Professional Documents
Culture Documents
DBS3900 Site Preparation Guidelines (V200 - 01)
DBS3900 Site Preparation Guidelines (V200 - 01)
01 2008-04-30
Huawei Technologies Co., Ltd. provides customers with comprehensive technical support and service. For any assistance, please contact our local office or company headquarters.
Website: Email:
Copyright Huawei Technologies Co., Ltd. 2008. All rights reserved. No part of this document may be reproduced or transmitted in any form or by any means without prior written consent of Huawei Technologies Co., Ltd.
Notice
The information in this document is subject to change without notice. Every effort has been made in the preparation of this document to ensure accuracy of the contents, but the statements, information, and recommendations in this document do not constitute a warranty of any kind, express or implied.
Contents
Contents
About This Document.....................................................................................................................1 1 Safety Information.....................................................................................................................1-1
1.1 Safety Precautions...........................................................................................................................................1-1 1.2 Electricity Safety.............................................................................................................................................1-3 1.3 Inflammable Environment...............................................................................................................................1-5 1.4 Battery.............................................................................................................................................................1-5 1.5 Radiation.........................................................................................................................................................1-7 1.6 Working at Heights.........................................................................................................................................1-9 1.7 Mechanical Safety.........................................................................................................................................1-11 1.8 Others............................................................................................................................................................1-12
3 Power Supply Requirements of the DBS3900......................................................................3-1 4 Grounding Requirements of the DBS3900............................................................................4-1 5 Transmission Requirements of the NodeB Site...................................................................5-1 6 Preparing Auxiliary Facilities for the DBS3900 Site...........................................................6-1
6.1 Installing the Cable Rack................................................................................................................................6-2 6.1.1 Introduction to Cable Racks...................................................................................................................6-2 6.1.2 Procedure for Installing the Cable Rack.................................................................................................6-4 6.1.3 Installing the Outdoor Cable Rack.........................................................................................................6-4 6.1.4 Connecting Cable Ladders.....................................................................................................................6-7 6.1.5 Installing the Cable Trough..................................................................................................................6-13 6.1.6 Installing Accessories...........................................................................................................................6-17 6.2 Installing the Grounding Bar of the NodeB..................................................................................................6-19 Issue 01 (2008-04-30) Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd i
Contents
ii
Issue 01 (2008-04-30)
Figures
Figures
Figure 1-1 Wearing an ESD wrist strap...............................................................................................................1-5 Figure 1-2 Lifting a weight................................................................................................................................1-10 Figure 1-3 Slant angle........................................................................................................................................1-11 Figure 1-4 One meter higher than the eave........................................................................................................1-11 Figure 2-1 Space requirements of the BBU3900 in the 19-inch cabinet (unit: mm)...........................................2-3 Figure 2-2 Space requirements of the BBU3900 on the wall (unit: mm)............................................................2-4 Figure 2-3 Recommended space requirements of one RRU with and without the SRXU (unit: mm)................2-5 Figure 2-4 Minimal space requirements of one RRU with and without the SRXU (unit: mm)...........................2-6 Figure 2-5 Space requirements of two combined RRUs (unit: mm)....................................................................2-6 Figure 2-6 Recommended space requirements of multiple RRUs with and without the SRXUs (unit: mm)......2-7 Figure 2-7 Minimal space requirements of multiple RRUs with and without the SRXUs (unit: mm)................2-8 Figure 2-8 Space requirements of the SLPU in the 19-inch cabinet (unit: mm)..................................................2-9 Figure 2-9 Space requirements of the SLPU on the wall (unit: mm)...................................................................2-9 Figure 6-1 Cable ladder........................................................................................................................................6-3 Figure 6-2 U-shape connecting piece...................................................................................................................6-3 Figure 6-3 Bracket angle......................................................................................................................................6-3 Figure 6-4 Cable manager....................................................................................................................................6-3 Figure 6-5 Triangular support..............................................................................................................................6-3 Figure 6-6 Connecting clip...................................................................................................................................6-3 Figure 6-7 Fixing clip...........................................................................................................................................6-3 Figure 6-8 Cable trough.......................................................................................................................................6-3 Figure 6-9 Bushing...............................................................................................................................................6-4 Figure 6-10 End cover..........................................................................................................................................6-4 Figure 6-11 Rectangular frame.............................................................................................................................6-4 Figure 6-12 U-steel...............................................................................................................................................6-4 Figure 6-13 Over-cabinet support........................................................................................................................6-4 Figure 6-14 Rectangular frame.............................................................................................................................6-5 Figure 6-15 Installing the outdoor cable rack on the floor...................................................................................6-6 Figure 6-16 Installing the outdoor cable rack on the wall....................................................................................6-7 Figure 6-17 Docking cable ladders......................................................................................................................6-8 Figure 6-18 Ladders turned on the same level (no cable trough).........................................................................6-9 Figure 6-19 Turning the cable ladder at different levels....................................................................................6-10 Figure 6-20 Connecting the cable ladder to the wall..........................................................................................6-11 Issue 01 (2008-04-30) Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd iii
Figures
DBS3900 Site Preparation Guidelines Figure 6-21 Front connection of cable ladders...................................................................................................6-12
Figure 6-22 Side connection of cable ladders....................................................................................................6-12 Figure 6-23 Oblique connection of cable ladders...............................................................................................6-13 Figure 6-24 Connecting cable troughs...............................................................................................................6-14 Figure 6-25 Installing a cable trough on the 200-mm or 400-mm wide cable ladder........................................6-14 Figure 6-26 Installing cable troughs onto the 600-mm wide cable ladder.........................................................6-15 Figure 6-27 Cutting off the upper side of the triangle aperture .........................................................................6-16 Figure 6-28 Installing a sloping cable trough.....................................................................................................6-16 Figure 6-29 Installed sloping cable trough ........................................................................................................6-17 Figure 6-30 Cable manager on the cable rack that is not installed with a cable trough.....................................6-18 Figure 6-31 Cable manager on the cable rack that is installed with a cable trough...........................................6-18 Figure 6-32 Installing the end cover, bushing, and baffle ring..........................................................................6-19 Figure 6-33 Grounding bar of the NodeB..........................................................................................................6-20 Figure 6-34 Installing the grounding bar............................................................................................................6-20 Figure 6-35 Profile chart for installing the grounding bar.................................................................................6-21 Figure 6-36 Installing the metal pole on the concrete floor...............................................................................6-22 Figure 6-37 Two stay poles with a metal pole...................................................................................................6-22 Figure 6-38 Base................................................................................................................................................6-23 Figure 6-39 Two metal poles with a stay pole...................................................................................................6-23 Figure 7-1 Tower for telecommunication purpose...............................................................................................7-2 Figure 7-2 Structure of the antenna support (unit: mm).......................................................................................7-4 Figure 7-3 Installing the antenna support on the tower........................................................................................7-5 Figure 7-4 Structure of the antenna support directly installed on the rooftop......................................................7-6 Figure 7-5 Installing the antenna support on the parapet (height of the parapet > 1,200 mm)............................7-7 Figure 7-6 Installing the fixing clip for the antenna support on the parapet........................................................7-7 Figure 7-7 Installing the antenna support on the parapet (height of the parapet < 1,200 mm)............................7-8 Figure 7-8 Structure and installation of the antenna support base ...................................................................... 7-9
iv
Issue 01 (2008-04-30)
Tables
Tables
Table 2-1 Climatic requirements........................................................................................................................2-13 Table 2-2 Requirements for the density of physically active materials..............................................................2-14 Table 2-3 Requirements for the density of chemically active materials............................................................2-14 Table 2-4 Mechanical stress requirements.........................................................................................................2-14 Table 3-1 Power supply requirements of the DBS3900.......................................................................................3-1 Table 6-1 Items required for mounting a cable rack.............................................................................................6-3 Table 8-1 Requirements for the materials of the outdoor NodeB cables.............................................................8-2
Issue 01 (2008-04-30)
Purpose
Before installing the DBS3900 hardware, you need to conduct site survey to select an appropriate site. This ensures proper operation of the DBS3900. This document serves as a reference for conducting the DBS3900 site survey. It describes the site requirements in terms of the site location, power supply, transmission, grounding, and auxiliary facilities of the site and antenna system. To ensure smooth site construction, the site requirements described in this document must be met.
Product Version
The following table lists the product version related to this document. Product Name DBS3900 Product Version V200R010
Intended Audience
This document is intended for NodeB installers.
Change History
For changes in the document, refer to Changes in the DBS3900 Site Preparation Guidelines.
