GS EP EXP 217 en 00
GS EP EXP 217 en 00
00 Rev.
10/08 Date
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Contents
1. Scope ....................................................................................................................... 3 2. Reference documents............................................................................................. 3 3. Terms and abbreviations........................................................................................ 4 4. Spare Parts definition ............................................................................................. 6
4.1 4.2 4.3 Commissioning & Start-up spare parts ..............................................................................6 Capital Spare parts ............................................................................................................6 Operating Spare Parts (refer to section 1.Scope)..............................................................6
6. EPC scope ............................................................................................................... 8 7. MIEC role.................................................................................................................. 8 8. COMPANY role ........................................................................................................ 8 9. Spare Parts dossiers............................................................................................... 9
9.1 9.2 9.3 9.4 9.5 9.6 9.7 9.8 9.9 Preliminary dossier ............................................................................................................9 Section 1 - Identification of VENDOR or SUPPLIERS' commercial references.................9 Section 2 - Commercial terms ...........................................................................................9 Section 3 - Spare Parts documents .................................................................................10 Section 4 - Spare Parts preservation...............................................................................10 Section 5 - Documentation ..............................................................................................10 Section 6 - Additional information ....................................................................................10 Quality Control (EPC, MIEC Contractor, COMPANY) .....................................................11 Final dossier ....................................................................................................................11
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 2/13
1. Scope
The scope of this specification is to provide VENDOR or SUPPLIER with the required method to define all the Operating Spare Parts comprising: Stored Spare Parts to be described and referenced in both CMIMS and MM module, purchased and delivered, as initial stock, to the Subsidiary, Non Stored Spare Parts, not purchased as initial stock but described and referenced in both CMIMS and MM module. The operational objectives pursued are: To have, as initial stock, all Stored Spare Parts stored in the Subsidiary Warehouse(s), before the start-up of the relevant installations, To get all the Operating Spare Parts (Stored Spare Parts and Non Stored Spare Parts) described and referenced in both CMIMS and MM module, in order to easily allow their procurement and/or replenishment at any time during the life time of the installations. VENDOR or SUPPLIER are requested to provide COMPANY with complete Spare Parts Dossiers including Spare Parts lists in order that a) and b) lists be established.
2. Reference documents
The reference documents listed below form an integral part of this General Specification. Unless otherwise stipulated, the applicable version of these documents, including relevant appendices and supplements, is the latest revision published at the EFFECTIVE DATE of the CONTRACT. Standards Reference Not applicable Title
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 3/13
Total General Specifications Reference GS EP EXP 203 GS EP EXP 205 GS EP EXP 207 Operations preparation Inspection documentation Title during project: Maintenance and
Bill Of Material Call For Tender Computerized Maintenance & Inspection Management System (name of the Affiliates CMIMS) TOTAL E&P subsidiary Contractor directly contracted by COMPANY Party acting as representative of the COMPANY Equipment List Generic term for Engineering Procurement and Construction contract It covers different types of contracts: EPSCC, EPCC, etc Project Group or Integrated Project Group The smallest element in a spare parts list (items in different spare parts lists can get the same Material Master code assuming they are identical)
Item
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 4/13
LLI MANUFACTURER
Long Lead Items (pieces of equipment with a long delivery time) Manufacturer of a piece of equipment (or sub-equipment) Material Master (set of descriptive data of one spare part).
MatM MIE (Maintenance & Inspection Engineering) MIEC MIEC Contractor MM module MM Module Quality Control Team MRP OEM PM module PO PR ML SPF SPF-E SPF-R SPL SPL-E SPLR SUPPLIER SUBCONTRACTOR Template MM VENDOR
1 spare part = 1 "MatM" with a SAP/r3 number Activity related to the realisation of the maintenance & inspection engineering preparation, including spare parts dossiers Contract or change order for the performances of the maintenance & inspection engineering activities Party to whom has been awarded the MIEC (either a CONTRACTOR of COMPANY or a SUBCONTRACTOR of the EPC) Material Management module of SAP/r3 COMPANYs team in charge of the quality control of the Material Management data Material Requirement Planning: used for managing stock reordering Original Equipment Manufacturer see section 4.3.1 Plant Management module of SAP/r3 Purchase Order Purchase Request MANUFACTURER List Spare Parts File SPF consists in a list of one or several SPLs Spare Parts File grouping by main equipment Spare Parts File grouping by SUPPLIER Spare Parts List Spare Parts List by main equipment Spare Parts List grouping by MANUFACTURER/ SUPPLIER Supplier of COMPANY (LLI, Company Items) Contractor contracted by CONTRACTORS Template used to load Material Management data into the MM module Supplier of EPC or CONTRACTORS
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 5/13
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 6/13
4.3.5 Critical Spare parts (including Insurance spare parts) Spare Parts not already listed as Capital Spare Parts, not subject to wear (but considered as strategic), of random consumption and maintained in stock for operational or safety reasons, or which failure may have heavy financial consequences.
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 7/13
5.1.3 Package no.3 - Operating Spare Parts In addition to package no.1 and no.2, VENDOR or SUPPLIER shall submit with its proposal a detailed Spare Parts List with prices and revision formula for the Operating Spare Parts: Stored Spare Parts to be described and referenced in both CMIMS and MM module, purchased and delivered, as initial stock, to the Subsidiary Non Stored Spare Parts, not purchased as initial stock but described and referenced in both CMIMS and MM module. Remark: VENDOR or SUPPLIER will propose as well complete Spare pieces of equipment (cf. 4.3.3). For those that are repairable, VENDOR or SUPPLIER will in addition propose the required spare parts and specific tooling to carry out those repairs (Those parts will be listed on a SPL-E following the relevant equipment). The spare parts included within the packages no.2 and no.3 shall NOT take into account the quantity proposed in package no.1.
6. EPC scope
All the equipment PO issued by EPC shall include the GS EP EXP 217 to describe the scope of VENDORS and/or SUPPLIERS. In particular, each PO shall describe that the preliminary spare parts dossier is to be transmitted to EPC within 10 weeks after the equipment PO. EPC shall ensure that his VENDORS and/or SUPPLIERS have fully understood the spare parts requirements. EPC shall recover and check/update as required the spare parts dossiers received from VENDORS or SUPPLIERS as per the workflow. EPC shall return to his VENDORS and/or SUPPLIERS the comments made by the MIEC contractor and the COMPANY representative as per the workflow. This process can be repeated several times as long as the spare parts dossiers are not validated by the MIEC contractor and the COMPANY representative. Once the spare parts dossiers are validated by the MIEC contractor and the COMPANY representative, EPC is responsible to issue the final spare parts dossiers provided by his VENDORS and/or SUPPLIERS.
7. MIEC role
MIEC Contractor is in charge to check that the Spare Parts dossiers have been issued by EPCS for all individual pieces of equipment, and to complete and update them as required. For that purpose MIEC Contractor shall contact EPCS, VENDORS, SUPPLIERS as necessary to collect the missing information.
8. COMPANY role
The COMPANY representative is responsible to validate the final Spare Parts dossiers. Refer to the Spare Parts dossiers workflow chapter 10.
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 8/13
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 9/13
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 10/13
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 11/13
Receipt of Tenders
EPC
VENDORS
PO including the GS EP EXP 217
Tenders
VENDORS
EPC
NO
MIEC Contractor
Company Representative
(1) Spare parts dossier to be considered at different steps: 1- preliminary dossier (first issue) 2- updated dossiers 3- final dossier
NO
YES
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 12/13
Appendix
1 to 6
The responsibilities to fill in the Spare Parts documents (appendices 1 to 6) are described below and on each appendix in the Excel file. Appendices 1 to 3: VENDOR or SUPPLIER and EPC Appendices 4 to 6: MIEC Contractor. They are transmitted for information to VENDOR or SUPPLIER no. Type of document Information Source Info provided by VENDOR or SUPPLIER VENDOR or SUPPLIER VENDOR or SUPPLIER SPF-E, SPLE, ML SPF-E, SPLE, ML SPF-E, SPLE, ML Document prepared by VENDOR or SUPPLIER VENDOR or SUPPLIER VENDOR or SUPPLIER MIEC Contractor MIEC Contractor MIEC Contractor Document reviewed for quality control by EPC EPC EPC MIEC Contractor MIEC Contractor MIEC Contractor Final review by MIEC Contractor MIEC Contractor MIEC Contractor Company Representative Company Representative Company Representative Decision for approval Company Representative Company Representative Company Representative Company Representative Company Representative Company Representative
1 2 3 4 5 6
Calculation_sheet_GS_EP_EXP_217_En_00.xls
This document is the property of Total. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Page 13/13