Call Routing Patterns Database integration with APSP 3 Telephony platform integration Develop and execute IVR test plans Create detailed design document of Avenues IVR end state build out IVR knowledge transfer to SRS staff Assist SRS-IT staff with analysis of SRS data network for required VoIP capacity VoIP Telephony design, test and deployment to SRS offices or other Avenues workers Conduct call capacity analysis for consolidated toll free service for statewide calling Assist SRS-IT staff with resizing of voice network circuits, if necessary Establish skills based routing through the ACD Identify individual offices in ACD routing patterns for effective closure procedures Standard ACD reporting Assist SRS trainers with the development of VCC CSR curriculum for Telephone/ACD use Create detailed design document of Avenues Telephony / ACD end state build out Telephony / ACD knowledge transfer to SRS staff
1
IVR
Modify APSP Communications Tab to capture SRS-Avenues required data, if different than K-MED Create detailed design document of Avenues Communication Tab K-MED CRM functionality knowledge transfer to SRS staff
Simple Call Routing Patterns employ no database calls, providing callers static information, e.g., program descriptions, hours of operation, addresses of local offices, etc. 2 Call Routing Patterns with Moderate Complexity have 1-3 database calls, using integration with back end database systems to provide secure, caller specific information, e.g., application status or program eligibility. 3 May not be attainable if systems referenced are incompatible or do not have this capability
For clarity, the following steps are out of scope for SRS Avenues:
Related VCC Platform
IVR
Version 5.0
Page 158
Complex call routing patterns employ 4 or more database calls or collect caller supplied data for compilation and reporting. Customer surveys are one example of an IVR complex routing pattern.
26.1
26.1.1 26.1.1.1
The purpose of the analysis effort is to identify SRS requirements related to VCC customer contacts. The VCC team analyzes customer contact criteria provided by SRS and develops call routing strategies that work within the SRS Avenues IVR/Telephony framework. These strategies employ the dissemination of public information (e.g., program descriptions, eligibility requirements) or caller specific information (e.g., customer application or eligibility status), and the statewide routing of calls to properly trained CSR resources. The VCC analysis phase focuses on: 1. Gap analysis of current IVR capabilities and those required under SRS Avenues. 2. The impact of call consolidation on existing toll free circuits determination of anticipated call volumes 3. Call consolidation impact on IVR port size and licensing 4. VoIP hardware/software/licensing for existing telephony platform 5. Analysis of data network capacities required for the deployment of a statewide VoIP solution 6. Verify IVR / Telephony integration required for passing call routing variables 7. Verify ACD capabilities required for intelligent call routing 8. Selection of web portal service calls to be used for customer specific inquiries (database dips that provide the same secure information available through the Customer Portal) 9. Identification of customer contact resources by program knowledge (skill) and language capability (if bilingual support is required).
Version 5.0
Page 159
Contractor Responsibilities: Conduct meetings with SRS and SRS-IT to identify IVR self-service requirements and define call routing through the VCC Assist SRS-IT with technical assessments of existing voice and data networks, and the processing of change orders with network providers, as required Perform Gap Analysis to identify gaps between legacy IVR and telephony systems compared with Avenues VCC requirements Work with SRS-IT, and IVR and telephony vendors to determine the level of integration permitted between systems Work with SRS-IT and APSP personnel to determine SRS-Avenues changes required in K-MED Communications Tab Report integration issues and impacts to SRS. Develop high level test conditions and expected results. Confirm and adjust Project Plan based on the outcomes of the Analyze Phase.
State Responsibilities: Provide Subject Matter Experts (SMEs) for each VCC system and related network. Process network change orders to provide VCC required voice and data capacities Process change orders on existing IVR / Telephony platforms to meet Avenues VCC requirements Assist in the development of high-level test conditions and expected results. If legacy IVR /telephony functionality is reused in the delivery of Avenues, SRS will take responsibility for testing those portions of the legacy systems. Review and approve the Gap Analysis. This is an important activity since the integration of multiple systems is key to the attainment of VCC objectives. Make design decisions in a timely manner. Confirm and adjust Project Plan based on the outcomes of the Analyze Phase.
Version 5.0
Page 160
26.1.2
Design Phase
Based on the requirement definitions and analysis done to this point, the Virtual Contact Center design phase specifies the IVR, Telephony and K-MED CRM components that will be required for VCC. The design specifications will: 1. Refine the initial Gap Analysis and document processes needed to address each gap 2. Confirm the level of IVR/Telephony integration 3. Confirm the IVR use of APSP web services for data retrieval 4. Confirm the K-MED Communications Tab changes in APSP 5. Confirm reuse of existing IVR/Telephony programming, if required. 6. Confirm the web services to be used in the IVR 7. Confirm network capacities for VCC voice and data networks 8. Detail the statewide VCC organization structure and floor space reorganization, by office, if required Contractor Responsibilities: Provide SMEs for IVR and Telephony design Provide SRS-IT with voice and data network analysis indicating the need for circuit change orders Lead design of intelligent call routing strategies base on Avenues requirements Work with SRS equipment vendors to verify systems integration design Work with APSP SMEs to incorporate APSP web service calls into the IVR design Work with APSP SMEs to modify APSP Communications Tab, if needed Escalate system integration issues to SRS Create VCC systems design documentation Create VCC Organizational diagrams including Management/Supervisory structure and CSR groupings by skill/program/language Create revised floor plan documents for VCC offices requiring change Initiate mentoring with SRS team members for project design. Page 161
Version 5.0
State Responsibilities: Evaluate call routing strategies to ensure compliance with Avenues customer contact directives. Assist the Contractor with the development of the Design Documents. Confirm selected web services will provide the specific information required Confirm APSP Communications Tab changes Assist with equipment vendor meetings for integration design Assist Contractor with documentation of VCC staffing by office, skill, program, and language Provide Contractor with floor plans of all new or existing VCC offices Actively participate in design mentoring activities
26.1.3 26.1.3.1
Produce Detailed Design documents for the VCC systems functionality approved during the Analyze Phase. Contractor Responsibilities: Produce Detailed Design documents for IVR call routing and self-service functions Produce Detailed Design documents for the Telephony System / ACD call routing functions directed to VoIP endpoints, by skill Produce Detailed Design documents for VCC voice and data networks
SRS Responsibilities: Assist the Contractor with the development of the Detailed Design document for the VCC IVR, Telephony system, and end-state voice and data network design. Review and approve each of the Detailed Design Documents
26.1.3.2
The Virtual Contact Center Team will code and unit test each VCC system.