Organization
1 Safety Information 2 Site Requirements of the DBS3900 This describes the site requirements of the DBS3900. The proper installation, commissioning, and operation of the DBS3900 are ensured only when the installation space is planned and prepared in compliance with the site requirements. The site requirements of the DBS3900 consist of the site selection, installation space, construction of the BBU3900 equipment room and the tower where the RRU is installed, and the operating environment requirements.
Issue 01 (2008-04-30) Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd 1
3 Power Supply Requirements of the DBS3900 This describes the power supply requirements of the DBS3900. To ensure the proper operation of the power system of the DBS3900, the power supply of all the functional modules must comply with the related specifications. 4 Grounding Requirements of the DBS3900 Grounding requirements of the BBU3900 and RRU in the DBS3900 system must be satisfied. 5 Transmission Requirements of the NodeB Site This describes the transmission requirements of the NodeB. The transmission devices and auxiliary devices must be prepared before the site construction. Transmission requirements of the NodeB site consist of the requirements for the DDF/ODF and transmission mode. 6 Preparing Auxiliary Facilities for the DBS3900 Site This describes how to prepare the auxiliary facilities such as the cable rack, grounding bar, and metal pole for the DBS3900 site. Before you install the DBS3900, the auxiliary facilities must be prepared. 7 Preparing Auxiliary Facilities for the DBS3900 Antenna System This describes how to prepare the auxiliary facilities such as the tower and antenna support for the DBS3900 antenna system in different installation scenarios. 8 Requirements for NodeB Cables This describes the requirements for materials and routing of the NodeB cables such as the power cables, signal cables, and PGND cables. 9 Checklist for the DBS3900 Site Preparation This describes how to check the NodeB site preparations. Before installing the NodeB, you need to check the site, power supply, transmission system, grounding system, antenna system, auxiliary facilities, and cables.
Conventions
1. Symbol Conventions The following symbols may be found in this document. They are defined as follows Symbol Description Indicates a hazard with a high level of risk that, if not avoided, will result in death or serious injury. Indicates a hazard with a medium or low level of risk which, if not avoided, could result in minor or moderate injury. Indicates a potentially hazardous situation that, if not avoided, could cause equipment damage, data loss, and performance degradation, or unexpected results.
Issue 01 (2008-04-30)
DANGER
WARNING
CAUTION
2
Symbol
TIP
Description Indicates a tip that may help you solve a problem or save your time. Provides additional information to emphasize or supplement important points of the main text.
NOTE
2. General Conventions Convention Times New Roman Boldface Italic Courier New 3. Command Conventions Convention Boldface Italic [] {x | y | ...} [ x | y | ... ] { x | y | ... } * [ x | y | ... ] * Description The keywords of a command line are in boldface. Command arguments are in italic. Items (keywords or arguments) in square brackets [ ] are optional. Alternative items are grouped in braces and separated by vertical bars.One is selected. Optional alternative items are grouped in square brackets and separated by vertical bars.One or none is selected. Alternative items are grouped in braces and separated by vertical bars.A minimum of one or a maximum of all can be selected. Alternative items are grouped in braces and separated by vertical bars.A minimum of zero or a maximum of all can be selected. Description Normal paragraphs are in Times New Roman. Names of files,directories,folders,and users are in boldface. For example,log in as user root . Book titles are in italics. Terminal display is in Courier New.
4. GUI Conventions Convention Boldface > Description Buttons,menus,parameters,tabs,window,and dialog titles are in boldface. For example,click OK. Multi-level menus are in boldface and separated by the ">" signs. For example,choose File > Create > Folder .
Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd 3
Issue 01 (2008-04-30)
5. Keyboard Operation Convention Key Key1+Key2 Key1,Key2 Description Press the key.For example,press Enter and press Tab. Press the keys concurrently.For example,pressing Ctrl+Alt+A means the three keys should be pressed concurrently. Press the keys in turn.For example,pressing Alt,A means the two keys should be pressed in turn.
6. Mouse Operation Action Click Double-click Drag Description Select and release the primary mouse button without moving the pointer. Press the primary mouse button twice continuously and quickly without moving the pointer. Press and hold the primary mouse button and move the pointer to a certain position.
Issue 01 (2008-04-30)
1 Safety Information
1
1.1 Safety Precautions
Following All Safety Precautions
Safety Information
This section describes certain safety precautions and helps to choose the measurement device and testing device. Read and follow these safety precautions before installing, operating, and maintaining Huawei devices.
Before any operation, read the instructions and precautions in this document carefully to minimize the possibility of accidents. The Danger, Caution, and Note items in the package of documents do not cover all the safety precautions that must be followed. They only provide the generic safety precautions for operations.
Symbols
DANGER
This symbol indicates that casualty or serious accident may occur if you ignore the safety instruction.
CAUTION
This symbol indicates that serious or major injury may occur if you ignore the safety instruction.
NOTE
This symbol indicates that the operation may be easier if you pay attention to the safety instruction.
Issue 01 (2008-04-30)
1-1
1 Safety Information
Only the trained and qualified personnel can install, operate and maintain the device. Only the qualified specialists are allowed to remove the safety facilities, and repair the device. Any replacement of the device or part of the device (including the software) or any change made to the device must be performed by qualified or authorized personnel of Huawei. Any fault or error that might cause safety problems must be reported immediately to the personnel in charge.
Grounding Requirements
The following requirements are applicable to the device to be grounded:
l l
Ground the device before installation and remove the ground cable after uninstallation. Do not operate the device in the absence of a ground conductor. Do not damage the ground conductor. The unit (or system) must be permanently connected to the protection ground before operation. Check the electrical connection of the device before operation and ensure that the device is reliably grounded.
Safety of Personnel
Ensure the following:
l l
When lightning strikes, do not operate the device and cables. When lightning strikes, unplug the AC power connector. Do not use the fixed terminal or touch the terminal or antenna connector.
NOTE
The previous two requirements are suitable for the wireless fixed terminal.
l
To prevent electric shock, do not connect safety extra-low voltage (SELV) circuits to telecommunication network voltage (TNV) circuits. To prevent laser radiation from injuring your eyes, never look into the optical fiber outlet with unaided eyes. To prevent electric shock and burns, wear the electrostatic discharge (ESD) clothing, gloves and wrist strap, and remove conductors such as jewelry and watch before operation.
1-2
Issue 01 (2008-04-30)
1 Safety Information
Device Safety
l
Before operation, the device must be secured on the floor or other fixed objects, such as the walls and the mounting racks. Do not block ventilation openings while the system is running. When installing the panel, tighten the screw with the tool.
l l
DANGER
l
The high voltage power supply provides power for running the system. Direct contact with the high voltage power supply or contact through damp objects may result in fatal danger. Non-standard and improper high voltage operations may result in fire and electric shock. The personnel who install the AC facility must be qualified to perform operations on high voltage and AC power supply facilities. When installing the AC power supply facility, follow the local safety regulations. When operating the AC power supply facility, follow the local safety regulations. When operating the high voltage and AC power supply facilities, use the specific tools instead of common tools. When the operation is performed in a damp environment, ensure that water is kept off the device. If the cabinet is damp or wet, shut down the power supply immediately.
l l l
Thunderstorm
The following requirements are suitable only for the wireless base station or the device with an antenna or GPS antenna.
DANGER
In a thunderstorm, do not perform operations on high voltage and AC power supply facilities or on a steel tower and mast.
CAUTION
Ground the device before powering on the device. Otherwise, the personnel and device are in danger.
Issue 01 (2008-04-30)
1-3
1 Safety Information
If the "high electrical leakage" flag is stuck to the power terminal of the device, you must ground the device before powering it on.
Power Cable
CAUTION
Do not install and remove the power cable with a live line. Transient contact between the core of the power cable and the conductor may generate electric arc or spark, which may cause fire or eye injury.
l l
Before installing or removing the power cable, turn off the power switch. Before connecting the power cable, ensure that the power cable and label comply with the requirements of the actual installation.
Fuse
CAUTION
To ensure that the system runs safely, when a fuse blows, replace it with a fuse of the same type and specifications.
Electrostatic Discharge
CAUTION
The static electricity generated by the human body may damage the electrostatic sensitive components on the circuit board, such as the large-scale integrated circuit (LIC). In the following situations, the human body generates a static electromagnetic field:
l l l l
Movement of body parts Clothes friction Friction between shoes and the ground Holding plastic in hand
The static electromagnetic field will remain within the human body for a long time. Before contacting the device, plug boards, circuit boards, and application specific integrated circuits (ASICs), wear a grounded ESD wrist strap. It can prevent the sensitive components from being damaged by the static electricity in the human body. Figure 1-1shows how to wear an ESD wrist strap.
