TASK RISK ASSESSMENT

1.

- Full Body Harness with double absorbing lanyard

- Full Body Harness with double absorbing lanyard

- Improper lanyard anchorage. - Improper wearing of fall protection - material fall hazard

- Personal injury

- Ensure lanyard is hook properly, Hook to rigid structure - Check Harness from cuts, wear and tear - Harness worn properly and adjusted. - Remove defective harnesses out of service

M - Conduct awareness -Proper wearing harness and correct way how to use.

-Permit Reciever - Unit Incharge -Job Supervisor

2.

Working on Scaffold Platform

- Working tools - mobile scaffold

- Unstable Scaffold - work at heights - Lateral Movements - Slip, trip &fall

- Personal Injury - Material/tool fall - Damage to plant and equipment

- Use only scaffolding with green tag - Wear Fall protection - Lock caster wheels prior to work on the platform - mobile scaffold to follow 1:4 base height ratio

- 3rd party inspection - Conduct awareness -proper of wearing harness in correct way to use.

Permit Reciever - Unit Incharge -Job Supervisor -

3.

Working on existing equipment platform / access way

- Tools and materials

- Ladder

- Missing guardrail - Removing of Guardrails deliberately due to required space requirements. - Stockpiled tools and other materials along walk way/access - Floor Openings -material fall hazard - Defective ladder - Improper use of ladders - Throwing of materials and tools

- Personal injury

- Install temporary guardrails do not leave openings. - Ensure approval when removing existing/permanent structure or guardrails. - Avoid storing unnecessary materials on the access - Ensure toe boards installed - Use proper lifting material basket - Inspect ladder before use

- Never use nylon rope or barricade tape as protection on open edge. - When ladder is required to be vertical proper lashing and clamp must be required.

Permit Reciever - Unit Incharge -Job Supervisor -

TASK RISK ASSESSMENT

- Observed 3 point contact while using ladder - Install ladder 4:1 ratio

4.

Working on top of Tanks, Columns, vessels and others

- Full Body Harness

- Fall hazard - roof opening

- Personal injury/fatality

- Wear full body harness - Install temporary covering on floor openings. - If barricade is not ideal, provide life line connected to rigid structure at both end.

- Close Supervision - Training for fall protection

Permit Reciever - Unit Incharge -Job Supervisor -

5.

Working at flare area

- Man basket

- Basket failure ( welding on lifting joints) - High wind - Acrophobia (fear of Height)

- Personal injury - Basket swaying - Fear lead to Personal anxiety

- Scaffolding platform

- Incomplete guardrails

- Personal fall

- DPT test on lifting eyes. - Do not operate if the wind speed is more than 15 miles per hour. - Monitor wind speed - Do not allow/force person to work at high elevation if having acrophobia. - communication between ground/crane operator and man basket personnel - Wear Fall protection - Install auxiliary sling for lifeline purpose.

- No work at nights - Basket and rigging to be inspected by competent person - Follow TRA of Flare tip replacement activities

-Permit Reciever - Unit Incharge -Job Supervisor -