Optimisation Process

Version 1.0

International Cellular Infrastructure Group

OPTIMISATION PROCESS

27th August 1997

System Engineering Italy Motorola Spa Trezzano Milan Abstract

Version 1.0

Page 1 Motorola Confidential Proprietary

Optimisation Process

Version 1.0

REVISION HISTORY Issu e 1.0 Date 27/08/97 Reason for Change Initial Issue. No changes

REFERENCES

Page 2 Motorola Confidential Proprietary

Optimisation Process

Version 1.0

TABLE OF CONTENTS 1. INTRODUCTION.......................................................................................................4 2. EXECUTIVE SUMMARY.........................................................................................5 3. OPTIMISATION PHILOSPHY...............................................................................6 3.1 BASIC OPTIMISATION PHILOSPHY.................................................................................................6 3.2 ADVANCED OPTIMISATION PHILOSPHY.........................................................................................6 4. OPTIMISATION METRICS.....................................................................................7 4.1 SOFTWARE OPTIMISATION TOOL..................................................................................................7 5. BASIC OPTIMISATION PRE-REQUISITES.......................................................7 5.1 PERSONEL REQUIREMENTS...........................................................................................................7 5.2 CHANGE CONTROL PROCEDURE...................................................................................................8 5.3 DRIVE TEST ROUTES...................................................................................................................8 5.4 RF DESIGN AND DATABASE PARAMETERS...................................................................................8 5.5 SWITCH TEST NUMBER................................................................................................................9 5.6 CUSTOMER FEEDBACK PROCEDURE.............................................................................................9 5.7 TIMESCALES................................................................................................................................9 6. BASIC OPTIMISATION PROCEDURE................................................................9 7. BASIC OPTIMISATION TOOLS AND SOFTWARE.......................................11 7.1 OMC.......................................................................................................................................11 7.2 TEMS........................................................................................................................................11 7.2.1 Gims....................................................................................................................11 7.3 RF PLANNING TOOL - NETPLAN...............................................................................................11 7.4 MAPINFO...................................................................................................................................11 7.5 A INTERFACE ANALYSER...........................................................................................................11 7.6 TEST MOBILES..........................................................................................................................12 8. ADVANCED OPTIMISATION PRE-REQUISITES..........................................12 8.1 SUBSCRIBERS.............................................................................................................................12 8.2 PERSONEL REQUIREMENTS.........................................................................................................12 8.3 TIMESCALES..............................................................................................................................12 9. ADVANCED OPTIMISATION PROCEDURE...................................................12 10. ADVANCED OPTIMISATION TOOLS AND SOFTWARE..........................13 10.1 EXPERT ADVISOR - INTELLIGENT OPTIMISATION TOOL............................................................13 10.1.1 Target Optimisation Solutions.........................................................................13 10.1.2 Frequency Plan Optimisation..........................................................................13 10.1.3 Topology Optimisation.....................................................................................14 10.1.4 Future Enhancements.......................................................................................14 10.2 SOT - SOFTWARE OPTIMISATION TOOL..................................................................................15 10.3 CELL ANALYSIS TOOL VER 2 (CAT2).................................................................................15 10.4 MARS - STATISTICAL DATA ANALYSIS.................................................................................15 11. TRAINING...............................................................................................................15

Page 3 Motorola Confidential Proprietary

Optimisation Process

Version 1.0

1.

INTRODUCTION

This document describes in detail the process of optimisation. The document covers the traditional methods of optimising a cellular system in the basic optimisation section. It then introduces the improvements being made to the Optimisation process with the introduction of new tools and techniques in the advanced optimisation section. The optimisation process is continually changing with the updates in technology and the tools available, some of the tools refered to in this document are extremely new and therefore at present no professional technical documentation or product literature exists within Motorola. The tools however are functional and have therfore been refered to in the document. The process refered to in this document should not be taken as the only way of Optimising a GSM system, as with all processes they are continually being improved with new tools and techniques. The basic strategy remains however in that optimisation is a process of improving the quality of a cellular network.

Page 4 Motorola Confidential Proprietary

Optimisation Process

Version 1.0

2.