1-4 Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd Issue 01 (2008-04-30)
1 Safety Information
1.4 Battery
Storage Battery
DANGER
Before handling the storage battery, read the safety precautions for the handling and connection of the storage battery. Incorrect operation of storage batteries may cause danger. During operation, ensure the following:
l l
Prevent any short-circuit. Prevent the electrolyte from overflowing and leakage.
Electrolyte overflow may damage the device. It will corrode the metal parts and the circuit boards, and ultimately damage the device and cause short-circuit of the circuit boards.
Issue 01 (2008-04-30) Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd 1-5
1 Safety Information
General Operations
Before installing and maintaining the storage battery, ensure the following:
l l l l
Use special insulation tools. Use eye protection devices and operate with care. Wear rubber gloves and an apron in case of an electrolyte overflow. Always keep the battery upright when moving. Do not place the battery upside down or tilt it.
Short-Circuit
DANGER
Short-circuit of the battery may cause injury. Although the voltage of a battery is low, high transient current generated by short-circuit will release a surge of power. Keep metal objects away from the battery to prevent short circuit. If they have to be used, disconnect the battery in use before performing any other operation.
Harmful Gas
CAUTION
l
Do not use unsealed lead-acid storage batteries, because the gas emitted from it may result in fire or device corrosion. Lay the storage battery horizontally and fix it properly.
The lead-acid storage battery in use will emit flammable gas. Therefore, store it in a place with good ventilation and take precautions against fire.
High Temperature
CAUTION
High temperature may result in distortion, damage, and electrolyte overflow of the battery. When the temperature of the battery exceeds 60oC, check whether there is acid overflow. If acid overflow occurs, handle the acid immediately.
1-6
Issue 01 (2008-04-30)
1 Safety Information
Acid
CAUTION
If the acid overflows, it should be absorbed and neutralized immediately. When handling a leaky battery, protect against the possible damage caused by the acid. Use the following materials to absorb and neutralize acid spills:
l l
Antacids must be used according to the instructions provided by the battery manufacturer.
Lithium Battery
CAUTION
There is danger of explosion if the battery is incorrectly replaced.
l
Replace the lithium battery with the same or equivalent type recommended by the manufacturer. Dispose of the used battery according to the instructions provided by the manufacturer. Do not dispose of the lithium battery in fire.
l l
1.5 Radiation
Electromagnetic Field Exposure
CAUTION
High power radio-frequency signals are harmful to human body. Before installing or maintaining an antenna on a steel tower or mast with a large number of transmitter antennas, the operator should coordinate with all parties to ensure that the transmitter antennas are shut down. The base transceiver station (BTS) has RF radiation (radiation hazard). Suggestions for the installation and operation of BTSs are given in the following section. Operators are also required to comply with the related local regulations on erecting BTSs.
l
The antenna should be located in an area that is inaccessible to the public where the RF radiation exceeds the stipulated value.
Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd 1-7
Issue 01 (2008-04-30)
1 Safety Information
l
If the areas where RF radiation exceeds the stipulated value are accessible to workers, ensure that workers know where these areas are. They can shut down the transmitters before entering these areas. Such areas may not exist; but if they exist, the areas must be within a range of less than 10 m around the antennas. Each forbidden zone should be indicated by a physical barrier and striking sign to warn the public or workers.
Laser
CAUTION
When handling optical fibers, do not stand close to, or look into the optical fiber outlet with unaided eyes. Laser transceivers or transmitters are used in the optical transmission system and associated test tools. Because the laser that is transmitted through the optical fiber produces a small beam of light, it has a very high power density and is invisible to human eyes. If a beam of light enters the eye, the retina may be damaged. Normally, staring into the end of an unterminated optical fiber or broken optical fiber with the unaided eyes from a distance of more than 150 mm [5.91 in.] will not cause eye injury. Eyes may, however, be damaged if an optical tool such as a microscope, magnifying glass or eye loupe is used to stare into the bare optical fiber end. Read the following guidelines to prevent laser radiation:
l l l l
Only the trained and authorized personnel can perform the operation. Wear a pair of eye-protective glasses when you are handling lasers or optical fibers. Ensure that the optical source is switched off before disconnecting optical fiber connectors. Never look into the end of an exposed optical fiber or an open connector if you cannot ensure that the optical source is switched off. To ensure that the optical source is switched off, use an optical power meter. Before opening the front door of an optical transmission system, ensure that you are not exposed to laser radiation. Never use an optical tool such as a microscope, a magnifying glass, or an eye loupe to look into the optical fiber connector or end.
l l
Only the trained personnel can cut and splice optical fibers. Before cutting or splicing an optical fiber, ensure that the optical fiber is disconnected from the optical source. After disconnecting the optical fiber, use protecting caps to protect all the optical connectors.
1-8
Issue 01 (2008-04-30)
1 Safety Information
The personnel who work at heights must be trained. The operating machines and tools should be carried and handled safely to prevent them from falling. Safety measures, such as wearing a helmet and a safety belt, should be taken. In cold regions, warm clothes should be worn before working at heights. Ensure that the lifting appliances are well prepared for working at heights.
l l l
Lifting Weights
CAUTION
Do not access the areas under the arm of the crane and the goods in suspension when lifting weights.
l l l
Ensure that the operators have been trained and qualified. Check the weight lifting tools and ensure that they are intact. Lift the weight only when the weight lifting tools are firmly mounted onto the weightbearing object or the wall. Use a concise instruction to prevent incorrect operation. The angle between the two cables should be less than or equal to 90o in the lifting of weights (See Figure 1-2).
l l
Issue 01 (2008-04-30)
1-9
1 Safety Information
Check the ladder before using it. Check the maximum weight that the ladder can support. Never overload the ladder.
The slant angle is preferred to be 75o. The slant can be measured with the angle square or with arms, as shown in Figure 1-3. When using a ladder, place the wider end of the ladder on the ground and take protective measures on the base of the ladder against slippage. Place the ladder on a stable ground.
The gravity of the body does not shift from the edge of the ladder. Keep balance on the ladder before performing any operation. Do not climb higher than the fourth highest step of the ladder.
If you tend to climb to the roof, the length of the ladder should be at least one meter higher than the eave, as shown in Figure 1-4.
1-10
Issue 01 (2008-04-30)
1 Safety Information
CAUTION
Do not drill on the cabinet without permission. Inappropriate drilling on the cabinet may damage the electromagnetic shielding and internal cables. Metal shavings from the drilling may result in a short-circuit of the circuit board if they get into the cabinet.
l
Before drilling a hole on the cabinet, remove the cables from the cabinet.
Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd 1-11
Issue 01 (2008-04-30)
1 Safety Information
l l l
During the drilling, wear blinkers to protect your eyes. During the drilling, wear the protective gloves. Prevent the metal shavings from getting into the cabinet. After drilling, clean the metal shavings in time.
CAUTION
When carrying the device by hand, wear the protective gloves to prevent injury by sharp objects.
Handling Fans
l
When replacing a component, place the component, screw, and tool at a safe place to prevent them from falling into the running fan. When replacing the ambient equipment around the fan, do not place the finger or board into the running fan until the fan is switched off and stops running.
CAUTION
l l
Be careful when moving heavy objects. When moving the chassis outwards, be aware about the unfixed or heavy objects on the chassis to prevent injury. Two persons should be available to move a chassis; one person must not move a heavy chassis. When moving a chassis, keep your back straight and move stably to prevent a sprain. When moving or lifting a chassis, hold the handle or bottom of the chassis. Do not hold the handle of the installed modules in the chassis, such as the power module, fan module, or board.
1.8 Others
Inserting and Removing a Board
CAUTION
When inserting a board, wear the ESD wrist strap or gloves. Insert the board gently to prevent any bent pins on the backplane.
1-12
Issue 01 (2008-04-30)
1 Safety Information
Insert the board along the guide rail. Avoid contact of one board with another to prevent short-circuit or damage. Do not remove the active board before powering off. When holding a board in hand, do not touch the board circuit, components, connectors, or connection slots.
CAUTION
Bundle the signal cables separately from the strong current cables or high voltage cables.
Cabling Requirements
At a very low temperature, movement of the cable may damage the plastic skin of the cable. To ensure the construction safety, comply with the following requirements:
l l
When installing cables, ensure that the environment temperature is above 0oC. If cables are stored in the place below 0oC, move the cables into a place at a room temperature and store the cables for more than 24 hours before installation. Move the cables with care, especially at a low temperature. Do not drop the cables directly from the vehicle.
Issue 01 (2008-04-30)
1-13
Issue 01 (2008-04-30)
2-1
The site is not exposed to excessive heat, dust, harmful gases, flammable or explosive materials, or unstable voltage. The site is not located at places that are prone to frequent earthquakes and exposed to loud noise. The site is far from power transformer station, industrial boiler, and heating boiler. The site is located far from high-power radio transmitters, radar stations, or other interference sources. The interference field intensity is not higher than the shielding specifications of the NodeB for useless radiation. The equipment room for the indoor NodeB is constructed at least 3.7 km away from the seaside or a salt lake. If this requirement cannot be met, the equipment room must be enclosed and configured with air conditioners. In addition, avoid using salt soil as the building material for the room. Otherwise, the equipment that can withstand the adverse weather must be configured. The distance between the outdoor NodeB and the sea exceeds 500 m. The site is away from pollution sources. If this requirement cannot be met, ensure that the site is in the perennial upwind direction of the pollution source.
l l
l l
The site is at least 5 km away from heavy pollution sources such as a smelting plant or a coal mine. The site is at least 3.7 km away from medium pollution sources such as a chemical plant, a rubber plant, or an electric plating plant. The site is at least 2 km away from light pollution sources such as a food products factory or a leather processing factory.
The air inlets of the telecommunication equipment are far away from the sewer pipe, septic tank, and sewage disposal pool. The equipment are in positive pressure state and free from corrosive gas. Otherwise, electronic components and circuit boards may corrode. The room for feeding poultry and the chemical fertilizer warehouse cannot be used as the equipment room for the indoor NodeB. If this requirement cannot be met, ensure that the equipment room is constructed in the perennial upwind direction of the room for feeding poultry or the chemical fertilizer warehouse. The equipment room for the indoor NodeB is preferably on the second floor or higher. If this requirement cannot be met, ensure that the room is located at least 600 mm above the maximum local flood level.
2-2
Issue 01 (2008-04-30)
2.2.1 Space Requirements of the BBU3900 This describes the space requirements of the BBU3900. When installed in a 19-inch cabinet, the BBU3900 has the minimal space requirements for cabling and OM. In addition, Huawei offers the recommended space requirements. 2.2.2 Space Requirements of the RRU and SRXU In different installation modes, the RRU and SRXU have the minimal space requirements for cabling and OM. Based on the engineering practice, Huawei offers the recommended space requirements. 2.2.3 Space Requirements of the SLPU This describes the space requirements of the SLPU. When installed in a 19-inch cabinet on a wall, the SLPU has the minimal space requirements for cabling and OM. In addition, Huawei offers the recommended space requirements.
Issue 01 (2008-04-30)
2-3
Figure 2-2 Space requirements of the BBU3900 on the wall (unit: mm)
20 mm above the equipment for maintenance 800 mm between the bottom and the ground for cabling and maintenance 50 mm on both sides for ventilation 600 mm in front of the equipment for maintenance
The following figures related to the space requirements assume that the cabling cavities are on the left side of the RRU and SRXU. If the RRU and SRXU are installed with the cabling cavities on the right, the horizontal space requirements are opposite to what are shown in the figures.
2-4
Issue 01 (2008-04-30)
Figure 2-3 Recommended space requirements of one RRU with and without the SRXU (unit: mm)
At least 500 mm under the equipment for cabling. It is recommended that the space be 1,200 mm between the bottom and the ground for easy maintenance. At least 800 mm in front of the equipment for maintenance. At least 200 mm above the equipment for maintenance. At least 600 mm on the left of the equipment for maintenance. At least 300 mm on the right of the equipment for maintenance. Regardless of whether the SRXU is fixed to the RRU, the space requirements are the same.
l l l l l
Figure 2-4 shows the minimal space requirements of one RRU with and without the SRXU.
Issue 01 (2008-04-30)
2-5
Figure 2-4 Minimal space requirements of one RRU with and without the SRXU (unit: mm)
300 mm under the equipment for cabling. It is recommended that the space be 1,200 mm between the equipment bottom and the ground for easy maintenance. 600 mm in front of the equipment for maintenance. 200 mm above the equipment for maintenance. 400 mm on the left of the equipment for maintenance. 100 mm on the right of the equipment for maintenance.
When two RRUs need to be combined, space requirements of each RRU must be met. In addition, the space between the two RRUs should stay within the range shown in Figure 2-5. Figure 2-5 Space requirements of two combined RRUs (unit: mm)
When two RRUs are installed horizontally, the space is 1,200 mm at most. When two RRUs are installed vertically, the space is 800 mm at most.
NOTE
The space requirements of two combined SRXUs are the same as those of two combined RRUs.
At least 500 mm under the equipment for cabling. It is recommended that the space be 1,200 mm between the bottom and the ground for easy maintenance. At least 800 mm in front of the equipment for maintenance. At least 200 mm above the equipment for maintenance. At least 800 mm on the left of the equipment for maintenance. At least 800 mm on the right of the equipment for maintenance. Regardless of whether the SRXUs are fixed to the RRU, the space requirements are the same. Regardless of whether the RRUs are in two-module or three-module centralized installation mode, the space requirements are the same.
l l l l l
Figure 2-7 shows the minimal space requirements of multiple RRUs with and without the SRXUs.
Issue 01 (2008-04-30) Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd 2-7
Figure 2-7 Minimal space requirements of multiple RRUs with and without the SRXUs (unit: mm)
300 mm under the equipment for cabling. It is recommended that the space be 1,200 mm between the equipment bottom and the ground for easy maintenance. 600 mm in front of the equipment for maintenance. 200 mm above the equipment for maintenance. 600 mm on the left of the equipment for maintenance. 600 mm on the right of the equipment for maintenance.
l l l l
2-8
Issue 01 (2008-04-30)
Figure 2-8 Space requirements of the SLPU in the 19-inch cabinet (unit: mm)
20 mm above the equipment for maintenance 800 mm between the SLPU bottom and the ground for cabling and maintenance 50 mm on both sides for ventilation 800 mm in front of the SLPU for maintenance
The equipment room is large enough for equipment installation and future capacity expansion. The feeder window is installed and feeders can be routed in the room. Sufficient space is provided for easy installation and maintenance of the equipment. The cabinet door can be opened and closed conveniently.
l l l
Floorboards are laid down firmly and there is no space between the boards. The horizontal error per square meter is within 2 mm. If the room does not have movable ESD floorboards, you need to use ESD floor with a volume resistance between 1.0 x 107 ohms to 1.0 x 1010 ohms. The ESD floor or movable floorboards are grounded by using cables and 1-megaohm current-limiting resistance. Tests must prove that the terrazzo floor (including the concrete floor) can meet the requirement.
Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd Issue 01 (2008-04-30)
2-10
All cable holes in the floor are capped with cover plates. Positions for the holes are determined in compliance with the engineering design and the dimensions are accurate to ensure easy installation.
The minimum dimension of the door is 2 m (height) x 1 m (width). The door and window are sealed with dustproof plastic tapes. Use reflecting paper on the windowpane or colored glass for windows that are exposed to excessive sunlight. You may block the window if the light in the room is sufficient.
The roof and walls are durable, well insulated, and leakproof. Waterproofing measures are taken if there are antenna poles or cable holes on the rooftop. Ensure that the rooftop is strong enough to bear the weight of the equipment. Lusterless paint can be used on the walls. Avoid painting the walls with paint that chalks off easily.
The ESD floor or movable ESD floorboards are used in the equipment room and properly grounded. The ESD work clothes and ESD wrist straps are provided in the equipment room. The density of the electric field is less than 300 mV/m. The density of the magnetic field is less than 11 GS.
l l
The equipment room is not exposed to direct sunlight. Otherwise, the circuit board and other components of the equipment room are easily deformed. An anti-explosion lamp with soft lighting is installed in the room where the batteries are located. The unmanned equipment rooms are lit normally and powered by the mains. The DC power is provided as the emergency lighting for the equipment room of heavy traffic or great importance.
l l
Telecommunication buildings are major fire protection units. Therefore, the NodeB equipment room must be designed in compliance with the local fire protection regulations. There is no flammable, explosive substance in the equipment room. Fire-fighting equipment are provided in the equipment room. If there are alarm devices such as a smoke sensor or temperature sensor, they function normally. Sockets of different voltages in the equipment room are clearly labeled. The holes left in the floor are capped with safe cover plates. In addition to the alarm devices such as the fire-alarm and smoke detector, the equipment room can also be installed with the automatic fire extinguisher. This can extinguish or control the fire in the initial stage of fire. A certain number of portable fire extinguishers are provided in the corridor outside the equipment room so that they can be used in the initial stage of the fire. The fire fighting pool, if equipped in compliance with the fire fighting specifications, can meet the water demand for both inside and outside of the equipment room during the fire, assuming the fire lasts for two hours. The fire hydrant is placed in the corridors or stair wells for easy accessibility.
l l
l l l
The width of the transporting corridor is greater than 1.5 m and the height is greater than 2.5 m. The emergency exit is free from obstruction. The emergency exit sign is clearly visible in the equipment room. The height of the elevator is greater than 2.4 m.
