Professional Documents
Culture Documents
Functional Safety
Functional Safety
Functional Safety
A Case Study: Updating a Refinery Boiler Controls utilizing ISA 84 Standard for Safety Instrumented Systems
Presenters
Alan Sharkey Audubon Chuck Laughter Audubon Matt Hufford Wilson Mohr Steve Papp - Wilson Mohr
Agenda Functional Safety Life Cycle Overview Case Study of Boiler in Refinery
HAZOP LOPA PFD/SIL Determination SRS Development SIS Implementation Phase Operation & Maintenance Phase
Q&A
Permission granted for ISA Houston Section Website
HAZID/HAZOP
Hazard ID and Risk Assessment
Step 1
HAZID/HAZOP
Objectives
Identify Hazards and Hazardous events of the process and associated equipment
Task Required
For each hazard identified , determine the consequence /severity level, the deviation, the initiating cause(s), and the safeguards(s) Note: Safe design should be developed as far as reasonably practical before reliance is placed on the SIS to reduce risk
LOPA
Objectives Identify required mechanical, operational & safety instrumented functions (SIF) protection layers for each consequence carried into LOPA For each SIF determine the associated SIL & and risk reduction target Tasks required Review hazard identification, for each hazard assign risk reduction credits Assign target PFD (SIL x) to each SIF Note: Client will most likely have own risk graph and acceptable levels of risk
Permission granted for ISA Houston Section Website
SRS
Definition of SRS: Function design requirements of the SIS Minimum Requirements SIS System architecture (sensor, logic solver & end control elements System hardware standards Spare capacity, loading & expansion Specify testing interval(s) I/O requirements I/O signal types and field interfaces System communications Equipment and field termination/marshalling cabinet design requirements Operator MOS Override requirements (HSW/KSW/Status Panel) Optional Items Preliminary SIL verification calculations
Permission granted for ISA Houston Section Website
Objectives Install and commission the SIS according to design documentation so that it is ready for final system validation. Commission and check calibration of the SIS components To integrate and test the SIS (SAT) To validate, through inspection and testing, that the installed & commissioned SIS & its associated SIFs meets in all respects the requirements as stated in the SRS.
Objectives To ensure that the functional safety of the SIS is maintained during operation and maintenance SIS documentation is maintained To control maintenance and testing activities, so that the design intent of SIS is retained over the asset life
Management of Change
Objectives To control all SIS modifications, so that safety integrity of the SIS is maintained over the asset life. To ensure that any SIS changes are properly planned, designed reviewed, approved and tested prior to implementation.
Case Study of Refinery SRU HAZOP LOPA SRS SIS Operations & Maintenance
SIS Implementation
Qualifications
Practical Considerations
Resulting Complications
- Customer Timing - Plant Control Infrastructure - Corporate Specifications - S84 vs NFPA 85 - Customer Awareness - Maintenance Restrictions
Impact on Cycle
- Concurrent Development Cycle - Vendor Restrictions - Conflicting Requirements - Needs dont match capabilities
SIS Implementation
Design Constraints for Case Study
- Customer Timing:
2 Year Turnaround Schedule
- Confecting Requirements
- Corporate Spec for S84 - Plant Spec for NFPA 85
SIS Implementation
Resulting Design for Case Study
- Redundant Processors Utilizing Independent Tasks - Shared Power & Comm Backbone - Dedicated Redundant Analog & Digital Inputs on SIS I/O - SIS & BMS Operate Totally independently - SIS Processes SIF and Controls Safety Relay Only - MFT Circuit is the Interlocking Mechanism Between the Two Systems
SIS Implementation
Resulting Design for Case Study
Low Fire Light off on Individual Burner Trains Single Block with Vent on Headers
Combustion Circuit
DCS Controlled
SIS Implementation
SIS Implementation
Questions?