EXECUTIVE SUMMARY

Optimisation can be an expensive omission from a network operators portfolio. Without optimisation the network will degrade from the commissioned state. This is because the network changes radically as the traffic on the GSM system grows, and the snap-shot optimisation will not keep pace with these changes. Without optimisation the system will suffer poor call quality, many dropped calls due to interference and inaccurate parameters resulting in poor handover performance. The return on investment will be reduced as less subscribers can use the cell. The potential for losing subscribers to another network (churn) is increased due to subscriber dissatisfaction as a result of their subjective observation of network quality. Implementing an optimisation cycle impacts the total cost of ownership of the GSM system and is often a hidden cost. Optimisation requires dedicated resource to tune the network as the traffic on the system grows and to ensure that particular test routes operate efficiently, not to the detriment of the rest of the cell coverage area. The flowchart shown in figure 2.1 summarizes the basic optimisation process. By constructing an understanding of the drive-test process cycle and applying radically new ideas it has been possible to provide dynamic and potentially automatic optimisation at an unparalleled rate (cells/day) with improved accuracy, without the requirement for drive testing. The solution takes advantage of the Motorola (M-Cell) intelligent base-site architecture and routes optimisation information to either the OMC-R location or locally to a BSC-based information collection system. By collating this information centrally and using cellular database information, such as cell position, network frequency plan and coverage areas, it is possible to provide comprehensive optimisation suggestions. By deploying Intelligent Optimisation solutions, network operators can undertake optimisation based on traffic load, using actual subscriber call information to provide optimisation information. The flowchart in figure 2.2 summarizes the the advanced optimisation process.

Page 5 Motorola Confidential Proprietary

Optimisation Process

Version 1.0

3.

OPTIMISATION PHILOSPHY

Setting the parameters that control mobility have equal importance to the frequency plan. In GSM there are a series of parameters that control mobility. Tuning these parameters for improved GSM operations, in terms of maximising calls carried, improved handover performance and increased call success rate, is termed Optimisation. The aim of optimisation is to maximise the Quality of Service of the GSM network. In order to do this you need to measure the QOS, compare the measured value with the desired value, and then take steps to correct the causes of any deviations from the desired value. 3.1 Basic Optimisation Philosphy

It is typical that during optimisation the choice of cell frequency, the neighbour list and any margins/timers will be examined and optimised for improved performance. Optimisation is traditionally undertaken immediately after the commissioning stage, or after a new frequency plan in a deployed network. Several teams of field personnel drive around each site making a number of calls,concentrating on testing the handover between each cell. Each call is investigated and any potential problems resolved by classical fault-reasoning/resolution methods. This methodology, termed drivetesting is used by most network operators as a tried and tested way to improve their network. Optimisation is divided into the following criteria when tuning a cell: -frequency plan -topology (neighbours) -cell dynamics (handover timers and margins) -real-estate (antenna tilts etc.) Only Basic optimisation can be done in the network, if the network does not have a substantial amount of active subscribers. For statistical data to be used as in the advanced optimisation process, the network must be carrying a signifigant amount of traffic 3.2 Advanced Optimisation Philosphy

Before optimisation is started the use of the advanced toolset in the RF design process should reduce the amount of optimisation required, this will be done by simulating the network, prior to intergration or the enhancement of the network, in Handsim. The network will be set up to perform optimumly as per the simulation. As the network grows and more information is feed back into the tools the better the accuracy of the simulation Motorola has developed advanced technology and a new series of GSM features that supersede the current drive-testing methodology. By constructing an understanding of the drive-test process cycle and applying radically new ideas it has been possible to provide dynamic and potentially automatic optimisation at an unparalleled rate (cells/day) with improved accuracy, without the requirement for drive testing. Motorola continues to develop the processes of intelligent optimisation, the intelligent optimisation tool is a product available now as a stand alone tool and has been put into the Motorola Roadmap to become fully intergrated into the network as an optional feature in the future.

Page 6 Motorola Confidential Proprietary

Optimisation Process

Version 1.0

4.

