Download as pdf or txt
Download as pdf or txt
You are on page 1of 26

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK Contractor Management 01/01/05

3.02-ADM-001 Revision: 1 Page i of 26

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK

3.02ADM001

Page ii of 26

Table of Contents
Introduction Purpose Company Contracts Site Specific Safety Requirements Safety is a Condition of the Contract Not an Exhaustive List and Not Legal Advice Policy Safety Rules Warning Signs Tools and Equipment Housekeeping Safe Work Practices Contractor Supervisions Responsibilities Contractor Personnels Responsibilities Safety Procedures Accident Reporting Emergency Procedures Evacuation and Alarm Procedures Evacuation Procedures OSHA Inspections Process Safety Management Safety Meetings Stop Work Guidelines Barricades and Traffic Control Erection of Barricades Types Hole Covers Traffic Control Flagging Blinding of Piping and Equipment Blinding Procedures Color Coding and Signs Compressed Cylinders Storage and Use Confined Space Electrical Safety Qualified Personnel General Fire Protection and Prevention Flammable and Combustible Liquids Handling and Storage of Flammable and Combustible Liquids Hazardous Material Safety and Spill Control Hoisting and Crane Operation Hot Work Permits Ladders Lockout and Tagout 1 1 1 1 1 1 1 1 2 2 2 2 2 3 3 3 3 4 4 4 4 5 5 5 5 6 6 6 6 6 6 7 7 7 8 8 9 9 10 10 10 10 12 12 13

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK

3.02ADM001

Page iii of 26

Personal Health and Safety Protection Introduction Clothing Hearing Protection Head Protection Foot Protection Hand Protection Eye and Face Protection Respiratory Protection Fall Protection Power-Activated Hand Tools Scaffolds Trenching and Excavation Vehicle Safety General MV Operating Safety Procedures Transportation Refueling Welding and Cutting General Welding Electrical Other Practices Asbestos-Containing Materials (ACM) Handling Lead in Construction Radiation Safety Industrial Radiography Waste Management Worksheets Site Specific Personnel/Emergency Information Emergency Information (Phone Numbers) Notes

14 14 14 14 14 14 15 15 15 15 16 16 17 17 17 17 18 18 18 18 18 19 19 19 19 19 20 21 21 22 22

Naturally Occurring Radioactive Material (NORM) 19

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK

3.02ADM001

Page 1 of 26

INTRODUCTION Safety is very important to all of the Companies that are a part of Magellan Midstream Partners, L.P. (Company). It is important that all Contractors understand how each task is to be done in a safe manner and that Contractors, who are unsure, STOP AND ASK before they begin work. Contractor safety, along with the safety of the Contractors personnel and subcontractors can be accomplished only through the Contractors and Companys committed efforts to safety. PURPOSE
The Contractor Environmental, Health & Safety Reference Handbook has been prepared to provide Contractor personnel with a quick reference of environmental, health and safety requirements that are generally applicable throughout Magellan Midstream Partners, L.P.

COMPANY CONTRACTS
Each Contractors Contract with the Company controls the Contractors legal obligations. The provisions in this Handbook may supplement the provisions in the Contract between the Contractor and the Company. In the event of a conflict between the Contract and the general guidelines in this Handbook, the Contract between the Contractor and the Company will govern the interpretation of the Contractors responsibilities to the Company.

SITE-SPECIFIC SAFETY REQUIREMENTS In addition to the guidelines in this Handbook, applicable Local, State and/or Federal rules and regulations, and the Contractual requirements, there may also be site-specific safety requirements the Contractor shall follow to perform the work safely. If work is occurring at an operating facility, that facilitys safety standard shall be determined and followed. In addition, if work is being conducted on a DOT asset and is deemed to be a Covered Task, the Contractor must have qualified personnel perform the task. Contractors are responsible for determining if there are site-specific safety requirements and complying with them. SAFETY IS A CONDITION OF THE CONTRACT
Your safety is not an option. The failure of any Contractor to perform work in a safe manner is grounds for termination.

NOT AN EXHAUSTIVE LIST AND NOT LEGAL ADVICE


Although this Handbook contains a variety of useful safety information to help increase the Contractors awareness of safety practices, it is not an exhaustive list of all safety requirements that may be required to perform the work safely. Each Contractor shall determine the safety requirements for his or her particular work.

It is not appropriate to take the position that if it is not in the Handbook, then it must not apply to the Contractors work. This Handbook is also not intended to serve as legal advice on the interpretation of statutes or regulations and shall not be relied on by the Contractor for that purpose. POLICY
Contractors are responsible for their own health and safety programs and shall abide by the applicable Local, State and/or Federal rules and regulations, including applicable Company policies and procedures as stated in the Contract between the Contractor and the Company. The management personnel working for the Contractor (Contractor Supervision) shall ensure that all personnel working for the contractor, including sub-contractors, are informed of and understand all Environmental, Health and Safety rules, precautions and requirements pertaining to the work and shall ensure they operate in compliance with such requirements.