Version 5.0
Page 162
Contractor Responsibilities: Code the IVR and Telephony systems with VCC designed call routing patterns Program IVR/Telephony integration Program IVR/ Database integration using APSP web portal web services Work with APSP SMEs to modify APSP Communications Tab functionality, as required Create platform specific test-scripts Conduct and document VCC systems testing as part of the development documentation Work with SRS training staff on the development of VCC training modules Create mentoring opportunities for State teammates during VCC platform builds
SRS Responsibilities: Review and approve the system test-scripts and system test results developed by Contractor SRS training staff begins development of CSR training modules Actively participate in build out of each VCC platform / application
26.1.4 26.1.4.1
The Virtual Contact Center Team will conduct end-to-end testing on call routing patterns in the Avenues IVR. This includes testing of simple and moderately complex route patterns and their associated voice files and database lookups. Contractor Responsibilities: Develop, plan, and execute detailed test plans for all VCC IVR call routing patterns and functions, including informational messages and database integrations Execution of test plans related to call routing for dissemination of general information, including SRS office locations, hours of operation, program descriptions, and other required messages. Testing to include accurate routing and messaging for bilingual callers, if required Execution of test plans related to all call routing patterns requiring retrieval of database information for callers seeking specific information related to their application or case status (web services testing) Page 163
Version 5.0
Mentor State team members in the development and execution of IVR test scripts
SRS Responsibilities: Assist with verification of call routing patterns and the accuracy of information provided in each Assist with the development and execution of IVR test plans Provide client test case information for database retrieval, including multiple test clients with data for each testable parameter (application status, program eligibility information, etc.) Actively participate in the development and execution of IVR test scripts Review and approve IVR test results
26.1.4.2
The Virtual Contact Center Team will conduct testing of VoIP telephony for each Avenues office location during normal production hours to ensure proper Quality of Service (QoS) tagging and adequate data bandwidth for all CSR required applications, including VoIP. This testing will be done in conjunction with ACD skills-based routing tests that will verify call routing to appropriate CSR agent groups across the state. Contractor Responsibilities: Execution of test plans related to all CSR identified skills, including program related and language related CSR call queues Develop, plan, and execute detailed test plans related to all VCC Telephony and ACD functions, including VoIP testing for IP telephony in each VCC location, and ACD routing and reporting VoIP quality check to ensure near toll quality voice transmission to each IP connected telephony location Test ACD office closure procedures for each Avenues VCC location ACD information storage and retrieval using standard ACD reports (platform dependent) Verify statewide access to the consolidated toll free number used for IVR/Telephony access Verification of IVR / Telephony integration through caller qualified identification being collected in the IVR and passed to the telephone system. Verification of APSP Communications Tab functionality, including customer data retrieval from APSP Page 164
Version 5.0
Verification of APSP Communications Tab reporting, including contact type, contact duration, CSR identification, reporting by location, and other specified parameters Mentor State teammates in the development and execution of all telephony / ACD test scripts Support SRS training staff for VCC CSR training sessions
SRS responsibilities: Assist with Telephony / ACD testing for statewide access, skills based routing, office closure procedures and systems integration. Active participation in the development and execution of ACD / Telephony systems test scripts Review and approve Telephony / ACD test results Initiate VCC CSR training sessions
26.1.5 26.1.5.1
The Virtual Contact Center Team will execute a flash cut installation of the VCC IVR. Following the successful completion of the IVR testing and at an SRS approved time, the new VCC IVR code will be promoted into the Avenues production environment. Contractor Responsibilities: Promotion of the VCC IVR code from the Avenues test to production environment Monitor toll free line access(voice network) to the IVR system Monitor IVR port capacities to ensure customer access Monitor IVR performance with regard to system integration and web service functionality. Mentor State team members for functional monitoring and ongoing support of the IVR
State Responsibilities: Assist with IVR performance monitoring following IVR go-live Actively participate in post-deployment IVR mentoring Review and approve successful IVR deployment
Version 5.0
Page 165
26.1.5.2
The Virtual Contact Center Team will execute a phased installation of the VCC Telephony / ACD platform. Once VoIP testing on the telephony platform has been completed, a staged approach will be used to roll out VCC functionality to Avenues locations across the state. This staged deployment will use the VCC programmed capability of closing individual offices. In this way the VCC team will be available to each office for day-one support as VCC functionality rolls out. Contractor Responsibilities: Promotion of the VCC Telephony / ACD code from the Avenues test to production environment Monitor skills based routing, including CSR availability, queue times, and abandon calls Monitor CSR use of APSP Communications Tab Assist SRS-IT with data network performance monitoring for VoIP active location Mentor State team members for functional monitoring and ongoing support of Telephony / ACD systems
State Responsibilities: Assist with go-live monitoring of VCC Telephony / ACD functions during staged call center roll out Provide vendor liaison support with voice and data network providers, as necessary Actively participate in post-deployment Telephony / ACD mentoring Review and approve successful VCC Telephony / ACD
The table below summarizes team responsibilities for the Virtual Contact Center implementation.
Scope Element
Create call routing patterns (IVR) Gap Analysis of existing IVR/ Telephony systems Order hardware/software for IVR/Telephony systems Voice network analysis (toll free call consolidation) Data network analysis (VoIP capacity) Voice / Data network change orders IVR / Telephony Integration APSP Communications Tab modifications IVR/ Database Integration (web services) VCC Training Curriculum development Lead Lead Lead Assist Lead Assist Lead Lead
Contractor
Assist Assist Lead Assist Lead Lead Assist Assist Assist Lead
SRS Team
Version 5.0
Page 166
Scope Element
ACD reporting VCC knowledge transfer Develop cutover plan VCC testing Lead Lead Lead Lead
Contractor
Assist Assist Assist Assist
SRS Team
26.2
Other Requirements
None identified.
26.3
Deliverables
The table below summarizes the virtual contact center deliverables/work products to be created during each phase:
Ref. No.