OPTIMISATION METRICS

The quality of the network can be measured through the statistics generated from the network, these are available through the OMC (Operations and Maintenance Center) These statistics are used to generate the key metrics. These metrics will then be measured against the required metrics as agreed between the operator and Motorola. Motorola believes this is the most effective way of monitoring the performance of the network as the metrics are derived from all of the users of the network. Drive test statistics, although a useful indication of network quality, do not really emulate the typical user of a mobile network, as they are only a very small sample of the total calls on the network, thus the statistics obtained from the whole network through the OMC are a more acurate assesment of the quality of the network. The following metrics require an agreed target between the operator and Motorola to measure the performance of the network. Dropped Call Rate Handover Sucess Rate Overall RF Loss Rate - TCH & SDCCH RF loss combined TCH Assignment Sucess Rate Call Success rate TCH Blocking Rate

If the agreed metric cannot be reached due to circumstances outside the control of Motorola, this will be brought to the attention of the operator and with agreement removed with respect to the overall acceptance metrics as agreed beteen Motorola and the operator. The typical targets set between operator and Motorola are 4.1 Dropped call Rate Handover Sucess RateRF Loss Rate TCH Assignment Rate Call Sucess Rate TCH Blocking Rate Software Optimisation Tool Less than 2% > than 95% Less than 3% > than 95% > than 95% To the RF design criteria (Usually 2%)

Motorola have developed a software tool for analysing the performance of the network (SOT - Software Optimisation Tool). Motorola use this tool to provide the optimisation metrics required to measure the performance of the network. 5. 5.1 BASIC OPTIMISATION PRE-REQUISITES Personel Requirements

The intention here is to show the engineers required in the optimisation process and not the amount of engineers. The amount of engineers will depend on the size of the network, the amount of area to be covered and the roll out schedule.

Page 7 Motorola Confidential Proprietary

Optimisation Process

Version 1.0

Once the above information is known a more precise proposal can be done detailing specific numbers of people required. The engineers required in the optimiation process is as follows Type of Engineer Functions

OMC Engineers Statistical feedback, Network availability, Database Changes. Drive Test Engineers Drive Testing, Performance evaluation, Antennae and database Changes. Performance Engineer OMC Statistical Analysis, Quality Metric figures. BSS Mtce Engineer Fault Identification and Clearance Antennae Riggers Antennae Azimuth and downtilt changes Optimisation Control Management responsibilities of all staff, Presentation of Quality Metrics, Technical Guidance to Engineers, Change control Management. 5.2 Change Control Procedure

A procedure to manage changes within the network is required to maintain the integrity and quality of the network. The procedure ensures all changes required to improve the quality of the network are valid and that precautions against failure of the change have been considered. This procedure below is the change control procedure and ensures changes on the network have been fully evaluated before implementation and that each change has a test plan and a back plan in case of failure.. 5.3 Drive Test Routes

Before drive testing is started drive test route need to be agreed with the operator. These routes should cover the following points before agreement is reached. All sites and sectors should be tested within the drive test routes at least once. All major roads and highways should be tested at least twice within the agreed routes. All cells should be tested for handout and handin within the routes if possible. The routes should be approxiamately 2 - 3 hours in duration. This is required to manage the data collected. Routes of major importance should be identified prior to starting and should be driven first. i.e Airports to the city center 5.4 RF Design and Database Parameters

Beforre Optimisation can begin the RF design and database parameters will be required. This is normally presented in spreadsheets from the RF planning and Datagen tools. This information is required to help the drive test engineers to identify possible sources of interference. The information is also used to evaluate possible changes to improve the quality of service.

Page 8 Motorola Confidential Proprietary

Optimisation Process

Version 1.0

5.5

Switch Test Number

To aid in the optimisaqtion of the network a test number is required within the MSC. This is required for the drive test teams to access from the test mobiles in the car, a test number in the MSC is preferred as this removes any contact with the land system, so in the event of any dropped or unavailable calls they will all be in the mobile network . 5.6 Customer Feedback Procedure

A procedure is required to feed back customer information on the performance and coverage of the network. The recieved information is used to target areas of optimisation and to verify coverage against the RF design. The information feed back is also used in the growth of the network by identifying were subscribers are using there mobiles. The process of feeding information back is an internal process for each operator, Motorola however have closely worked with customer care departments to assist in providing information as to the coverage and quality of the network. The format of providing information is usually graphically based around the Mapinfo GIS software, this provides coverage maps from the RF planning tool and live data gathered from drive test data. This support can be provided to any future customers. 5.7 Timescales

