Professional Documents
Culture Documents
HW 16
HW 16
HW 16
ME 326 HW 16
Question 13-4
The CPI measures cost efficiency of the work accomplished to date. The CPI of .696 shoes that $.70 of the work planned
to date has been completed for each $1.00 actually spent. A project manager could use the CPI to see if the project is
ahead, behind, or on schedule. If the CPI is greater than 1, the project is ahead of schedule. If the CPI is less than 1, the
project is behind schedule. If the CPI is equal to 1, the project is on schedule. The CPI is the most accepted and used
index. It has been tested over time and found to be the most accurate, reliable, and stable.
Question 13-5
BAC is the budgeted cost at completion, the total budgeted cost of the baseline or project cost accounts. EAC is the
estimated cost at completion.
Exercise 13-2
EV=$600, AC=$650, PV=$560
CV=EV-AC
SV=$40
CPI=.923
CV=-$50
SV=EV-PV
CPI=EV/AC
EV
6
6
2
14
AC
6
8
3
17
PV
4
3
4
11
CV
0
-2
-1
-3
SV
-2
3
-2
-1
EV
12
12
6
30
AC
13
14
8
35
PV
12
10
8
30
CV
-1
-2
-2
-5
SV
0
2
-2
0
EV
12
12
8
3
0
3
38
AC
13
15
10
4
0
4
46
PV
12
15
8
3
0
3
41
CV
-1
-3
-2
-1
0
-1
-8
SV
0
-3
0
0
0
0
-3
EV
14
30
38
50
EV
12
15
8
6
3
6
0
50
AC
13
18
10
8
3
8
0
60
PV
12
15
8
6
6
6
0
53
CV
-1
-3
-2
-2
0
-2
0
-10
SV
0
0
0
0
-3
0
0
-3
AC
17
35
46
60
PV
11
30
41
53
SV
-1
0
-3
-3
CV
-3
-5
-8
-10
CPI
0.823529
0.857143
0.826087
0.833333
Exercise 13-5
Status Report Ending Period 1
%
Task
complete
1
50
Cumulative Totals
EV
1000
1000
AC
500
500
PV
1000
1000
CV
500
500
SV
0
0
EV
2000
2000
AC
1500
1500
PV
2000
2000
CV
500
500
SV
0
0
EV
2000
0
300
500
2800
AC
1500
0
200
500
2200
PV
2000
1600
500
1000
5100
CV
500
0
100
0
600
SV
0
-1600
-200
-500
-2300
BAC
11
30
41
53
PCIB
1.272727
1
0.926829
0.943396
EV
2000
1200
900
1000
5100
AC
1500
1000
800
1500
4800
PV
2000
2400
1000
2000
7400
CV
500
200
100
-500
300
SV
0
-1200
-100
-1000
-2300
EV
2000
2400
1500
1800
400
8100
AC
1500
2000
800
1500
400
6200
PV
2000
2400
2000
2200
400
9000
CV
500
400
700
300
0
1900
SV
0
0
-500
-400
0
-900
EV
2000
2400
2400
2000
800
9600
AC
1500
2000
2100
1800
600
8000
PV
2000
2400
2300
2400
800
9900
CV
500
400
300
200
200
1600
SV
0
0
100
-400
0
-300
AC
500
1500
2200
4800
6200
8000
PV
1000
2000
5100
7400
9000
9900
SV
0
0
-2300
-2300
-900
-300
CV
500
500
600
300
1900
1600
BAC
1000
2000
5100
7400
9000
9900
Period
1
2
3
4
5
6
EV
1000
2000
2800
5100
8100
9600
Period
1
2
3
4
5
6
SPI
CPI
PCIB
1
2
1
1
1.333333
1
0.54902 1.272727 0.54902
0.689189 1.0625 0.689189
0.9
1.306452
0.9
0.969697
1.2
0.969697
Summary Graph
12000
Labor hours
10000
8000
6000
EV
4000
AC
PV
2000
0
0
Time Periods
2.5
Index
2
1.5
CPI
SPI
0.5
0
0
Time Periods