41
Phase
Deploy Design
Description
The Virtual Contact Center Team will execute a phased installation of the VCC Telephony / ACD platform. The Organization Design for the SRS-Avenues Virtual Contact Center documents the infrastructure and staffing required to deploy a statewide call center. This design incorporates intelligent call routing through the VCC IVR, skills based routing to CSR resources across the state, and program efficiency gains using IVR self-service. Based on the requirement definitions and analysis, the Virtual Contact Center detailed design document specifies the IVR, Telephony and K-MED CRM components that will be required for VCC.
44 45
Virtual Contact Center System Test Plan Virtual Contact Center System Acceptance Virtual Contact Center System Documentation and Knowledge Transfer Working in collaboration with SRS personnel, this deliverable will document the design, build and testing of each Virtual Contact Center component. A resource that is available to SRS staff who may be new to VCC, it is also a living document that details the continuing change that will occur as the VCC adapts to changes in program, policy and technology.
46
Version 5.0
Page 167
27.0
Business Process Reengineering (BPR) and Business Process Improvement (BPI) Change Management
During the Business Process Reengineering and Business Process Improvement phase, we conduct an assessment of which business processes will impact SRS such that they need to be included in the Design Phase. The BPR work effort is expected to be completed by Change and Innovation (CIA), in conjuction with Accenture. Any Business Process changes that are not included in the Design Phase could be deferred to a post-implementation work effort.
Version 5.0
Page 168
Version 5.0
Business Activity and Task Descriptions recommendations, Procedural Manual, Process Measures; Implementation Plan
Leadership of 1-2 day sessions where staff are finalizing the deliverables once approved by Agency Leadership Working with local leaders on a weekly basis going through implementation plans, informing SRS of any roadblocks, providing management training. Provide a team of 3-5 over a very structured 4-day implementation of the new process. Develop a group of internal experts to carry on with roll-outs (usually after 10-15 offices). As offices go-live, we will initially facilitate a weekly phone call between office managers and the SRS operations leader to discuss performance, find consistent fixes, etc. The results of these calls will be documented and distributed to the appropriate individuals. Conduct shorter planning sessions with three facilities per session to build their Process Management Plans Review implementation plan progress, provide management training. - Provide a team of 3-5 over a very structured 4-day implementation of the new process.
Facility Readiness
Review of Performance
Contractor Responsibilities: Create the SRS Business Process Reengineering approach and teach the approach to State partners to assist in carrying out the activities. Research, evaluate and identify new business practices.
Version 5.0
Page 170
Identify a plan of implementation of the new business processes, work with SRS to establish and maintain a model business process office, and aid the state in the rollout of these new processes, training, education, and any other aspects of successfully transitioning the organization to the new business processes. Measure the benefits of the changes by collecting business process metrics via detailed performance reporting during the Model Business Office. Conduct the assessment activities and communicate the results iteratively with key stakeholders to refine the approach as needed along the way. Work with SRS to understand the factors that influence appropriate organizational design decisions such as: The agencys mission and how the new technology strengthens it Shared values, the beliefs that guide actions and behaviors within the organization Core competencies, what the agency does really well and wants to continue doing well o Key Performance Indicators, what and how SRS measures success. Analyze your organization charts, position descriptions, and the work you have already done to document your as-is processes. Participate in BPR/BPI activities and project fit gap analysis sessions to gain an understanding of the to-be business processes. Conduct a SWOT analysis to identify and document the strengths, weaknesses, opportunities and threats that influence SRSs ability to achieve the projects objectives. Facilitate working sessions with SRS personnel to identify the impacts of the new processes on the organization and job roles. We foresee multiple sessions so that we can spend adequate time with the various business units, ITS, and SRS leadership. Document information about the current organizational model and behaviors. Develop initial suggestions for the future organizational model and how team policy should occur. Once we present the initial recommendations to SRS leadership and other personnel SRS identifies, we refine the Organizational Assessment to reflect the feedback. Upon acceptance of the initial recommendations, we work with you to identify specific SRS staff to participate on the Organizational Change Team. We see this team as a natural part of the overall Change Management team who is already in place on the project to support the change management efforts. Designated SRS and Accenture change management team members work together with HR to create more detailed recommendations and perform the analysis required to modify organization charts, job roles, skills requirements, capacity planning, and transition activities. Conduct the ITS Organizational Assessment effort. Evaluate the ITS organization and produce the deliverables associated with the states requirements, including resource needs (both the SRS and third party models), training needs, skills sets, a knowledge transfer/mentoring plan and a recommended IT governance strategy. Page 171 o o o
Version 5.0
State Responsibilities Provide detailed and comprehensive list of the As-Is Business processes and and indication of the variations in these As-Is processes among local offices, where available. Assist the Contractor in the research, identification, and evaluation of new business practices. Assist in the development of the Concept of Operations document. Provide input regarding stakeholders and levels of involvement. Assist the Contractor in identifying a plan of implementation of the new business processes. Establish and maintain a model business process office, and participate in the rollout of these new processes, training, education, and any other aspects of successfully transitioning the organization to the new business processes. Provide staff to attend and participate in the Model Business Office to test new processes. Provide a select pool of SRS Staff (e.g. Change Agents and BAs where available) in the BPI effort. We recommend selecting participating users from various offices across the state that the K-MED/Avenues solution must support. The State will review the Organizational Assessment work products and participate in refining them prior to finalizing them. Assist the Contractor in gaining access to the documents, plans, staff, and governance forums needed in order to conduct the organizational assessment. Assist the Contractor in the development of the IT Organizational Assessment. Assistance includes identification and input regarding organizational charts, staff, access to interview and work with staff, and access to planning documents and governance forums. The State would review the ITS Organization Assessment work product that will be included in the Organization Assessment deliverable. Deliverables/Work Products
27.2
The table below summarizes the deliverables to be created during each phase:
Ref. No. Phase 2 Deliverables BPR Assessment Description To-Be business model, business processes and workflow swim lane diagrams Gap analysis of business processes and requirements Detailed business requirements document including an established requirements traceability matrix
Version 5.0
Page 172
Ref. No.
Phase
Deliverables
2 2 2
Conversion Plan
Version 5.0
Page 173
Version 5.0
Page 174
APPENDIX
Version 5.0
Page 175
Version 5.0
Page 176
As the State of Kansas prepares to select a trusted business partner to jointly execute the K-MED and Avenues projects, it is important to ensure the partners share a common vision. Accenture and the State have been mildly introduced during the K-MED evaluation process, and the state has been able to further communicate its vision.