The optimisation process never comes to an end within a network, the process usually evolves into the performance engineering department as the network evolves. The rate of growth in most cellular networks means the network continues to expand with new sites or more capacity with different RF design techniques, this will always mean that optimisation will be required to maintain and improve the quality of the network. The initial optimisation of a system is somewhat variable depending on many factors i.e amount of sites, area to be optimised, road traffic density e.t.c. However as an indication until the precise information is known on the network it takes approxiamately 2-4 weeks for one drive test team to optimise a BSC, a BSC usually consists of about 14 - 18 sites at with present software load. If a faster optimisation process is required more engineers will be required, another team would see a reduction of 10 days in the process. 6. BASIC OPTIMISATION PROCEDURE

The optimisation process starts immediatly the network is brought into operational service or an enhancement takes place on the network. During times of little change to the network Performance Engineering monitor the quality of the network and will seek assistance from Optimisation Engineers if the quality of the network begins to fall. The procedure below is the basic method for Optimising a system and can be modified to each operator to maximise results. 1. Before Optimisation starts all of the pre-requisites must have been done or be in place. There must be a change control procedure in place with the operator that Motorola are familiar with, the RF design and Database parameters must be presented to the Optimisation control manager. All drive test teams must have test
Page 9 Motorola Confidential Proprietary

Optimisation Process

Version 1.0

mobiles and SIM cards provided by the operator. Note - The Optimisation control personel are usually situated with the OMC personel for maximum effieciency as OMC and Optimisation control are continually passing information between each other. 2. 3. The drive test routes must be agreed with the operator and a priority set on the routes for testing. The drive test teams make test calls on the network of 2 minute duration with a 15 second break between calls to the MSC test number with the Test Mobile equipment (TEMS) and all data is logged to the computer, location information is also taken using a GPS reciever to provide location information. The drive test routes are usually 3 - 4 hours in duration so that the data collected can be managed. During or after completion of the drive test route analysis of the data collected is done to find areas of dropped or noisy calls. This can either be done on the RF planning tool or using the GIMS software in the field The results of the drive test, including analysis is passed to Optimisation Control for performance logging of the route.

4. 5.

6. 7.

Should the analysis of the route indicate problems of either dropped or noisy calls ,with the aid of the RF design and Database parameters an assesment is made to identify the possible source of interference causing the noisy or dropped call. If a call is dropped and no interference is present a retest is made in the same area, if the scenario of the dropped call can be repeated, information of the problem cell should be obtained, this will then be escalated to Optimisation control to seek assistance from the BSS maintenance engineers to investigate the cell dropping calls. Note - To assist in confirming possible sources of interference there may be a requirement to remove the suspected interfering channel. This would be done via the optimisation control engineersf. The suspected interfering carrier would be removed temporarily from service and test calls made again in the problem area, this would show if the interference had been removed. The process for temporarily removing carriers would have to be agreed with the operator, this usually varies as to the importance of the cell as to what time of day it can be taken out of service. 8. After conformation as to what is causing the problem with the drive test route, the drive test engineer will attempt to find a solution to the problem. This can be one of a number of possibilities i.e Power Change to BTS, Frequency Plan change, Neighbor addition required e.t.c. Note - In the case of a frequency plan problem, this is usually escalated through Optimisation Control to the RF design engineer to find a solution to the problem. The RF designer and Optimiser for an area are usually the same engineer in Motorola, this has continually proven to be the most efficient method of improving the quality of the network with respect to problems with the frequency plan of the network. 9. Once a possible solution to the problem has been found it may be possible in some circumstances to immediatly attempt the solution via the OMC, this usually relates to minor database changes and adding neighbors. The solution is
Page 10 Motorola Confidential Proprietary

Optimisation Process

Version 1.0

implemented and proven immediately. If the problem is rectified the change remains in place and a change request is raised for the solution for the purpose of keeping records of all changes in the network. If the solution requires a major database change or antennae work a change request must be raised via the Optimisation Control Engineers. After the solution is implemented a retest of the problem area is carried out to confirm the problem has been solved. 10. In the event of the problem not being solved alternative solutions may be attempted, this process continues until it becomes immpossible to find a solution. At this point the problem is discussed with the operator as to the reasons that the problem cannot be solved for example the solution may require a new cell to be built, clearly this is beyond the scope of optimisation. If the operator is in agreement this particular problem will be removed from the drive tests until such time a solution is implemented. 11. Steps 3 to 10 are repeated throughout the system until such time that all routes meet the required metrics or no further improvement can be made due to circumstances outside the control of Motorola. 7. 7.1 BASIC OPTIMISATION TOOLS AND SOFTWARE OMC

