PROJECT REPORT FOR GRANITE TILING PLANT

1. 2.

Market Position:- There is good market for granite tiles in Euope,USA,Middle East &
Other countries.

Present Granite tile manufacturers in India:- There are few manufacturers in India
as below a. P.R.P.Granites b. ARO Granites c. Tab India d. SVG Exports e. Dacss Granites f. God Granites g. BVL Granites h. Ankith Granites i. CNR Granites And other few samll manufacturers.

3.

Details of processings:- Mainly there are 3 steps of process


a. Block Dressing b. Cutting

c.

Processing

-1-

4.

Flow chart of processing:Block Dressing

Cutting Edge Cutting Calibrating Polishing Square cutting


Beweling & Chamfring

Inspection Packing & Crating Container Loading Dispatch

-2-

5.

Pant Layout:-

Hand written sketch will be scanned & Send

6.

Details of Plant & Machinery:- Below the following machines required for the Plant.
a. Block Dressing Machine(Wiresaw) b.56 discs Block Cutter c. Edge Trimming Machine d. Calibrating Machine(4 or 5 Heads) e. Polishing machine(16 or 18 Heads) f. Multi Disc Cross Cutting Machine(11 or 12 heads) g. Beweling & Chamfering Machine(4+8 Heads) h. Drying & Buffing Machine with inspection table i. Gantry Crane 60 Tons j. EOT Cranes 5 Tons k. Water treatment Plant l. Water Storage Steel Tanks m. Fork Lift 2.5 Ton n. Compressor (20 HP) o. Utilities ( Pumps & Others) -31 No. 2Nos 1 No. 1 No. 1 No. 1 No. 1 No. 1 No. 1 No. 2 No 1 No. 2 Nos 1 No. 1 No. 1 Set

7.

Production Capacity of the Plant:a. Cutting Capacity: With 2 Nos 56 disc Block Cutters can cut 600 to 700 sq. mtrs. Per
day( its depending upon the block size.

Total cutting in sq.mtrs per month = 600 sq,mtrs x 25 days = 15000 sq.mtrs.
b.

Processing Capacity : With above mentioned processing machines


mtrs can process per shift. Average 450 x 25 days = 30000 sq.mtrs. per month

400 to 500 sq.

8. 9.

Requirement of Power:- For the above mentioned machineries required Power


500 to 600 KVA

Water Requirment:- 3500 to 4500 Ltrs. Per Minute(Its recycled water) 10. Labours:- 80 to 100 people including operators, helpers & Casual Labours. 11. Staff:- 10 to 15 people including supervisary staff & Plant manager. 12. Cost of Production:a. b. c. d. e. f. g. h. i. j.

Raw Material: Cutting Cost: Processiong: Packing & Forwarding Cost:


90 cft

Rs.500 to 700 Per Sq.Mtrs. - 600/sq.mtr Rs.60 to 70 Per Sq.Mtrs. Rs.50 to 60 per Sq.Mtrs. Rs.70 to 80 per Sq,Mtrs. Rs.60 to 70 Per Sq.Mtrs. Rs.50 to 65 Per Sq.Mtrs. Rs.15 to 20 Per Sq.Mtrs. Rs.7 to 10 Per Sq.Mtrs. Rs.40 to 50 Per Sq.Mtrs. Rs.10 to 15 Per Sq.Mtrs. - 65/sq.mtr 120 - 60/sq.mtr 100 75/sq.mtr 120 65/sq.mtr 65/sq.mtr 15/sq.mtr 50 8/sq.mtr 15 45/sq.mtr 12/sq.mtr

Power: Labour: Over Heads: Maintenance: Depreciation: Others: Total Cost per Sq.Mtrs.

= 1075/-sq.mtr.

-413.

Cost Economics:- Generally the selling price of the tiles is Rs.1300 to 1600 per Sq.Mtrs. Its
depending upon the country, colours & type of the buyer. Average selling price will be Rs,1400 per s.mtrs. Profit = Rs.1400 Rs.1075 = Rs.375/Sq.Mtrs.

14.

Turn Over:- Usually in one container 8000 to 8500 sq,feet will be stuffing. One container
cost will be Rs.10 to 11 Lakhs. For the above mentioned set up can be produced 15 containers per month. Rs.10Lakhs x 15 containers = RS.1.5 Crores. The Average Annual Turnover = 1.5Cr. x 12 Months = Rs.18

Crores.

15.

Total Capital Investment- For the above mentioned set up if you are used cutting & Processing machines with all new utilities the approximate cost will be Rs.10 Crores.
If you are going for brand new machines cost will be 15 to 16 crores.(Its depending upon make)

16.

Raw Material:day.

For the above mentioned set up required 15 to 20 cubic mtrs. Per

For one month around 500 cubic mtr. Material is required to run the plant with full production capacity.

NOTE: All the above informations are given as per my experience & knowledge. If any further information required please contact.