Engineering specifications of the tower comply with the requirements for communication equipment installation. There is a maintenance channel on the tower with safety design. The channel is spacious enough to hold at least one person. Sufficient space is provided for the RRU installation and future maintenance. The grounding system meets the grounding requirements of the site. A grounding bar for connecting the PGND cable of the RRU is installed. If the grounding bar is not installed, sufficient space is provided for installing the grounding bar. A cable rack is installed for the routing of the RRU cables such as the power cables and optical cables. If the cable rack is not installed, sufficient space is provided for installing the rack.
Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd Issue 01 (2008-04-30)
l l l
2-12
Climatic Requirements
Table 2-1 lists the climatic requirements for the working environment of the DBS3900. Table 2-1 Climatic requirements Item Altitude Air pressure Temperature Specification 4,000 m 70 kPa to 106 kPa BBU3900: -20 to +55 RRU:
l l
-40 to +50 (with solar radiation) -40 to +55 (without solar radiation)
Relative humidity
Absolute humidity
Biological Requirements
The working environment of the DBS3900 should not conducive for the growth of fungus or mildew.
There is no explosive, conductive, magneto-conductive or corrosive dust in the air. The density of the physically active materials meets the requirements listed in Table 2-2.
Issue 01 (2008-04-30)
2-13
Table 2-2 Requirements for the density of physically active materials Physically Active Material Suspended dust Falling dust Sand Note:
l l l
Suspended dust: diameter 75 m Falling dust: 75 m diameter 150 m Sand: 150 m diameter 1,000 m
The density of the chemically active materials meets the requirements listed in Table 2-3. Table 2-3 Requirements for the density of chemically active materials Chemically Active Material SO2 NH3 Cl2 Unit mg/m3 mg/m3 mg/m3 Density 1.50 0.15 0.30
Frequency range: 5-100-5 Hz; acceleration: 1.0 x g; scanning frequency: 0.25 oct/min; triaxial test
2-14
Issue 01 (2008-04-30)
Specification 100 m/s2 0 Frequency range: 0.3 Hz to 50 Hz Zero Period Acceleration (ZPA): 1.5 x g 30s
Anti-seismic requirements
Earthquake
Note:
l
Impact response spectrum refers to the maximum acceleration response curve generated by the equipment under the specified impact excitation. Impact response spectrum II means that the duration of semi-sine impact response spectrum is 6 ms. Static payload refers to the capability of the equipment in a packing case to bear the pressure from the top in normal pile-up method.
Issue 01 (2008-04-30)
2-15
NOTE
If the voltage stability does not meet the requirements, you need to use voltage regulators to ensure a proper power voltage range.
Issue 01 (2008-04-30)
3-1
The green and yellow PGND cable of the BBU3900 must be copper-based and plasticinsulated with the cross-sectional area no less than 6 mm2. The grounding resistance of the BBU3900 is less than 10 ohms. When the BBU3900 is installed in the equipment room, the PGND cable of the BBU3900 is connected to the protection grounding bar of the equipment room. When the BBU3900 is installed in outdoor cabinets such as the APM30 or the APM100, the PGND cable of the BBU3900 is connected to the grounding bar in the cabinet. When the BBU3900 is connected to the RRU, do not use fibers that has have strengthening ribs. When the E1/T1 cable of the BBU3900 is routed out of the equipment room overhead, add a surge protection box for the BBU3900 that is installed in the equipment room. Connect the PGND cable of the BBU3900 to the grounding bar on the surge protection box, and then route the PGND cable from the surge protection box to the grounding bar of the equipment room. When the E1/T1 cable of the BBU3900 is routed outdoors, add a surge protection box for the BBU3900 that is installed in an outdoor cabinet. Connect the PGND cable of the BBU3900 to the grounding bar on the surge protection box, and then route the PGND cable from the surge protection box to the grounding bar in the cabinet.
l l
The green and yellow PGND cable of the RRU must be copper-based and plastic-insulated with a cross-sectional area not less than 25 mm2. The grounding resistance of the RRU is less than 10 ohms.
NOTE
Refer to Antenna System User Guide for the grounding requirements of the RRU, antennas, and feeders in different scenarios.
Issue 01 (2008-04-30)
4-1
The delivered transmission cables and connectors match the connectors on the DDF/ODF on the transmission device side. Before you install the NodeB, the DDF/ODF is installed and external trunk cables or optical cables are connected to the DDF/ODF. It is recommended that the copper wires be used to connect the DDF/ODF and the grounding bar of the equipment room.
Transmission resources must meet the upcoming requirements of the NodeB site and extra resources must be reserved for capacity expansion. When RNCs and NodeBs are close to coverage of the Metropolitan Area Network (MAN) or backbone network, they are directly connected to the networks through E1s or SDH interfaces in ATM or IP transport mode. There are restrictions on the maximum transmission distance for the trunk cables. Additional transmission devices are required if the trunk cables are longer than the corresponding maximum transmission distance. If the NodeB is at the far end of the RNC and the MAN/backbone network, and is within the Line of Sight (LOS) of microwave transmission, the microwave transmission is used. The indoor units of the microwave transmission devices are installed in the reserved space. If the NodeB is at the far end of the RNC and the MAN/backbone network, and is not within the LOS of microwave transmission, the xDSL transmission is used. It is recommended that the devices for xDSL transmission be installed in the reserved space.
Issue 01 (2008-04-30)
5-1
Issue 01 (2008-04-30)
6-1
Specifications
Select the cabling troughs by observing the following rules:
l l l
For a 200-mm wide cabling ladder, use a 200-mm wide cabling trough. For a 400-mm wide cabling ladder, use a 400-mm wide cabling trough. For a 600-mm wide cable ladder, use a 400-mm wide cable trough and a 200-mm wide cable trough.
The cable ladder is 2,500 mm long and the cable trough is 2,000 mm long.
Items
Table 6-1 shows the items required for mounting a cable rack.
6-2
Issue 01 (2008-04-30)
Table 6-1 Items required for mounting a cable rack Figure 6-1 Cable ladder Figure 6-2 U-shape connecting piece
Issue 01 (2008-04-30)
6-3
Procedure
Step 1 6.1.3 Installing the Outdoor Cable Rack Step 2 6.1.4 Connecting Cable Ladders Step 3 6.1.5 Installing the Cable Trough Step 4 6.1.6 Installing Accessories ----End
Context
CAUTION
When you determine the location of the cable rack, place the rectangular frame correctly, as shown in Figure 6-14.
6.1.3.1 Installing the Outdoor Cable Rack on the Floor An outdoor cable rack can be installed on the floor if the cable rack cannot be mounted on the wall. 6.1.3.2 Installing the Outdoor Cable Rack on the Wall This topic describes how to install an outdoor cable rack on the wall.
Procedure
Step 1 Based on the engineering design, determine the location of the cable rack. Step 2 Determine the location of the rectangular frame and accordingly mark the positions of the drilling holes. Ensure that each segment of the cable ladder is supported by two rectangular frames and that the spacing between two adjacent rectangular frames is 1,250 mm. Step 3 Use a 10 bit to drill holes at the marked positions. Ensure that the depth of the holes is between 60 mm and 65 mm. Step 4 Use a screwdriver to fasten the nuts in the counterclockwise direction to the top of the M8 x 80 expansion bolts, and feed the bolts vertically into the holes. Hammer the expansion bolts until the tubes are completely buried in the wall. Step 5 Remove the flat washers, spring washers, and nuts from the expansion bolts, and lead the expansion bolts through the insulating pads.