The OMC is an integral part of a GSM system, its relationship to the Optimisation process is to provide statistics for the quality metrics and information on the status of the network. 7.2 Tems Tems is the drive test mobile and software from Erisoft. The kit consists of a laptop P.C, an Ericsson GH688 test mobile and a GPS reciever for positioning information. 7.2.1 Gims Gims is the graphical display software associated with Tems, it displays the drive test routes graphically on a map of the drive test area. It is especally good at providing information to customer care and marketting departments. 7.3 RF Planning Tool - Netplan

An RF planning tool is required in the Optimisation Process for displaying drive test routes for analysis, modifications to the frequency plan and antennae azimuths and downtilt changes. Motorolas RF planning tool is Netplan. 7.4 Mapinfo

Mapinfo is a GIS software tool, it is used to display drive test data for analysis and to produce Optimisation reports in a clear and easy manner. 7.5 A interface Analyser

An A interface analyser i.e Siemens K1103 tester, is required to analyse the A interface for possible messaging problems. This tool is required to prove areas of

Page 11 Motorola Confidential Proprietary

Optimisation Process

Version 1.0

dropped calls when there are no interference problems. It can also be used to identify faulty handover processes between the BSS and MSC. 7.6 Test Mobiles

Test mobiles are an invaluable source of information, all field engineers should be equipped with a test mobile to identify problem areas. The test mobile should be capable of giving the recieved signal level, RXQual value, Cell I.D and six neighbors with rxlevels. 8. ADVANCED OPTIMISATION PRE-REQUISITES

The advanced optimisation toolset developed by Motorola will be required to undertake the advanced optimisation procedure in the network. 8.1 Subscribers

To gather meaningful data for the advanced optimisation tools the network should have a substantial amount of traffic being generated by subscribers on the network. 8.2 Personel Requirements

The type of engineers required will remain the same as the requirements in the basic optimisation pre-requisites. There will however be a requirement for extra performance engineers to analyse data gathered from the intelligent optimisation tool,the Call Trace Product Tool and the Cell Analysis Tool . The requirement for drive test engineers will still be valid for verification purposes, but a there should be a signifigant reduction in the amount of drive test engineers required. The reduction will be based on the amount of advanced tools available in the network and the timescales involved. 8.3 Timescales

As there is typically no requirement for drive testing in the advanced optimisation process, the time taken to optimise the network is reduced signifigantly. This reduction will depend on the amount of advanced tools available, the size of the network and the roll out plans of the network. As a comparison with basic optimisation for a BSC it should take approxiamately one week to optimise as opposed to 3 - 4 weeks for the basic optimisation process. 9. ADVANCED OPTIMISATION PROCEDURE

The advanced optimization procedure for a network is as follows 1. The Motorola advanced OMC tools should be loaded onto all OMCs 2. The analysis of these tools will identify the worst performing BSCs in the network. 3. Intelligent Optimization is then carried out on the worst performing BSCs first.

Page 12 Motorola Confidential Proprietary

Optimisation Process

Version 1.0

4. The intelligent optimization tool is usually deployed at the BSC site which serves the area being optimized. This is required to extract the data via the A interface links to each BTS. 5. Measurement report data is collected via remote nodes at the cell sites and sent to the Intelligent Optimisation Tool over the A interface links. 6. The Intelligent Optimisation tool analyses the data and can identify problem areas in the network. 7. If problem areas are identified then changes will be required to the network to improve the problem areas and thereby improve the quality of the network. 8. Steps 3 to 7 are then repeated until the quality of the network reaches the objectives set in the optimisation metrics agreed between Motorola and the operator. 10. 10.1 ADVANCED OPTIMISATION TOOLS AND SOFTWARE Expert Advisor - Intelligent Optimisation Tool

