2 Part 1 CASE STUDY 2 3

WBS Element Description


WBS Element Title: WBS Element No:

Extraction Steim System

Parent WBS No: Parent WBS Title: Project:

6.1 Steam System


Originator:

WBS Level:
4

600 MW Fossil Unit

D. Mitchell

WBS Element Description: The scope of this element includes all engineering and design effort required for the development of the extraction steam system.

Revision No: Revision Date:

Page 1 4 Of 27

WBS Element No:


6.1.4

Example 1

WBS Element Description


WBS Elenient Title: . .
Extraction Steam System

WBS Element No:

Parent WBS No: Parent WBS Title: Project:

6.1 Steam System

WBS Level:
4

Originator:
600 MW Fossil Unit

J. Jones

WBS Element Description:

The scope of this element includes all engineering work related

to piping systems, mechamcal equipment, electrical power, instrumentation and control for the extraction steam system. This includes determination of design pressures and temperatures, pipe sizes, wall thickness, plpe material, insulationrequirements, pipe supports, and control schemes. The scope of this element includes all supporting studies and calculations used in determination of the previously mentioned design definition.

Related Work Excluded


1. Associated supervision (included in WBS Element 3.16) 2. System Design Review (included in WBS Element 3.20)

3. Engineering input to schedule logic development (included in WBS Element 4.11)

Revision No: Revision Date:

Page 1 4 Of 27

WBS Element No:


6.1.4

Example 2

64 Part 1 CASE STUDY 2.3

WBS Element Description


WBS Element Title:
Extraction Steam System

WBS Element No:


6.1.4

Parent WBS No: Parent WBS Title:

6.1 Steam System

WBS Level:
4

1
600 MW Fossil Unit
I

originator:

A. Thompson

WBS Element Description: The scope of this element includes the engineering and deslgn effort for
the extraction steam system, as defined in the control element work products defined below. Svstem Descriotions SDlOl Extraction Steam Procurement Packages None Drawings Control Logic Diagram C L D l O l Extraction Line Control, LP and HP Heaters Control Logic Diagram CLD102 - Extraction Line Control, Deaerator P&ID101 - Extraction Steam Electrical Elementary Diagram EED 101 -Extraction Line Control, LP and HP Heaters Electrical Elementary Diagram EED102 -Extraction Line Control, Deaerator Piping Drawing PDlOl - First, Second & Third Point Extraction Steam Piping Piping Drawing PD102 Fourth & Fifth Point Extraction Steam Piping Piping Isometric PI101 -First, Second & Third Point Extraction steam Isometric Piping Isometric PI102 -Fourth & Fifth Point Extraction Steam Isometric Pipe Supports PS101 - Supports for First, Second &Third Point Extraction Steam Piping Pipe Suppoa PSI02 - Supports for Fourth & Fifth Extraction Steam Piping Calculations Pressure drops for Extraction Steam Lines Related Work Excluded 1. Associated supervision (included in WBS Element 3.16) 2. System Design Review (included in WBS Element 3.20) 3 . Engineering input to schedule logic development and review (included in WBS Element 4.11)
-

Revision No: Revision Date:

Page 1 4 Of 27

WBS Element No:


6.1.4

Example 3

66 Part 1 CASE STUDY 2.3

1 WBS Element Title:


Extraction Steam System

WBS Element Description

I WBS Element No:

Parent WSS No: Parent WSS Title: Project:

6.1 Steam System

WBS Level:
4

Originator:
600 MW Fossil Unit
R. Smith

WBS Element Description: The scope of this element includes the engineering and design effort for the extraction steam system, as defined in the WBS element work products defmed below.

I System Descriptions

- 1,

estimated 50 pages long

Pmcurement Packages - 0

Drawings - 73 sheets, as broken down below; 15 sheets control logic diagrams 2 sheet P t I D 21 sheets elementav wiring diagram 26 sheets piping drawings 5 sheets piping isometrics 4 sheets pipe support drawings

Revision No: Revision Date: