Project: Associated Equipment: - AHU - Thru - CHWP - Thru - VFD For CHWP - B-T Station - (
Project: Associated Equipment: - AHU - Thru - CHWP - Thru - VFD For CHWP - B-T Station - (
- _____ thru ______ ____CHWP - ____ thru ____ ____VFD for CHWP _______ ____B-T Station _______ [_________________ ]
Related Tests: ______________________________________ Project No:_________
1.
Participants
Name Firm Participation
Party filling out this form & witnessing _____________________ Date of test _________
Approvals. This filled-out checklist has been reviewed. Its completion is approved. Exceptions are noted below or attached. ___________________________________ General Contractor [Construction Manager] _________________________ Commissioning Authority/Agent __________ Date __________ Date ____________________ Owners Representative __________ Date
2.
Prerequisite Checklist a) The prefunctional checklist for the pump(s) is complete and approved: Yes / No b) The prefunctional checklist for the piping is complete and approved: Yes / No c) The prefunctional checklist for the associated Bridge-Tender station is complete and
approved: systems connected: e) TAB report provided: f) All A/E punchlist items for this and related equipment are corrected:
FUNCTIONAL TEST CHECKLIST CHILLED WATER SYSTEM 15998-06-1 OF 4
d) Testing, Adjusting and Balancing (TAB) completed and approved for the hydronic and air
03/02
D:\DOCS\DIV1\03-02\15998-06.DOC
FUNCTIONAL TEST CHECKLIST Chilled Water System (Chwsys) - ____________ g) Functional testing is complete and approved for the variable frequency drive for the
pump(s): N/A / Yes h) Functional testing is complete and approved for the air handling units of this system: N/A / Yes i) Sequence of operation is attached: Yes j) Design setpoint information included on forms: Yes k) Controls: i) DDC loops operational, temperature/pressure setpoints met without hunting:Yes ii) Master transmission diagram is updated on device graph: Yes iii) Graphic programming is complete and operational: Yes iv) System communicates with mainframe: Yes v) Bridge-Tender is set to design/final setpoints: N/A / Yes vi) Local reading of setpoints agree with remote readings: Yes / No / No / No / No / / / / / / No No No No No No
3. a.
Step 1
HOA Operation
HOA in Auto position. Pump and Bridge-Tender Verification: AHU supply air (SA) discharge setpoints at initial value 55F as a group. Through BMS raise/lower setpoints per schedule record table. HOA in Auto position. Move HOA switch to Off position for all pumps. Command P-1 On with HOA switch. Command P-1 Off with HOA switch. Repeat for all pumps. Reset pump, P-1, HOA switch to Auto, after start, place remaining pumps in Auto position. HOA in Auto position. Pump, P1, commanded Off by BMS,
03/02
D:\DOCS\DIV1\03-02\15998-06.DOC
HOA in Auto position. Pump and Bridge-Tender Verification: AHU supply air (SA) discharge setpoints at initial value 55F as a group. Through BMS raise/lower setpoints per schedule record table. HOA in Auto position. Pump, P2, local disconnect moved to Off position (simulating power failure to pump, P-2). After pump, P-1, starts, restore power to pump, P-2.
b.
Step 1 2 3
HOA Operation
All pumps turned Off by HOA switches. P-1 turns On. When commanded by HOA switch, all other pumps turn On. After reset of pump, P-1, to Auto, P-1 starts. All other pumps remain Off.
Verify by visual inspection that pump, P2, is On, other pumps are Off.
03/02
D:\DOCS\DIV1\03-02\15998-06.DOC
Pump, P-2, is Off. Pump, P-1, starts automatically. Pump, P-1, continues to run, pump, P-2, remains Off.
Comments:
-- END OF SECTION --