SRS has joined in the evaluation and procurement process of the K-MED project by including the scope of the Avenues project as an optional bid of the RRO. The Avenues project scope includes the eligibility, benefits administration, and case management for the means tested programs within the Department of Social and Rehabilitation Services (SRS) for the state of Kansas. These programs primarily reside in the Economic and Employment Support (EES) unit within the Integrated Service Delivery division of SRS.
To ensure alignment of expectations, this document describes the State of Kansas vision for the KMED/Avenues system and what the state intends to achieve by successful project execution. The scope of this document applies mainly to the means tested programs administered by SRS.
Version 5.0
Page 177
SRS conducted a current state evaluation of their organization, processes and technology by conducting site visits and staff interviews which revealed a setting in which linear work and labor intensive processes are the rule, rather than the exception. The Information systems supporting the current environment provide little relief from the paper-based business processes, and in some situations, they contribute to the creation of additional paperwork. The following lists some of the major inefficiencies that are prevalent within the current environment and how we envision correcting these in the future: Processes: Current: The current processes are full of manual steps, rework, and handoffs. There is a certain level of rework that is inherent in handoffs of work; the person on the receiving end of the hand-off must review the work previously completed in order to complete his or her task. Hand-offs often leads to bottlenecks in the workflow. For example, when an application for EES benefits is received, in most of the offices visited, the application passes through at least four different staff members before it is processed. The application is handled by the receptionist, screener, a clerk who registers the application and the Case Worker. At any step of the process, the application can become bottlenecked or be returned to the previous worker. Future: With the use of automation, an integrated work-flow engine, integrated business rules, content management, and the customer providing the majority of our data entry; rework and excessive handoffs will be eliminated or drastically reduced. The initial steps that are currently completed by SRS staff members to register an application can be automated and only exceptions will be processed by SRS staff. SRS understands there will be instances when human intervention is required as it is not feasible to try to put every situation into the business rules when trying to resolve people identification and household composition issues. Current: The current processes are full of workarounds and manual steps. Case workers currently have paper case files for each of their assigned case located at or around their desk. There are no electronic case files. This limitation makes it necessary for customers who call in to make changes or request information to speak directly to their case worker rather than a more generalist staff member. If a customer moves or wants to relocate to a different office, staff has to copy the case file and mail it to the other office which delays the customers ability to work with that new office for a few days. Future: Content will be captured electronically and the content management solution will be fully integrated into the new Avenues system. To the end user, the content management system is simply a part of their new benefits administration and eligibility system. Staff and customers will see all content related to a case on their user interface of the Avenues system and will be allowed to add additional content, view content, and delete content (with the proper security). Content will be viewable by staff and customers at a customer and/or case level. Customers and staff will have the ability to scan documents at an SRS office or at a Version 5.0 Page 178
community partner as well as sending in electronic documentation. The system will have the ability to index and automatically attach documents to a customer/case record given the proper information is supplied by that customer/staff. QA processes will reside in both the offices and the Records Management Center. As a part of this effort, SRS will convert existing case file content for cases that are currently open. SRS will analyze which documents are necessary to convert and attempt to clean out the current case files in advance. Because the case files are needed in instances where a customer contacts their case worker, the case files will have to be converted at their physical location. SRS is open to doing this conversion prior to the implementation of the Avenues system. The hardware and software necessary to convert these documents could be implemented at a location at a time and we could convert location by location, moving the larger scanning equipment to the next location. We understand this will require training of our staff and the utilization of a stand-alone content management system prior to the implementation of Avenues. Current: With some exceptions, limited knowledge of programs within and outside of SRS leads to limited referrals for customers to other SRS and community-based services. Some of the smaller offices in the Southeast Region have employed generalists who screened for all programs and worked closely with outside agencies to become aware of services available in the community. This model worked well for customer service but given current economic conditions, these workers have been moved back to caseload management. However, this was not widespread among all of the offices. In addition, each of the Regions have staff members that are responsible for working with the community to ensure access points are staffed with information about SRS benefits and application forms. However, there is no central repository of information about services outside of SRS for the staff to access to pass this information on to the customer. The current SRS Website only provides the customer with information about services SRS provides, not what is provided in their community. Future: SRS will provide access to a service locator on their Customer Portal in order to assist customers with information about services provided in their area. The customer will be able to put in the kind of services they need (such as assistance with food) and the service locator would provide them a list of places that may be able to assist (such as a local food bank or WIC). This service locator could be built as a part of K-MED/Avenues or we could provide a link to the current 211 system in Kansas. SRS will continue to work with community partners to ensure they have updated information regarding SRS programs, how to assist the customer with the application process, and how to easily interact with SRS to develop more partnerships. Current: New or expanded programs and responsibilities have been added with little or no system, and financial, or additional staff support. The regions are expected to determine the best way for their region to implement these changes, thus resulting in 6 (or more) different ways to implement. This means that 6 times the necessary resources are used to come up with the implementation plans, ongoing support, and possible creation of ancillary systems. The more efficient way to implement these changes would be to have a responsible entity develop Page 179
Version 5.0
the best implementation plan, systems required to support this change, provide the costs for the implementation and ongoing support and maintenance. Future: Prior to adding new programs or expanding existing programs, individuals within Policy and Program Management will be knowledgeable in the areas of policy, rules, systems, procedures, and contracts. These staff will be involved with several related and integrated business activities that start with continuous monitoring and research of proposed legislative changes and the economic impact to SRS customers. The staff in this role must have the capability to respond quickly to prioritize programmatic needs that are driven by legislative and budget concerns and constraints. Data will be available to this team to allow for proactive costeffective decision making for policy development and implementation. The Policy and Program Management staff will have the capability to utilize the automated system to forecast policy/program changes for a group of selected cases and once the system-generated results are available, shall analyze the effects of the changes and the impact to the corresponding program(s). Such analysis may include, but is not be limited to, dollar savings or increased costs, the number of cases impacted, and eligibility impacts such as the number of cases closed, additional cases that would be eligible, amount of benefit changes, etc. Once changes have been approved and prioritized with the other requests, the Program and Performance Management staff will work with ITS and training staff to determine the process, training and system changes required to properly implement the changes in the field. Training staff will update or develop the training materials and conduct the training necessary to properly train field staff prior to the implementation of the change. SRS will have the ability to provide training in multiple methods, some of which might be: in person, via recorded session, online tutorials, etc. Current: There is no way for SRS to monitor and measure business processes. The current business processes are manual and typically sit outside of the systems, making them impossible to measure or compare them. This information would be very helpful when trying to ensure that all customers are going through the same process, or determining which of the regional processes are most efficient and trying to implement them in the other offices. In the current environment, policy staff do not have ownership over the processes yet are oftentimes accountable for correcting process issues. Future: In the future business model, the new technology will allow staff access to the duration each task in a business process takes, down to a person level. This information will assist management in determining where possible bottlenecks are present and allow them to see if staff are deviating from that process. This role will be responsible for instructing field staff on the correct performance of tasks and how to implement policy procedures. These staff members will ensure consistency and standardization of processes across all regions. These staff will work closely with the Policy and Program Management, Training and ITS staff when changes are required to the business processes and the system. Current: The interaction between SRS and KHPA appears convoluted and cumbersome. There is a blurry demarcation of duties between KHPA and SRS related to the Medical Assistance programs. Some types of applications are only processed by SRS (Elderly and Disabled); others Page 180