Issue 01 (2008-04-30) Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd 6-5
Step 6 Lead the expansion bolts through the holes in the rectangular frame. Add in sequence the insulating washers, large flat washers 8, spring washers 8, and nuts M8 to the expansion bolts, and then fasten the M8 nuts to fix the rectangular frame to the floor, as shown in Figure 6-15. Step 7 Place the cable ladder on the horizontal beam of the rectangular frame, align the holes on the lower side of the U-steel with the holes in the horizontal beam of the triangular support, and fix the cable ladder to the rectangular frame by using bolts M6 x 20 and nuts M6, as shown in Figure 6-15. Figure 6-15 Installing the outdoor cable rack on the floor
----End
Procedure
Step 1 Based on the engineering design, determine the location of the cable rack. Step 2 Determine the location of the rectangular frame and accordingly mark the positions of the drilling holes. Ensure that each segment of the cable ladder is supported by two rectangular frames and that the spacing between two adjacent rectangular frames is 1,250 mm. Step 3 Use a 10 bit to drill holes at the marked positions. Ensure that the depth of the holes is between 60 mm and 65 mm. Step 4 Use a screwdriver to fasten the nuts in the counterclockwise direction to the top of the M8 x 80 expansion bolts, and feed the bolts vertically into the holes. Hammer the expansion bolts until the tubes are completely buried in the wall.
6-6 Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd Issue 01 (2008-04-30)
Step 5 Remove the flat washers, spring washers, and nuts from the expansion bolts, and lead the expansion bolts through the insulating pads. Step 6 Lead the expansion bolts through the holes in the vertical beam of the rectangular frame. Add in sequence the insulating washers, large flat washers 8, spring washers 8, and nuts M8 to the expansion bolts, and then fasten the nuts to fix the rectangular frame to the wall. as shown in Figure 6-16. Step 7 Place the cable ladder on the horizontal beam of the rectangular frame, align the holes on the lower side of the U-steel with the holes in the horizontal beam of the triangular support, and fix the cable ladder to the rectangular frame by using bolts M6 x 20 and nuts M6, as shown in as shown in Figure 6-16. Figure 6-16 Installing the outdoor cable rack on the wall
----End
If one of the two cable ladders that are connected in a T shape is installed with a cable trough but the other one is not, a cable ladder and the cable trough of the other ladder should be connected in a T shape. 6.1.4.4 Connecting the Cabling Ladder to the Wall This topic describes how to use bracket angles, insulating pads, insulating washers, spring washers, flat washers, and expansion bolts to connect a cable ladder to the wall. 6.1.4.5 Connecting Cable Ladders on Different Planes The cable ladders on different planes can be connected by a front connection, side connection, or oblique connection, as shown in
Context
NOTE
If the length of the cable ladder is not an integer multiple of 2.5 m, cut off the surplus part. You then need to apply paint to the sections for rust prevention and for visual appeal.
Procedure
Step 1 Connect two cable ladders by using U-shape connecting pieces. Use a grounding cable to connect the first and the fourth bolts that connect the cable ladder and the U-shape connecting piece. as shown in Figure 6-17. Figure 6-17 Docking cable ladders
6-8
Issue 01 (2008-04-30)
Step 2 Use a grounding cable to connect the second or the third bolt to the corresponding bolt. as shown in Figure 6-17. ----End
Procedure
Use bracket angles, bolts, and nuts to connect the two cable ladders, and ensure the two ladders are on the same level, as shown in Figure 6-18. Figure 6-18 Ladders turned on the same level (no cable trough)
----End
Issue 01 (2008-04-30)
6-9
Context
CAUTION
Ensure that the cable ladder and the cable trough are connected at the same level.
Procedure
If one of the two cable ladders has a cable trough segment, use bracket angles, bolts, and nuts to connect the two cable ladders. Figure 6-19 shows how to turn two cabling ladders at different levels. Figure 6-19 Turning the cable ladder at different levels
----End
Procedure
Step 1 Use expansion bolts M6 x 20 to connect the bracket angles to the cable ladder, as shown in in Figure 6-20.
6-10
Issue 01 (2008-04-30)
Step 2 Use expansion bolts M8 x 80 to connect the bracket angles to the wall, as shown in in Figure 6-20. ----End
Procedure
Step 1 Choose a cable ladder of corresponding length and use it as a climbing ladder. Step 2 Use bracket angles, bolts, and nuts to connect the climbing ladder and the cable ladder. The cable ladders on different planes can be connected by a front connection, side connection, or oblique connection, as shown in Figure 6-21, Figure 6-22, and Figure 6-23.
Issue 01 (2008-04-30)
6-11
6-12
Issue 01 (2008-04-30)
----End
Context
Troughs can be 200-mm or 400-mm wide. Thus, the cable troughs can be installed on the following:
l l
6.1.5.1 Connecting the Cable Troughs If a long cable trough is required, you should connect cable troughs first and then install them. 6.1.5.2 Installing the Cable Trough on the Cable Ladder This topic describes how to install a cable trough onto the cable ladder. The cable ladder can be 200-mm, 400-mm, or 600-mm wide. 6.1.5.3 Installing the Sloping Cable Trough This topic describes how to install a sloping cable trough.
Procedure
As the cable troughs taper, you can connect two cable troughs by feeding the thinner end of a cable trough into the thicker end of the other one, as shown in Figure 6-24. The length of the inserted part must not exceed 250 mm.
Issue 01 (2008-04-30) Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd 6-13
----End
Prerequisite
The cable ladder should be installed.
Procedure
l Install a cable trough onto the 200-mm or 400-mm wide cable ladder. 1. 2. 3. Based on the width of the cable ladder, choose a cable trough of the same width. Place the cable trough on the cable ladder. Fix the cable trough to the cable ladder by using fixing clips. A combined cable trough requires four clips, two on each side. The clips on both sides are laid symmetrically, as shown in Figure 6-25. Figure 6-25 Installing a cable trough on the 200-mm or 400-mm wide cable ladder
l
6-14
1.
Combine a 200-mm wide cable trough with a 400-mm wide cable trough to build a 600-mm wide cable trough by using connecting clips. Three connecting clips are required for combining two cable troughs. Fix the cable trough to the cable ladder by using fixing clips. A combined cable trough requires four clips, two on each side. The clips on both sides are laid symmetrically, as shown in Figure 6-26. Figure 6-26 Installing cable troughs onto the 600-mm wide cable ladder
2.
----End
Prerequisite
The cable ladder should be installed.
Context
NOTE
The actual slope of the cable trough can be smaller than the required one.
Procedure
Step 1 Cut off the upper side of the triangle aperture in the cable trough, as shown in Figure 6-27. Be sure to apply paint to the surface of the cut sections.
Issue 01 (2008-04-30)
6-15
Figure 6-27 Cutting off the upper side of the triangle aperture
Step 2 At the marked line, bend one part of the cable trough to the corresponding slope, as shown in Figure 6-28. Figure 6-28 Installing a sloping cable trough
Step 3 Fix the cable trough to the cable ladder by using fixing clips. Figure 6-29 shows an installed sloping cable trough.
6-16
Issue 01 (2008-04-30)
----End
Issue 01 (2008-04-30)
6-17
Context
CAUTION
To align the cable manager with the cable rack, abide by the following principles:
l l
If the cable rack is installed with a cable trough, fix the cable manager to the cable rack through the lower row of holes in the cable manager. If the cable rack is not installed with a cable trough, fix the cable manager to the cable rack through the upper row of holes in the cable manager.
Procedure
l Install the cable manager on the cable rack that is not installed with a cable trough. Figure 6-30 shows the cable manager on the cable rack that is not installed with a cable trough. Figure 6-30 Cable manager on the cable rack that is not installed with a cable trough
Install the cable manager on the cable rack that is installed with a cable trough. Figure 6-31 shows the cable manager on the cable rack that is installed with a cable trough. Figure 6-31 Cable manager on the cable rack that is installed with a cable trough
----End
6-18 Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd Issue 01 (2008-04-30)
Procedure
l Install the bushing at the bottom edge of the cable trough, as shown in in Figure 6-32. All the exposed bottom edges of the cable troughs must be covered by bushings. Figure 6-32 Installing the end cover, bushing, and baffle ring
l l
Cover all the exposed ends, as shown in in Figure 6-32. If allowed, cover all the ends of the cable ladders. Mount the baffle rings onto both sides of the cable trough, as shown in in Figure 6-32. A cable trough requires four baffle rings. The baffle rings must be evenly mounted on both sides.
----End
Context
Figure 6-33 shows the grounding bar of the NodeB.