SAFETY RULES

The construction environment includes heavy equipment operation, moving vehicles, welding operations, side booms, cranes, excavations, elevated platforms, tie-ins, dust, mud, etc. All of these conditions provide potential hazards to personnel. Horseplay on the job shall not be tolerated. Keep safety devices operative.

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK Possession of firearms or other weapons is prohibited. Stay clear of suspended loads and overhead power lines. Store and label materials properly.

3.02ADM001

Page 2 of 26

There is no smoking on Magellan property except in designated areas. Use the right tool for the job.

WARNING SIGNS
Signs are for informing personnel of potential hazards and, therefore, must be obeyed. Signs are not a substitute for education, training or proper planning. If you do not understand a sign, ask your supervisor.

TOOLS AND EQUIPMENT


Contractor tools and equipment shall be in good condition and meet regulatory and functional requirements. The Company reserves the right to restrict entrance or to remove any equipment or materials that are in an unsafe condition or are not in compliance with regulations. The use of Company equipment is not permitted.

HOUSEKEEPING
Housekeeping is defined as the arrangement of operations, tools, equipment, materials and supplies in an orderly manner that is conducive to the safety of personnel and the protection of property. Good housekeeping is essential to safe operations. Work areas shall be kept clean and free from obstructions. Recognize that the work area, including exits, aisle space and emergency equipment shall be kept clear of all obstructions. Parking vehicles or storing equipment in the path of exits is forbidden. Do not obstruct stairways, aisles or passageways. Keep equipment rooms clean at all times and do not use them as storage areas. Keep all floor surfaces clean and dry. Spilled oil, material or liquids on floors or walkways shall be promptly cleaned or removed. Be sure to post Caution or Wet Floor signs as needed. Remove signs when no longer required.

SAFE WORK PRACTICES


When working, the following safety precautions can be taken to protect personnel against the unplanned or unexpected: Receive authorization from location for all hot work activities or post a log in an area where personnel gather so that all work groups will know what is happening. Watch for and report any vapors. Do not walk or drive through vapors. Know where your co-workers are and consider body positions if working in an area where a blowout could occur or excess pressure could be vented.

CONTRACTOR SUPERVISIONS RESPONSIBILITIES


Contractor Supervision shall ensure compliance with all applicable rules, regulations, orders, standards and interpretations promulgated under the Occupational Safety and Health Act (1997) and all other applicable laws, ordinances, rules, regulations and orders of any public body having jurisdiction over the safety and health of persons or property or the protection of same to protect them from injury, illness, damage or loss. Contractor Supervision shall designate a trained safety representative within its organization to communicate and enforce all safety, health and accident prevention procedures on all major projects. The Company recommends that the contractor designate a trained safety representative on all projects. Contractor Supervision shall ensure all contract personnel are trained to do the required job tasks. Contractors are required to provide safety and site orientation to all of their personnel and sub-contractors. Written documentation shall be provided to the Company Representative. The contractor is responsible for providing safety instruction and encouraging safe work performance to all personnel under contractor supervision, for example, through prejob/new hire safety orientations and frequent safety and daily tailgate meetings. The contractor will use the appropriate work permits, hot work permits, confined space permits, etc. as required. The contractor is responsible for the repair and/or replacement of all equipment, machines and protective equipment found to be defective that may be a potential cause of injury. All contractor personnel must be informed of the proper personal protective equipment required for their assigned job task and trained in the use and care of that equipment. Contractors should consult the Safety Representative and/or the Workplace Hazard Assessment at each

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK facility for PPE information.

3.02ADM001

Page 3 of 26

All accidents and near misses must be reported to location management, investigated and documented in an accident report. Contractor Supervision shall support and enforce the Company's standards, policies and procedures for maintaining a drug-free and alcoholfree workplace. Contractor Supervision shall ensure all contractor personnel understand their responsibilities as outlined in this handbook. Contractor Supervision shall be primarily responsible to evacuate and protect all personnel when necessary. Contractor Supervision shall ensure proper medical care for their personnel.

CONTRACTOR PERSONNELS RESPONSIBILITIES


Contractor personnel are responsible for their own safety. Contractor personnel are responsible for reporting unsafe acts and conditions. Contractor personnel are required to abide by all safety rules and regulations. Understand your job task instructions. If you do not understand the assigned job task, ask your supervisor for clarification. All contractor personnel must use the proper personal protective equipment required for their assigned job task and trained in the use and care of that equipment. Observe all posted warning signs. All personnel are required to practice good housekeeping on the job site. Know the substances you work with that may be hazardous or potentially hazardous and review the Material Safety Data Sheets (MSDS). Possession and use of intoxicating beverages or illegal drugs shall not be tolerated. Inform your supervisor if you are using any medication that may affect your job performance. There is no smoking on any Magellan property or in any Magellan vehicle except in designated smoking areas.