Version 5.0
are processed by either agency; while other applications are only processed by KHPA. In some situations, such as the receipt of an EES Family/Children application for benefits, the application is initially submitted to SRS where the Case Worker processes the eligibility. However, once the initial eligibility is determined, the SRS Case Worker copies and transfers the Medical Assistance portion of the case to KHPA, but retains the TANF portion of the case. At that point, any changes to a customers circumstances require action both on the part of the SRS and KHPA Case Workers. (Please keep in mind, this is for current state only and does not reflect changes that will be done in the future as a result of the K-MED project.) Future: KHPA/KDHE and SRS will have an integrated system in the future which will store the customer information, documents, and case information. Customers will no longer have to notify both agencies when they need to report a change to their demographics or provide documentation. SRS staff will no longer have to photocopy paper documents to send to the Clearinghouse, the necessary documentation will be electronic and available to KHPA. When a customer requests services from both agencies, an electronic notification will alert KHPA they have a medical case if there is processing to complete on that case. The Elderly and Disabled cases will continue to be processed by SRS, this includes the case management. The integrated system will allow KHPA and SRS to easily share historical and demographic documentation to make the process more customer friendly. For instance: if a customer has had a medical case with KHPA but no services with SRS, if they apply for SRS services most of their information will already be in the system as well as documentation necessary to meet federal guidelines. Organization: Current: Roles and responsibilities of field staff varied from location to location. Even when staff performed the same process, they may do it differently than the other location. This can cause inconsistencies in your results and makes it difficult for staff to transfer to another location. Training appeared to be light once the initial training was completed. Shortcuts that are learned from staff are not often shared with others to gain those efficiencies. Future: Standard processes and roles will be implemented with this project. Management will ensure processes are executed in a standard manner across the state; this includes standardization of roles performing the tasks. There will be standard training documentation for new staff, the implementation of new functionality, and ongoing training. With the ability to monitor the business processes down to the task level, they will have the tools necessary to determine if retraining is necessary for some staff. Current: Although, there is a customer service office today, their function is to take complaints and then distribute them for resolution through the regional customer service staff and central office. There is no single entity responsible for customer service in the agency, yet that is one of the strategic goals. When there is not a single point of contact responsible for something as large as customer service, there is really no one to hold accountable. Customer services are not measured in SRS today.
Version 5.0
Page 181
Future: A primary change with the implementation of Avenues is the development and implementation of the Virtual Contact Center which will provide the initial single point of contact for customers when accessing services in person, by telephone, or other electronic means. The Virtual Contact Center will consist of: Customer Service Representatives (CSRs) who will be located at local offices to assist customers who walk-in to the office seeking information or to apply for services Customer Service Representatives will answer routine inquiries when customers call for assistance, or contact SRS with other electronic means such as email, chat, etc. Customer Service Representatives will be responsible for manually entering any paper applications that are received at a local office Help Desk personnel will assist with computer-related problem resolution
The purpose of the Virtual Contact Center is to serve the customer by handling all routine inquiries whether made in person, via phone or by email. This unit will consist of the various CSRs, staff members that are generalists with a generalized knowledge of all EES program areas and a broad knowledge of services available within the community. Regardless of whether located in the Virtual Contact Center or in the Local Offices, the CSRs will be responsible for handling all routine inquiries, performing triage, gathering information, assisting with referrals to community agencies and performing pre-screening activities as well as assisting the customer in completion of their online application. The new solution will provide the capability for the CSRs to enter and track all customer inquiries and complaints. If the inquiry/complaint can be handled by the CSR, they will log that transaction and close it. If the inquiry/complaint cant be handled by the CSR, the transaction will be assigned (or forwarded) to the proper staff. All inquiries/complaints will be logged and monitored to determine the agencies challenges and allow SRS to measure our customer service. SRS will utilize workflow to route the inquiry/complaint to the proper person or queue. Management will monitor the queues to ensure these transactions are being managed in an acceptable timeframe. Technology: Current: Customers are currently limited in their choice of service channels. The systems do not provide sufficient web accessibility for the customers or staff. SRS currently provides the customer with an online screening tool and online application. With the implementation of CAPP, the screening tool and online application will be updated to be more user friendly and there will be some integration with the legacy systems. The online application allows the customer to apply for TANF, Food Assistance, and Child Care Subsidy. This portal has very limited access and does not allow the customer to apply for other benefits, view their case information, update information, or request other services. Future: The customer portal will be significantly expanded with Avenues. The screening and online application will be expanded to include all programs within the scope of Avenues and KVersion 5.0 Page 182
MED and will be fully integrated with the K-MED/Avenues system this includes the eligibility and benefits administration system, MDM, telephony, and content management system. The customer will have the ability to apply for new services, view their information, add documentation to their case, and change information. If a customer has questions or concerns when using the portal, they will have the options of an online chat with a CSR, contacting a CSR via phone, or sending an email to the CSR mail queue. The online chat and phone options will be available during normal business hours. If the customer calls on the phone, the Interactive Voice Response (IVR) system will pass the identifying information (customer ID of some type) into the case management system of the CSR answering that call to pull up the case information for that customer. SRS would like the ability for the CSR to view exactly what the customer is seeing on their screen. When a customer makes a change to their information, the proper workflow will be activated to take proper actions based on the type of change. An example is a change of income source; the workflow would generate an employer letter or automated interface. Current: SRS staff members are required to rely on numerous cheat sheets in order to enter a correct code in the legacy system or understand the information that already exists in the system. Each system has its own set of required codes that are entered so the workers have to look up codes in two or more separate guidebooks. New employees require lengthy training to understand use of the system and Social Workers and staff at outside agencies, such as the hospitals, report that it is easier to email or call SRS staff as opposed to trying to decipher the codes that exist in the legacy system. Any external contractors that have access to the system also are reliant on SRS staff to understand the data that exists in the systems. Future: The new system will not utilize cryptic codes, meaningful words will be used and dropdown lists and/or radio buttons will be utilized whenever possible. The system will utilize workflow and screen flow to traverse the customers, staff, and partners down the necessary path. Smart scripting will be utilized so the end user will not have to answer unnecessary questions or go down a path that is not necessary for their particular need. Training needs will still be necessary, but there will no longer be a need for staff to memorize codes and policy information as it will be accessible and understandable from the system. Online tutorials and help will be available for all types of users. Current: The systems lack checks and balances or editing within the systems to ensure that cases are not established incorrectly. There is no automated check to show if a customer is a part of another family on another case or if a customer is receiving benefits in another program area; all of these checks are completed manually. Changing of demographic information is not automated and requires staff to manually search systems to determine where the change should be applied. Future: The new Master Data Management (MDM) will be utilized as the Master Client Index (MCI) for KHPA and SRS. The MCI will house the common information for all customers known to the system. One common client index will be utilized regardless of the agency. The system will have the ability to show all relationships of that customer to any case information, making it much easier to determine what services that customer may currently have or has had in the Version 5.0 Page 183
