Professional Documents
Culture Documents
I395 Presentation Advisory Group January 2013
I395 Presentation Advisory Group January 2013
Existing Conditions/Deficiencies
Safety and Operational Issues: poor horizontal and vertical geometry, lane continuity, etc. Entrances/Exits Ramps: undesirable left hand entrance/exit ramps Weaving: competing movements in a very short distance Access: poor access to and from I-395 Clearances: low clearance from local streets to I-395
Commitments
Roadway vertical clearance west of FEC should be a minimum of 19 feet and east of FEC a minimum of 25 feet. A minimum of 200 feet between the I-395 westbound bridge and the Adrienne Arsht Center for the Performing Arts (AACPA) will be provided. A minimum of 225 feet of column span length will be provided. The Department commits to providing a signature span design. The Department will provide aesthetics enhancements (e.g. landscaping) to help maximize the total integration of the project with the adjacent community. Reconnect NW 2nd Avenue .
Refinements to Alternative
Approved by FDOT D6 June 2012 Added additional thru lane in each direction from 2L to 3L. Eliminated most design exceptions and variations. Improved interchange at North Miami /NE 1st Aves. with I-395. Length of Aesthetic Pleasing Bridge is approximately 600 feet total length.
METROMOVER
24.0
25.3
29.6
16.5
23.4
28.5
NW 3 AVE
NW 2 AVE
FEC RR
MIAMI AVE
NE 1 AVE
20.2
Right-of-Way Plans
Total of 70 Fee Simple Parcels and 15 Permanent Easements required for project. Twenty-six parcels acquired to-date. Right-of-way funded thru FY 2015.
Bridge/Structures Design
Main Span ~ 600 ft x 2 = 1,200 FT Main Span Length was optimized to manage total project construction cost Avoid curved alignment
Based on five TAC and four PAG meetings held, the following four Designs have been recommended:
Infinity Arch Wishbone Arch Segmental Box Aesthetic Viaduct
Overall Length
Suspended span approximately 690 ft.
Challenges
Arches erected separately Complicated foundation
Overall Length
Suspended span approximately 600 ft.
Challenges
No Aesthetic Component for Main Span
Overall Length
Main Span 300 ft.
Challenges
Fabrication of tower Maintaining cables taut over time
Overall Length
Main spans approximately 300 ft.
19
Cross Section
Cross Section
21
Pier Renderings
14th St NE
22
Pier Renderings
14th St NE
23
Schedule of Milestones
Survey: Completed Soil Testing: Completed Traffic Analysis: Completed Alignment: Completed Public Involvement: On-Going Draft Preliminary Plans: Submitted November 2012 Bridge Development Report (BDR) Visual Quality Manual (VQM) Various Component Sets Final Preliminary (15%) Plans: Late February 2013 Hold Public Meeting: April 2013 Issue Draft Request For Proposal (RFP): June 2013 Complete Right of Way Acquisition: Summer 2015
24
I-395 Reconstruction
25