SAFETY PROCEDURES ACCIDENT REPORTING

Contractor Supervision shall: Verbally notify Company Inspector or Company Representative as soon as possible after the accident; Provide a copy of the accident report to the Company Inspector or Company Representative as directed by the Company; and Investigate all accidents, complete applicable accident reporting forms and implement corrective measures as required and directed by the Company.

EMERGENCY PROCEDURES

The Contractor Supervision and Company Representative shall develop an emergency plan for each construction site to include:

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK

3.02ADM001

Page 4 of 26

Emergency call sequence and action plan Designation of a central assembly area in case of evacuation and/or emergency Securing emergency site Company personnel shall be responsible for designating a media relations spokesperson.
A review of potential emergencies and the emergency plan shall be communicated to all contractor personnel by the contractors.

EVACUATION AND ALARM PROCEDURES

EVACUATION PROCEDURES
Upon identification of an emergency evacuation situation, sound an alarm. Contractor Supervision shall ensure that each person recognizes and understands the significance of each alarm. Upon hearing an emergency evacuation alarm, all personnel and contractors shall quickly evacuate to an area of safety and/or a designated assembly area. The Contractor Supervision shall account for all personnel in the area of evacuation. They shall recount other additional relevant information to the Company Inspector or Representative at the assembly area.

OSHA INSPECTIONS

OSHA inspections may occur during the project. OSHA inspectors do not always schedule inspections; they may arrive at the construction site unannounced. If an OSHA inspector arrives at your location: Be courteous and cooperative Immediately notify Magellan Supervisor or Delegate, and then Immediately notify Contractor Supervision and Company Representative.

PROCESS SAFETY MANAGEMENT (PSM)


It is important that Contractors performing maintenance, repairs or other construction work in or adjacent to facilities covered under OSHAs Process Safety Management (PSM) regulations (29 CFR 1910.119) be fully aware of their specific responsibilities as specified in this CFR and PSM procedure. If the Contractor observes a security incident within or around the Facility, the incident must be reported to Magellan personnel immediately. If the Facility is unmanned at the time, the Contractor should immediately call 9-1-1 and then notify Magellan On-Call personnel.

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK

3.02ADM001

Page 5 of 26

SAFETY MEETINGS

Contractor Supervision and Company Inspectors or Representatives shall conduct and document regularly scheduled meetings (e.g., daily tailgate meetings, weekly or monthly safety meetings, etc.) Note: The frequency of the meetings may vary depending on the scope of the work and contract terms. These meetings provide a forum for the Company and the Contractor to discuss site-specific safety hazards, safety issues and methods of improving safety. Attendance at the meetings is mandatory unless the Contractor Supervision, Company Inspector or Company Representative gives prior approval. Attendance must be documented and a copy provided to the Company Inspector or Company Representative.

"STOP WORK GUIDELINES

Stop Work Orders are issued when Contractor Safety nonconformance could result in a potential fire or explosion, toxic release, personnel injury or death. All personnel at the work site are authorized to issue a Stop Work Order. The work in progress is placed in a safe stop condition until the Stop Work Order is released. Company Supervision and contract personnel are advised immediately of all Stop Work Orders. Stop Work Orders are released by the Company originator when corrective actions have been completed. The Area Safety Representative (SR) will perform random, documented on-site Contractor Inspections annually using the Contractor Inspection Checklist. The SR will immediately stop work, document and discuss with the Contractors Representative any observed condition that could be Immediately Dangerous to Life or Health (IDLH) and develop a remedial plan for each of these deficiencies using the Work Site Inspection Action Log that is located in the Contractor Inspection Checklist. The SR will require the Contractor to produce a remedial action plan for all remaining deficiencies using the Work Site Inspection Action Log that is located in the Contractor Inspection Checklist within 10 days of discovery. Lastly, the SR will forward inspection findings and remedial action plans per distribution list on Work Site Inspection Action Log that is located in the Contractor Inspection Checklist within 10 days of completion. Contractors with substantially deficient conditions will be removed from the Preferred Contractor List until corrective action has occurred.

BARRICADES AND TRAFFIC CONTROL


Anyone who makes an excavation, hole or opening is responsible for having it barricaded. Barricades are required around most excavations, holes or openings in floor or roof areas, edges of roofs and elevated platforms, around certain types of overhead work, pipeline excavations, hazardous areas where ignition sources could cause an explosion or fire, and wherever necessary to warn people against falling in, through or off. Barricades and/or guard services shall be employed in highly populated areas, school grounds, residential areas, etc., to keep people out of excavations and off equipment, pipeline or materials.