Intelligent Optimisation is an optional product for the OMC Expert Advisor or can be a stand alone product. Where deployed, it will: Automatically identify optimisation issues to determine which cells require optimisation. Provide the necessary user interface to set up the scope of the optimisation Direct the operation of the Intelligent Optimisation system i.e. Plan and schedule data collection and analysis Provide Optimisation recommendations to the Operator for final analysis Provide C/I and C/A Matrices in a format for import to a planning tool Provide accurate Performance statistics before and after the optimisation to monitor the improvement in the network. Provide facilities to start and stop the IOS processes Provide facilities to view and change optimisation change requests Link to the Expert Advisor on-line help system. 10.1.1 Target Optimisation Solutions The following is a list of the solutions that are candidates for the first release of the product. 10.1.2 Frequency Plan Optimisation The frequency plan is the primary cause of RF sub-system problems, since a nonoptimal plan will produce many coverage "holes" and significant co- and adjacent channel interference. Providing an optimal frequency plan will facilitate improved network performance. The mechanism by which the frequency plan will be updated (iterated) is via the generation of a Carrier-to-Interference channel (C/I) and a Carrier-to-Adjacent (C/A) channel matrix. This is a prioritised list of each source cells interfering neighbours. A
Page 13 Motorola Confidential Proprietary

Optimisation Process

Version 1.0

new frequency plan is generated by processing this C/I and C/A matrix in conjunction with spectral availability. For completeness since the generation of the iterated frequency plan requires subscriber measurement, for the first plan the system will use the propagation prediction-based frequency plan as the base-line and then iterate to converge on an optimal and "best compromise" solution. The iterated solution will encompass the subscriber usage within its data. This means that the frequency plan will be statistically valid for the majority of the cells users. This is in contrast with the traditional Drive Test method where routes are predetermined as representative without the benefit of correlation with subscriber usage patterns. 10.1.3 Topology Optimisation Once the frequency plan is updated the next influence on RF sub-system performance is the network topology. The topology encompasses the relationship that the source cell has with its surrounding neighbour cells. Clearly, there are three possible conditions that can exist for optimisation of topology: i. No problems exist. ii. The topology is incomplete, i.e. a neighbouring cell is missing from the topology and if entered may reduce dropped calls since an appropriate handover will be undertaken. iii. The topology is "over-complete", i.e. the topology has redundant elements where handovers are not undertaken. This is not a significant issue if the cell is not heavily utilised since the processing associated with each neighbour is not significant. However, in a busy cell with many neighbours, the redundant link could be utilised by a true neighbour. The topology is modified in many different ways, but in all cases the topology modifications are directed to increase subscriber call satisfaction by reducing the poor call quality. In GSM, the mobile phone is the source of neighbour information since up to 6 neighbour cells are reported. Over a period of time, all the frequencies can be scanned. The neighbour information is then processed to add the missing neighbours and remove the redundant links. The process of scanning frequencies is aided by the "Test Neighbour" feature. It is envisaged that test neighbours will be incorporated into the topology to aid both frequency planning and topology optimisation. In addition, since new neighbours are only identified by their BCCH ARFCN / BSIC combination, propagation information is required to identify the neighbour GSM Cell Identity for the neighbour list. 10.1.4 Future Enhancements In addition to the above solutions Motorola is investigating the addition the following solutions to the Intelligent Optimisation Tool: Location Area Code (LAC) Optimisation Cell Dynamic Optimisation

Page 14 Motorola Confidential Proprietary

Optimisation Process

Version 1.0

10.2

SOT - Software Optimisation Tool

The SOT tool is a software package that analyses BSS statistical data stored on the OMC. The tool provides statistical metrics for measuring system performance as well as information on poorly performing cells. 10.3 Cell Analysis Tool Ver 2 (CAT2)

The CAT2 tool is a software package that analyses BSS statistical data stored on the OMC. The tool profiles the statistics against preset profiles input to the tool for each cell. This process is known as footprinting a cell. Should the analysis of the statistics show a deviation outside the footprint set in CAT2 an alarm is raised on the OMC for the attention of the OMC engineer. 10.4 MARS - Statistical Data Analysis

The MARS tool is a software package that runs on a unix system. The tool is used to analyse long term data, upto 6 months worth of data can be analysed. The tool can be used to provide growth plan information for the operator. The tool can also aid in the fault identification process by analysis statistics recently gathered by the tool. The tool can analyse all statistics available in the BSS. 11. TRAINING

Motorola provide extensive training on its GSM infrastructure, this is done through the Motorola Technical Training department. As well as Motorola technical training, Motorola have a certification process for System Engineers involved in the Optimisation of the network. This certification consists of Motorola Technical training and on the job training with local System Engineers who support the operator. The training will cover all tools and techniques involved in the optimisation of the network, full certification of the operators engineers will only be given when they are capable of performing all tasks involved in the optimisation process.

Page 15 Motorola Confidential Proprietary