ER288 090714 5082 CV OKP (089) Method Statement For Plate Baring Test
ER288 090714 5082 CV OKP (089) Method Statement For Plate Baring Test
14th Jul 2009 Officer-in-Charge Land Transport Authority 1 Hampshire Road Singapore 219428 Attn : Mr Lau Hwa Cheong/ Mr Tan Peng Heng Dear Sirs, CONTRACT NO. : ER288QP PROJECT TITLE: QUALIFIED PERSON (SUPERVISION) SERVICES FOR CONTRACT ER288 WIDENING OF CTE FROM PIE TO BRADDELL INTERCHANGE
Re: OKP (089)-Method Statement for Plate Bearing Test
1.
2. The above submission is accepted with comments, as detailed in Annex A. 3. The contractor should resubmit, incorporating response to the comments. Thank you Yours faithfully,
Vashdev A Khialani QP(Supervision), ER288QP C.C: LTA - Mr Ang Pui Boon (PO) - Mr Kuek Chin Meng (PO) Attachment: Annex A (Total No. of Pages including cover letter: 3)
Annex A
Comment Codes 1 = Minor Importance 2 = Moderate Importance 3 = Major Importance
CONTRACT ER288 QUALIFIED PERSON (SUPERVISION) SERVICES FOR CONTRACT ER288 WIDENING OF CTE FROM PIE TO BRADDELL INTERCHANGE
DOCUMENT REVIEW
Transmittal No: OKP/ER288/LTA/09-089 Transmittal Date: Subject: Method Statement for Plate Bearing Test Review Department QP (Supervision) Date Received No. Document/Drawing Comments No. 1 General
Code 1 2 2 2 2 2 2 2
1) Please provide document control form on cover page, indicate revision, person to prepare, person to approve, date etc. 2) Please provide design check for reference beams and endorsed by PE. 3) Please provide the equipment brochure with certificate. 4) Please provide the LG certificates. 5) Please submit the layout sketch to show setting out of testing equipment. 6) Please provide the excavator operators license, certificates of lifting supervisor, signal man, rigger etc. 7) Please provide the reference drawing (D/ER288/CS/RETW/0001). 1) Please notice that total counter weight should be at least 10% greater than the anticipated maximum test load. (BS 1377 Part 9: 1990 Standards) 1) Please select test location and depth at or adjacent to the location where the real foundation will be constructed, if possible. If the test is performed in a test pit, the width of the pit should be at least 4 to 5 times of plate diameter. 1) More details work activities such as mobilization and demobilization, Lifting operation etc should be considered in risk assessment for plate baring test.
Method Statement Item II. Apparatus Method Statement Item III. Procedure
Risk Assessment
1. Accepted
Overall Acceptance Status Please Cross (x) one box 2. Accepted with comments x 3. Noted with comment
4. Rejected
The above comments do not relieve the contractor of his contractual obligations. The submission is a) Accepted with comments; b) Please resubmit, incorporating response to the above comments.