past. Household composition will be easily determined within the new system to ensure staff has the overall view of the customer and household. When a customer or partner enters information into the portal, the system will automatically do a customer and case search for everyone on that application to ensure we are not duplicating benefits or adding duplicate customers to the system. The business rules engine will provide the rules for determining customer and case matches. If all rules pass, the system will automatically register the case and determine eligibility. If all rules do not pass, that application or change will go into a queue for CSR processing. The system will allow the CSR to look at the rule(s) that failed and resolve any issues, and then the case can move forward in the registration and eligibility process. Current: The systems that are utilized to support these services have been built independently by program area and are old and antiquated. Most of the systems were transferred in from other states and were built using business models that were not in alignment with Kansas which caused them to be heavily modified and difficult to maintain. Most systems were built using different programming languages and technology making it difficult to utilize programming resources across the different systems. These technologies are older and not easily modularized or extendable like current technology options. The business rules are coded into the system and not easily identified and can reside in multiple locations. The systems were not meant to support the number of programs and services that we have today, so the programmers often times have to fake the system into doing something different. With the older technology, it is increasingly difficult to find staff to support these systems when state staff retire. SRS has had to contract for support in many instances which increases the cost of ownership for these systems. These legacy systems run on the mainframe and as other state agencies modernize their systems, SRS costs continue to rise as our agency share of usage continues to rise. Future: The future system will be service oriented architecture (SOA) compliant. SOA takes common business applications and breaks them down into individual business functions, called services. SOA allows you to build, deploy and integrate these services, independent of the applications and computing platforms on which they run. Rather than building separate standalone systems to meet each programmatic requirement, the framework will be a collection of software products or modules that fulfill functional business needs across all programs within Avenues/K-MED, integrated through service oriented architecture. These new technologies have inherent functionality that can meet a broad spectrum of business requirements and can be configured, rather than requiring custom software development, to meet specific program needs. Business services created with these new solutions are reusable within the system which will decrease development time and cost and provide the flexibility to respond to the constantly changing business environment. This comprehensive approach will enable flexibility when adding new programs or modifying existing programs. The business rules, business process management, IVR, workflow management, content management, business intelligence, and MDM will be components that are not embedded in the system, making them more easily modifiable and traceable. All system components will be integrated, making it appear to the end user as one comprehensive system. An example of this is the integration of the case management system with the content management system. The end user will have a listing of all content for a customer or case on their screen and have the ability to click on a link of that content and it will be brought up in a new window for that end user to view. Version 5.0 Page 184
Configuration Specialists, Application Administrators, and Integration Specialists are new roles to the agency. Support and maintenance right after implementation will be completed internally with the assistance from a vendor for training and mentoring, with the goal to become more self-sufficient over time. The vendor could be utilized for quick ramp-up for future enhancements or emergency cases. Current: Information gathering requires both paper documentation and data entry into the systems. The systems oftentimes do not interact with each other and do not populate the appropriate fields with data that is entered in another SRS system, thereby requiring the staff to enter the same data in two or more separate systems. For example, if an applicant is applying for both TANF and Child Care benefits, the information that is on the application form has to be entered in both KAECSES-AE and in KSCares. This duplication of effort is very inefficient and error prone as keying errors can be made. Future: All programs within the scope of Avenues and K-MED will be included in the new comprehensive and integrated system and data will be shared between the programs, thus reducing the amount of data entry for the customer and staff. Documents can be captured once and shared between programs. Documents can be viewed at a customer level or a case level but will only be stored in the system once. If a customer is already registered in the Customer Portal, information can be pre-populated for them to reduce the data entry necessary for them to reapply or expand their benefits. Current: The database technology used in most of the systems does not easily lend itself to user access, making it difficult to create ad hoc reports. This has also limited the amount of integration that can be accomplished among the systems. The current systems are more like data repositories and do not contain many of the automation features of newer technology. Future: The new system will be built on more modern relational database technology. There will be a separate data repository for reporting and business intelligence. The end user will have more robust capabilities with expanded data elements for producing ad hoc reports based on their security. Their access to information will be on a more real-time basis than what they have today. The business intelligence repository will be utilized for performance management, as-if scenarios when changes are suggested, and other agency reporting. Our expectation is the data repository utilized for business intelligence and reporting will be refreshed nightly. Current: Currently, there is no capability to record conversations with customers within our current legacy systems, forcing staff to create manual logs of interactions with customers. Case workers keep a Word file on each of their customers and have to open that file and record conversations with customers into that file. These manual logs are kept on a shared drive at that regional or local office as opposed to having this ability integrated into the system and visible state wide. Future: Staff will have the ability to record notes and conversations they have with their customers as a part of the case management. Emails sent by the customer can be attached to the case and an entry automatically added to allow staff to add narrative based on that email. If Version 5.0 Page 185
a customer calls, the telephony system will automatically enter a log entry of that phone call and date and time of the call, staff will have the ability to add to that entry to provide more details. The system should be flexible enough to allow SRS to record conversations between a CSR and a customer which can also be stored within the system. The success of this project depends on each area (people, process, and technology) working together in a integrated, cohesive manner and the support of the SRS Management Team. In order to transform the department to a truly customer centered business model will require changes to processes and organization as well as the technology. Prior attempts made by the department have not been successful because the technical supports needed for integrated service delivery were not available. Likewise, in the process of moving forward implementing new technical systems will, by themselves, be insufficient. It is critical that the agency move forward on all three axis and restructure processes and organizational structures as well to produce the business model required to service SRS customers in the future. Technology services in SRS have, admittedly, not been able to adequately keep pace with the programmatic needs of the organization with the current resources, but with the support of the agency, this modernization project will put SRS/EES systems at the forefront of Social Services delivery. SRS recognizes that each of the three operational areas wants to become more efficient, and has attempted at some level to become so. Executive management at SRS are committed to providing the leadership, organization, and resources that allow people, processes, and technology to work together to provide effective services to all Kansans, in the same way, every time they are needed.
Scenario 1: Sally Smith loses her job and is not eligible to receive unemployment insurance. With the loss of her job, she loses medical insurance coverage for her and her family and it is getting increasingly difficult for her to feed her children. 1. Sally goes to her public library to look for some type of assistance on one of their local computers. 2. A staff member from the library asks Sally if she needs any assistance. 3. Sally asks the library staff member if they know who she might contact for some assistance with getting her children medical coverage as well as assistance to get her children food. 4. The library staff member had been updated previously from SRS communications about the ability to screen for eligibility as well as look for other types of assistance on the SRS website and provides that address to the customer. 5. The customer goes into the SRS Customer Portal and follows the online instructions on how to fill out the screening information to see if she might qualify for any benefits. This can all Version 5.0 Page 186
6.
7. 8.
9.
be completed anonymously, or the customer can choose to create a unique signon to the SRS Customer Portal. The customer goes through the very simple screening process and finds out that she and her children might be eligible for Medical coverage, TANF, and Food Assistance so she has decided she would like to go ahead and apply for these benefits. The customer is also provided a list of services within her area that might also be of assistance, such as: the local food bank, the department of Commerce to assist her with finding a new job, WIC, as well as others. The customer now creates her unique user ID, password, and completes the four questions asked as a part of the authentication process to be used if she forgets her password. The customer fills out the application and utilizes the online assistance provided by some of the fields on the screen by clicking on the link beside that field to get a better idea of what she is to fill out in that specific field. The customer comes to a question she is still not clear how to answer, so she starts an online chat (this customer is filling out her application during normal business hours) with one of the SRS CSRs to get better clarification. She is able to resolve her issue and go right back to filling out her application. Option 2: The customers calls the SRS office and talks with a CSR who is able to see exactly where she is in her application and that CSR walks the customer through the part of the application that customer is having difficulties with.
10. The customer completes her application and sends it for processing. She indicated on her application that she would like to be notified via text message if she needs to check the SRS Customer Portal for any updated information, with her second preference as a phone call. She acknowledges that all the information she entered is valid and true and types in her name for our electronic signature requirements. 11. The system provides her with information about her application number, what documentation the agency will need and when they will need it before they are able to determine if she is qualified to receive benefits, provides her with information about the closest place she can go to send her documents electronically to SRS for faster processing, and then provides her with an approximate date and time of when she can expect to hear back from us. 12. Since this customer is applying for TANF, she is required to complete an interview. The system asks her for her availability and automatically schedules her interview by cross referencing her schedule with the SRS staff schedule. 13. The system starts processing the application. Since she and her children are not known to the system, the system automatically adds her and her children to the client index and assigns them a unique customer ID number. 14. If desired, the system assigns a case worker to that case this must be flexible, we may not want to assign a certain case worker to all cases. Version 5.0 Page 187
15. The system automatically registers the case and starts the eligibility process. The system realizes that all necessary documentation has not been received and puts that case on hold for 10 days before a message is sent to the customer notifying them we have not received their information and cannot process their application until that is received. 16. Sally mails her documentation to the central address provided as a part of the information she received after filling out her application. 17. The central records management center opens Sallys mail which contains Sallys unique application number. The staff scan and index Sallys documents into the system which is attaching them to both the person and the case. This means the birth certificate for the children are attached to the correct child, etc. 18. As soon as all necessary documents are attached to the case, the eligibility process begins again. If any issues occur in the eligibility process, that case goes into a queue for a CSR to work. The CSR is able to look at the business rules that failed to determine what issues might have occurred with the case to resolve these issues. 19. The CSR works with the customer to resolve all issues and the eligibility process is kicked off again. 20. The customer and her children are eligible for food assistance, TANF, and Medical coverage. 21. The system generates an email and text message to Sally to let her know she is eligible, how much she will receive, and when her EBT and medical card will be sent to her. The text message alerts Sally to check her email. 22. The system automatically generates a file (or request) to the EBT contractor who sends the card to Sally. 23. The system automatically notifies the proper SRS Case Coordinator to determine how we can successfully get Sally back to work. This will include providing benefits for child care, travel and training expenses. 24. When Sally attends a community college for training, the community college provides updates via the Provider Portal to be applied directly to Sallys case file information. 25. Since Sally continues her education, she is now due for her annual review. 26. The system generates her annual review packet, texts Sally and then emails the information to Sally to fill out electronically and send back to SRS. 27. Because the documents are electronic and bar-coded, they are automatically attached to Sallys case and an alert is sent to her Case Coordinator for review.