Issue 01 (2008-04-30)
6-19
(1) Bolt M8
NOTE
l l l
Install the indoor grounding bar on the wall close to the cabinet and at the same height as that of the cable rack. Mount the indoor grounding bar horizontally on the wall. Apply insulating pads to the expansion bolts to insulate the grounding bar from the wall.
Procedure
Step 1 Determine the installation position according to the engineering design. Step 2 Mount the indoor grounding bar horizontally on the wall by using expansion bolts, as shown in Figure 6-34 and Figure 6-35. Figure 6-34 Installing the grounding bar
6-20
Issue 01 (2008-04-30)
Step 3 Use PGND cables to connect the grounding bars of each equipment to the grounding busbar of the equipment room. ----End
Context
The requirements for the metal pole at the DBS3900 site are as follows:
l
The metal pole is at least 1800 mm and the diameter of the metal pole ranges from 60 mm to 114 mm. The base is made of steel frame and concrete block. The dimensions of the base are 630 mm x 430 mm x 120 mm. The jointing surface is coated with antirust paint. The jointing is firm and there is no dry or open weld. If the metal pole for the RRU is within the surge protection coverage of the antenna and connected properly with the grounding grid, no lightning rod is required on the top of the metal pole. If the metal pole for the RRU is not within the surge protection coverage of the antenna, a lightning rod is required on the top of the metal pole. The metal pole must be connected properly with the grounding grid.
NOTE
l l l
When the basic design requirements are met, the length of the metal pole and stay pole can be flexible, depending on the actual requirements.
Procedure
l Preparing a metal pole. Install the metal pole on the concrete floor of the rooftop, as shown in Figure 6-36.
Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd 6-21
Issue 01 (2008-04-30)
Prepare a metal pole and two stay poles. Figure 6-37 shows two stay poles with a metal pole. Figure 6-37 Two stay poles with a metal pole
The base is made of steel frame and concrete block, as shown in Figure 6-38.
6-22
Issue 01 (2008-04-30)
Prepare a stay pole and two metal poles. Figure 6-39 shows two metal poles with a stay pole. Figure 6-39 Two metal poles with a stay pole
The two metal poles are I-shaped with a one-meter-long beam in between and the stay pole helps to form a triangle support. ----End
Issue 01 (2008-04-30)
6-23
Issue 01 (2008-04-30)
7-1
The height of the tower depends on the field requirements of the NodeB. Typically, the tower has one to three platforms with round or hexagon structure. The minimum diameter of the circle is 4 m and the space between two platforms is 6 m. The guard rails on the platforms are 1 m high. The minimum bearing capacity of the platforms is 150 kg/m2. A ladder is installed on the tower for maintenance. The reinforcing angle steel is installed every 1 m on both sides of the ladder and the angle steel extends 0.5 m out of the ladder on either side.
Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd Issue 01 (2008-04-30)
7-2
A lightning rod is installed on the tower. The lightning rod is located 8 m above the upper platform to ensure that all the antennas are under the coverage of the lightning rod. In the strongest wind that occurs once every 30 years, the maximum axial wobble and torsion of the tower body is within 1. The tower is designed to resist one degree of seismic intensity over the limit stipulated in local regulations. When earthquake occurs, the tower can withstand the earthquake and devoid of any distortion that affects the quality of communication. A cable rack that can bear the weight of a person is installed on the tower. Surge protection and lightning induction devices are installed on the tower. Solar energy lamps are used for the tower.
l l l
Power cables with metal jackets are used for the aeronautical lights that use AC power. Ensure that the metal jackets are grounded at the top of the tower and at positions where the cables are led into the equipment room. Surge protection devices are installed on the control cables of the tower lamps and on the phase lines of the power cables at the positions where the cables are led into the equipment room. The neutral lines are directly grounded.
Context
Figure 7-2 shows the structure of the antenna support.
Issue 01 (2008-04-30)
7-3
When installing the antenna support on the tower, stick to the following principles:
l l
The installation plane of the antenna support must be perpendicular to the horizontal plane. The pole for the lightning rod must be installed separately on the tower. Ensure that the lightning rod is placed high enough so that all the antennas are within the protection area of 45 degree below the lightning rod. The antenna support must be installed correctly to ensure the receiving and transmitting performance and direction adjustment of the directional antenna. The rotating lever must be reinforced by using a stiffener. Length of the expansion lever and the rotating lever depends on the field situation. Ensure that the cut on each lever is soldered with a cover plate for waterproofing. Ensure that each part is securely soldered and there is no dry or open weld. The galvanized steel is preferred for making the support and the support must be coated with antirust paint.
Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd Issue 01 (2008-04-30)
7-4
Procedure
Step 1 Mount a fixed pulley at the top of the tower. Then use one or two ropes to hoist the support to the tower platform by using the pulley, and use another rope to maintain the rising direction of the support. Step 2 Determine the installation position of the antenna support on the tower according to the engineering design. Step 3 Hang the support out of the tower platform, and then secure the support on the tower by using a U-shaped fixing clip (including the connecting piece and the U bolt), as shown in Figure 7-3. Figure 7-3 Installing the antenna support on the tower
(3) U bolt
Step 4 Connect the guard rail on the tower platform with the connecting plate by using M12x45 bolts. If it is difficult to connect them, solder the two parts securely. ----End
Context
Typical Structure of the Antenna Support Installed on the Rooftop
l
Figure 7-4 shows the structure of the antenna support directly installed on the rooftop.
Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd 7-5
Issue 01 (2008-04-30)
Figure 7-4 Structure of the antenna support directly installed on the rooftop
(6) Support lever 2 (7) Base of the supporting (8) Stiffener anchor lever
If the antenna support cannot be directly installed on the rooftop that has parapet higher than 1,200 mm, you may use expansion bolt assemblies and fixing clips to secure the antenna support. Figure 7-5 shows an antenna support that is installed on the parapet. Figure 7-6 shows the methods for installing the fixing clip for the antenna support.
7-6
Issue 01 (2008-04-30)
Figure 7-5 Installing the antenna support on the parapet (height of the parapet > 1,200 mm)
Figure 7-6 Installing the fixing clip for the antenna support on the parapet
When the antenna support cannot be directly installed on the rooftop and the parapet is lower than 1,200 mm, you may secure one fixing point on the support lever to the parapet using an expansion bolt assembly and a fixing clip and secure the other fixing point on the rooftop. Figure 7-7 shows the antenna support installed on the parapet.
Issue 01 (2008-04-30)
7-7
Figure 7-7 Installing the antenna support on the parapet (height of the parapet < 1,200 mm)
When installing the antenna support on the rooftop, stick to the following principles:
l
The connecting pieces for the stiffeners are fixed in proper positions that do not affect adjustment of the antenna direction or downtilt. The installation plane of the antenna support must be vertical to the horizontal plane. When the directional antenna is installed on the rooftop, a lightning rod must be installed on the antenna support, and the support must be connected with the surge protection grid of the building. When the omnidirectional antenna is installed on the rooftop, the lightning rod is not installed on the same support as the omnidirectional antenna. Another support is required to install the lightning rod. If the lightning rod is installed on the support of the omnidirectional antenna, note that the antenna must stretch out of the support for 1 m to 1.5 m. All the soldered points on the antenna support are coated with antirust paint. Ensure that each part is securely soldered and there is no dry or open weld.
l l
Procedure
Step 1 Determine the installation position of the antenna support on the rooftop according to the engineering design. Step 2 Solder the lightning rod to the support lever with their centerlines aligned. Step 3 Use eight expansion bolts M10x45 to secure the base of the antenna support vertically on the rooftop, as shown in Figure 7-8.
7-8 Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd Issue 01 (2008-04-30)
(2) Connecting piece for the stiffener (5) Expansion bolt M10x45
Step 4 Use the connecting piece to link the stiffener and the support lever, and then install the stiffener anchors on the stiffeners. Ensure that each stiffener anchor is secured through two expansion bolts M10x45, as shown in Figure 7-4.
