5. SLUICE 5.

1 Repairs and Reconstruction

U/S head wall has to be shifted for 3 Nos. sluices (13th mile Sluice, 12th mile Sluice and 11th mile Sluice) where U/S filling is proposed and D/S head wall has to be shifted for 3 Nos. sluices (Adaikalamoddai Sluice, Sinnaudaippu Sluice, Periyaudaippu Sluice) where D/S filling is proposed. Kuruvil Sluice has to be reconstructed as there was a piping observed through the barrel in 2004 and temporarily repaired. As this is an ancient tank and the sluice are made of dressed stone masonry it is recommended to maintain the same type for repairs & reconstruction. New sluice gates and emergency gates have to be installed for all 7 sluices and also 7 Nos. trash tracks have to be installed. 5.2 Design of Sluice (Kuruvil) Data FSL 44 MSL HFL 46.4 MSL BTL 52 MSL Sluice type Concrete Head wall Location At Kuruvil (7+075 m) Sill Level 35.88 MSL

48

7. RECOMMENDATION 1. Embankment Even though the capacity of this tank is 31,500 Ac.ft and length of the bund is 7+125 meter, FSD is only 11.56 ft. For 100 years flood, HFL From Method I From Method II 46.4 44.7 BTL 54 52.3 Free Board 7.6 7.6 Difference 4.5 2.8

Considering the availability of funds from NEIAP, it is proposed to have the BTL at 51.5 MSL as stage I and it is proposed to have the BTL at 54 MSL as stage II and funds has to seek from donors. D/S filling is recommended from 3+000 to 7+125 as the Rip-Rap work has been completed almost up to 49.5 ft recently. From 0+000 to 3+000m U/S filling has to be done.

2. Road The existing Jubilee road which is little beyond the toe from 3+000 to 7+125 (Where D/S filling is proposed) has to be repaired. (Filling pothole, gravelling, repairs to drainage crossing and side drainage have to be attended) There is no road on the bund top at present, but it is very necessary to have a road on bund top because the length of the bund is 7.125 km and there are 7 Nos. sluices.

92

8. CONCLUSION Design Command area for Maha extent 30,000 Ac of paddy. Command area for Yala extent 6,000 Ac of paddy Categorized its hazard potential as Low (100 years Flood is taken for Analysis) High Flood Level (HFL) 46.40 feet MSL Bund Top Level (BTL) 54.00 feet MSL Bund Top Width (BTW) 10 feet Pro-rata Cost is 8236/= per Ha

Proposal Due to the availability of funds, it is decided to have the BTL 51.50 feet MSL as Stage I Repairs to Jubilee road Repairs to six nos. of Sluices. Reconstruct one no. of Sluice.

93