Visually Impaired: Sam Smith is visually impaired and it is difficult for him to get to an SRS office. Sam has a computer and assistive devices at his home and has been instructed to complete an online application to apply for food assistance due to a loss of income.
Version 5.0
Page 188
1. Sams scenario is much like Sallys scenario above, but Sam is utilizing the JAWS reader to read each of the fields on each screen of the online application. Sam is able to navigate the complete application and utilize the help text when necessary. 2. Sam is not required to complete a face to face interview and can do a phone interview. The system automatically schedules a time to do a phone interview with a CSR.
Help Desk: Steve is a CSR at the Virtual Contact Center. His duties rotate between assisting customers faceto-face, via the phone, via the fax, or via email. Depending on the volumes, Steve can be reassigned throughout the day to assist in areas that have higher traffic than others.
1. This morning Steve is assigned to assist customer that are calling in for assistance. 2. Steve signs into his computer and sets his status to available; he does not speak Spanish so he is assigned to the English queue. 3. The telephony system automatically routes incoming calls based on the CSR that has been idle the longest period of time. If all CSRs are on the phone, the customer is put on hold and provided with a message to let them know approximately how long they will be waiting for the next available CSR, provides them with the opportunity to leave a message, and lets them know they can receive information online. 4. Steves phone rings and his screen pops over to information about a customer named David Dirt, providing him just a few seconds to read over his information. 5. David indicates to Steve that he is unable to complete his online application and isnt sure why. 6. Steve is able to see exactly where David is in his application process and determines David has not clicked on the I agree button at the bottom of the application, which is a required field. 7. The conversation between Steve and David is automatically entered into the system. Steve is able to enter the resolution of the call and mark the status as closed. 8. Once that call is complete, Steve is on to the next call. 9. The system tracks the time spend on the customer resolution.
Managers: Doris is the Virtual Contact Center manager for the North East Region. She has a staff of 30 Customer Service Representatives and is responsible for making sure the workload is evenly
Version 5.0
Page 189
distributed between all service channels. Doris must do quarterly feedback sessions and annual review for all of her staff.
1. Doris has a dashboard on her monitor that lets her know how many the volumes of each of her service channels: phone, email, online chat, in person, fax, mail, etc. 2. Doris has a regular schedule for each of her staff, they understand which service channel they are working on any given day. 3. If Doris sees the wait times on the phones are getting higher than normal, she looks at the volume in her other areas and determines she can take 2 CSRs out of online chat and have them help out with the phone calls. 4. Doris instant messages the 2 CSRs and tells them they will be working the phones for the remainder of the day, or until she lets them know they can change to a different service channel. 5. The 2 CSRs log into the telephony system and quickly the wait times are back to an acceptable level. 6. Doris receives daily, weekly, and monthly reports to assist her with staffing plans and performance appraisals. She utilizes these reports to determine if someone has a strength or weakness in certain areas. She utilizes these reports to set measurable outcomes for CSRs to effectively communicate expectations.
Objectives
Key objectives (i.e. business, strategy/policy, project execution, technology knowledge transfer) are presented below.
SRS is the safety net provider for services which cant be effectively or cost efficiently provided by public/private partners. SRS is obligated to provide certain services, however the agency will refer customers to other state agencies and to community partners for provision of services to the maximum extent possible. Page 190
Version 5.0
SRS will facilitate and enable service delivery through public/private partnerships. The agency will make concerted outreach efforts to not only educate the community on services offered by SRS but also to obtain knowledge of services offered by the community. The agency will provide universal access and a single point of entry for customers to obtain services, both those external and internal to the agency. SRS will transform from a program-centric model to a client-centric model which places the customer at the center of its planning, policy, program and practice efforts. This will require the agency to integrate with other state services outside of SRS. The agency approach will change from that of a programmatic eligibility determination to an approach where the client is viewed holistically across multiple programs. SRS wants a single view of service providers which links providers to multiple programs. Currently multiple provider registries exist depending on the program and the provider type. Service delivery needs to be outcome and accountability-based instead of output-based by focusing on results. The agency will need to provide and share information across SRS programs, other state agencies, contract service providers, and community based organizations. Data access must be subject to a legitimate need to know, the minimum needed for the business function, and in compliance with HIPAA and other privacy standards. Customers should have access to their case information if they are the source of the data and it does not involve sensitive or otherwise confidential information. Parents and guardians would have access to relevant information with appropriate restrictions and authority. SRS will define the common business processes (e.g., intake) that exist for programs administered by SRS based on Core Business Functions; these should be primarily defined by the Regions collectively in collaboration with the central office. Future business model must be flexible enough to accommodate Program-specific business processes (function) without sacrificing the overall goals and objectives related to common functions and standardization. Work should be done by the appropriate level of staff. Work flow should start with generalists and be assigned to specialists only when needed. For example the initial intake and triage for financial programs could be performed by generalists. Emergency contacts such as child and adult abuse and neglect calls should always be assigned to a specialist right away. The future business model will result in work efficiencies but the current SRS workforce should be preserved when possible. However, specific job descriptions will evolve and take on new characteristics. There must exist the flexibility to assign staff to new roles if necessary, e.g., reassigning current case worker/clerical staff to Contact Center duties. Page 191
Version 5.0
The existing service locations will be required at the same level in the near term although the physical appearance, atmosphere and functions performed at the location may change in the future. The future business model may require greater co-location of SRS staff with Community Based Organizations (CBOs) and other partners. The development of common terminology, taxonomy and other metadata across programs is desirable except those linked to a legitimate Program-specific business requirement. For example, the agency would need to establish a common definition of case management, case maintenance, etc. Customers may initially be unfamiliar with or lack access to technology such as the Internet. Overcoming the digital divide for customers should be accomplished through partners. The goal is to minimize the use of paper transactions and paper documentation and maximize reliance on electronic methods. The future vision requires the maximization of cross channel service integration across business functions, e.g., the capability to start a process, such as filing an application on the web and finish it on the phone. To the extent possible clients should be encouraged to start with self-service (low touch) through the web and involve SRS and other support (high touch) as needed. SRS will assist customers in achieving self-sufficiency by holding them accountable to comply with applicable rules, regulations, and laws; and by promoting customer learning of applicable life skills.
Version 5.0
Page 192