NOTE
Step 5 Use six expansion bolts M10x80 to connect the support lever 1 and the support lever 2, as shown in Figure 7-4. Step 6 If the antenna support on the rooftop is not soldered with the outdoor cable rack or if the antenna support is soldered with the cable rack that is not connected to the surge protection grid of the building, use a connecting plate to connect the base of the antenna support with the surge protection grid. Note that the connecting plate for surge protection is delivered with the outdoor cable rack. Step 7 Use antirust paint to coat all the soldered points and surface of the antenna support base. Step 8 Use concrete to reinforce the base of the antenna support on the rooftop, stiffener anchors, and the expansion bolts that connect the stiffener anchors and the rooftop. ----End
Issue 01 (2008-04-30)
7-9
Issue 01 (2008-04-30)
8-1
NOTE
When selecting the outdoor cables, check weatherproof performances of the cables in terms of low temperature bending, low temperature impact, stretching, thermal aging. The outdoor cables are usually coated with PVC jackets. If there are specific requirements for mechanical performances, use cables coated with PE jackets. Insulating materials and protection jackets of the cables must comply with the Restriction of Hazardous Substance (RoHS) requirements. The cable materials can either be customized or selected in compliance with local regulations.
l l
8-2
Issue 01 (2008-04-30)
NOTE
In the preceding table, D refers to the diameter of the cable jacket and R refers to the bending radius of the cable.
Cables of different types are bound separately. The cables cannot be coiled. The cables are tightly and neatly bundled. Ensure that the jackets of the cables are not damaged. Two adjacent cable ties are spaced 200 mm and face the same direction. The cable ties at the same position are placed at the same level. All cuts of the cable ties are smooth without sharp projections. Attach labels or nameplates to both ends of the cables after they are installed.
Cables of different types are routed separately. Cables of different types are not crossed. The space between cables of different types are greater than 30 mm when the cables are routed parallel inside the cabinet. The space between cables of different types are greater than 100 mm when the cables are routed parallel outside the cabinet. If such requirements cannot be met, If such requirements cannot be met, the cables must be separated with specified objects.
Issue 01 (2008-04-30)
8-3
The optical cables are routed in compliance with the engineering design and general cabling specifications. If the cable is not long enough, replace the cable. Do not add connectors or solder joints to lengthen the cable. The cables are insulated if they are bound to and routed on the metal cable rack. Fuses or switches are not allowed on the cables. The -48 V power cable and the GND cable are bound together. Both ends of the PGND cables are anti-corrosive and antirust. Connections of the PGND cables are secure. The low-voltage AC power cable for the NodeB is covered with a metallic conduit and buried in the ground for at least 50 m before they are led into the equipment room. Note that if such cables are shorter than 50 m, they must be completely buried in the ground. If such cables are routed overhead and led into the room, surge protection for the connectors of the AC power cables are affected. The PGND cables are buried in the ground or routed indoors. The PGND cables cannot be routed overhead before they are led into the equipment room.
l l l l
The optical cables are routed in compliance with the engineering design and general cabling specifications. The E1/T1 cables cannot be routed overhead outdoors. If the E1/T1 cables are routed outdoors, coat the E1/T1 cables with PVC jackets and route them underground based on the site conditions. If the E1/T1 cables routed outdoors are longer than 5 m, a surge protection box is required. The proper cable surpluses are reserved when the E1/T1 cables are curved. The idle wires of the E1/T1 cables are grounded properly in the equipment room.
l l
l l l
The optical cables are routed in compliance with the engineering design and general cabling specifications. Reserve proper cable surpluses where the optical cables are curved. Do not stretch, step, or place heavy objects on the optical cables. Keep the cables away from sharp objects to avoid damage. The optical cable that is curved or pressed or the optical connector which is damaged cannot be used. Extra optical cables are coiled on the specific device such as the fiber coiler. Coil extra optical cables properly. Do not bend the cables forcibly to avoid damaging the cables. Use protection tubes to coat the bare fibers. The idle connectors of the optical cables are covered with dustproof caps. If one end of the optical cable is connected to an optical device, do not look directly at the end face of the optical connector. Otherwise, you may damage your eyes. Fill soft materials such as fireproof cottons in the optical cable inlets at the top of the cabinet to protect the optical cables.
Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd Issue 01 (2008-04-30)
l l
l l l
8-4
You need to check whether the optical connectors are clean before installation. If the optical connectors are dirty, clean them by using the dustfree cloth or fiber cleaner.
Issue 01 (2008-04-30)
8-5
2.2.1 Space Requirements of the BBU3900 2.2.2 Space Requirements of the RRU and SRXU
300 mm under the RRU3804 for cabling 600 mm in front of the RRU3804 for maintenance 200 mm above the RRU3804 for maintenance 400 mm on the left of the RRU3804 for maintenance 100 mm on the right of the RRU3804 for maintenance
Issue 01 (2008-04-30)
9-1
Check Item
Requirement The floor of the equipment room is semiconductive and free from dust with a bearing capacity greater than 450 kg/m2 is required. Generally, the movable ESD floorboards are used. Lusterless paint or wallpaper can be used on the walls. Do not use the paint that chalks off easily. The EMI in the equipment room does not exceed 300 mV/m. The magnetic field intensity does not exceed 11 GS. The operating environment of the BBU3900 must meet the following requirements:
l l l
Reference Information
Temperature: -20 to+55 Relative humidity: 5% to 85% Absolute humidity: 1 g/m3 to 25 g/m3
The operating environment of the RRU must meet the following requirements:
l
Temperature: -40 to +50 (with 1120 W/ m3 solar radiation), -40 to +55 (without solar radiation) Relative humidity: 5% to 100% Absolute humidity: 1 g/m3 to 30 g/m3 3 Power Supply Requirements of the DBS3900
l l
When -48 V DC is used for the BBU3900, the operating voltage ranges from -38.4 DC V to -57 V DC. When -48 V DC is used for the RRU, the operating voltage ranges from -36 DC V to -57 V DC.
Transmissio n system
The connectors of the delivered transmission cables match those on the DDF/ODF on the transmission device side. The DDF/ODF is installed and external transmission cables are connected to the DDF/ ODF.
Grounding system
The grounding resistance is subject to the standard or regulation stipulated by the respective country or operator. Huawei recommends that the grounding resistance of the cabinet be smaller than 10 ohms.
9-2
Issue 01 (2008-04-30)
Check Item
Requirement The distance between the grounding bar and the copper-based wires is less than 30 m. The PGND cables are routed to the DC power distribution frame or the junction box. The PGND cables of all devices are connected to the same grounding busbar. The cross-sectional area of the PGND cables between the BBU3900 and the grounding bar is at least 6 mm2. Grounding clips are installed at an interval of 20 m on the feeder. The feeder is respectively grounded 0.5 m to 1 m away from the tower and the outdoor cable rack.
Reference Information
Auxiliary facilities
The cable rack and grounding bar are installed. The metal pole for installing the antenna system is at least 1,800 mm and the diameter of the metal pole ranges from 60 mm to 114 mm. The tower is installed and meets the requirement for azimuth of the antenna, bearing capacity, wind load, and quake proofing. A lightning rod is installed on the tower. The antenna support is securely installed and meets the requirements for the azimuth of the antenna and surge protection.
Antenna system
7.2 Installing the Antenna Support on the Tower 7.3 Installing the Antenna Support on the Rooftop 8.2 Cabling Specifications for the NodeB
Cables
The requirements for the bending radius of the feeders are as follows:
l l l l
1/2" feeder: 127 mm 7/8" feeder: 250 mm 5/4" feeder: 380 mm 13/8" feeder: 510 mm
The requirements for the bending radius of the jumpers are as follows:
l l
Bending radius of the power cables: three times the diameter of the power cable jacket Bending radius of the optical cables: 20 times the diameter of the optical cables
Issue 01 (2008-04-30)
9-3
Check Item
Requirement Cables of different types are not crossed. Labels or nameplates are attached to the cables after they are installed.
Reference Information
9-4
Issue 01 (2008-04-30)
Index
Index
A
antenna support installing on rooftop, 7-5 on tower, 7-3 outdoor cable material, 8-2 power supply, 3-1 site selection, 2-2 tower, 2-12, 7-2 transmission, 5-1
C
cable material, 8-2 cabling specification, 8-2 checklist site preparation, 9-1
S
site selection requirement, 2-2 space requirement, 2-4 specification cabling, 8-2
T
tower requirement, 7-2 transmission requirement, 5-1
G
grounding requirement, 4-1
I
installing antenna support on rooftop, 7-5 on tower, 7-3 baffle ring, 6-19 bushing, 6-19 cable ladder, 6-8, 6-9, 6-9, 6-10, 6-11 cable manager, 6-17 cable trough, 6-13, 6-13, 6-14, 6-15 end cover, 6-19 grounding bar, 6-19 outdoor cable rack, 6-5, 6-6
W
working environment requirement, 2-13
P
power supply requirement, 3-1 preparing metal pole, 6-21
R
requirement equipment room, 2-10 grounding, 4-1
Issue 01 (2008-04-30) Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd i-1