ERECTION OF BARRICADES
Barricades shall be 42 inches high and encompass the area of concern. Erect barricades before the hole is cut and extend them as the excavation progresses. Numerous excavations in one area may be barricaded effectively by erecting a barricade around the general area. Blinking lights shall be used on roadblocks and other pathways after dark.

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK Leave an entrance, opening or gate where practical.

3.02ADM001

Page 6 of 26

TYPES WARNING - Calls attention to a hazard but offers no physical protection. Example: Yellow synthetic tape on galvanized stands or posts. PROTECTIVE - Warn as well as provide physical protection from falling. Example: Wood post and rail, fencing, chain and/or cable. HOLE COVERS
All holes or openings through floors or decking at all elevations shall be secured with hole covers or barricades immediately. Do not store material or equipment on a hole cover.

TRAFFIC CONTROL
Construction areas shall be posted with legible traffic signs at points of hazard. Personnel in roadways shall wear reflective vests to heighten their visibility while in hazard areas. All traffic control signs or devices used for protection of construction workers shall conform to and be set up according to American National Standards Institute D6.1-1988, Manual on Uniform Traffic Control Devices for Streets and Highways.

FLAGGING
When operations are such that signs, signals and barricades do not provide the necessary protection on or adjacent to a highway or street, certified flaggers or other appropriate traffic controls shall be provided. Signaling directions by flaggers shall conform to American National Standards Institute (ANSI) D6.1-9 (most recent edition) Manual on Uniform Traffic Control Devices for Streets and Highways. Poorly maintained, defaced, damaged or dirty construction signs are ineffective and shall be replaced, repaired or cleaned without delay. All personnel engaged in the practice of flagging shall be dressed as follows to promote high visibility when approached by oncoming motorists:

High visibility vest Warning garments worn at night shall be of reflective material Stop and Slow sign paddles designed in accordance with ANSI D6.1 (most recent edition)
When hand signaling is done in periods of darkness, the sign paddles must be reflective or illuminated.

BLINDING OF PIPING AND EQUIPMENT


A blind is a metal plate that is bolted to the end of a pipe or is inserted between gasket pipe flanges to prevent the flow of gas or liquid in either direction. A blind shall be of sufficient rating strength to withstand the pressure to which it may be subjected. Blind spacers, commonly called spectacles, incorporate both a blind and a spacer and are frequently installed in a flange as a permanent part of the line. The blind spacer is manually rotated from one side to the other depending upon whether flow is to be permitted or prohibited.

BLINDING PROCEDURES
The installation and/or removal of blinds shall be performed by or at the direction of the Company Representative. Blinds shall be installed on or in all piping connected to vessels or equipment scheduled for entry or hot work. Blinds shall be near the vessel preferably on the first flange from the vessel shell. NOTE: In these instances where a blind cannot be installed near the vessel, it may be necessary to plug the inside of the vessel after the blind is installed. In some instances, a valve, spool piece or other device may be removed from the line and a blind flange installed on the line and the vessel. A blind list shall be maintained. This list includes the size, location and date of installation and removal of any blind. The authorized person shall consult the blind list to ensure that all blinds have been removed/returned prior to start-up. Failure to remove all blinds can lead to over-pressurization or other hazardous conditions.

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK

3.02ADM001

Page 7 of 26

COLOR CODING AND SIGNS


Color coding is a visual reminder system to warn, inform and guide personnel. OSHA assigns specific meaning to certain colors. Colors can be a warning of a particular hazard or give information or directions. These colors usually indicate the following:

Danger - Red, predominantly red, with lettering or symbols in a contrasting color Caution - Yellow, or predominantly yellow, with lettering or symbols in a contrasting color Warning - Orange, or predominantly orange, with lettering or symbols in a contrasting color Biological Hazard - Fluorescent orange or orange-red, or predominantly so, with lettering or symbols in a contrasting color
Instructional Green background with white lettering All signs giving instructions must be followed.

COMPRESSED CYLINDERS STORAGE AND USE


All cylinders must be stored in an upright position or in accordance with manufacturer instructions and Department of Transportation standards and secured to prevent tipping. Valves are to be closed and safety caps are to be in place. Oxygen and acetylene cylinders shall not be stored together except in approved carts. Label empty cylinders "Empty." Do not use grease or oil on oxygen valves, fittings, etc. Valve protector caps shall be installed on all cylinders when being transported. Do not lift cylinders by the cap. For short distance moving, a cylinder may be rolled on its bottom edge but never dragged. Always check a cylinders markings to be sure it contains the correct type of material for the job. Know how and when a substance should be used. Do not tamper with or bypass any safety devices; report all defects to your supervisor. When checking cylinder gauges or opening cylinder valves, stand off to one side to lessen your risk that an exploding object might hit you. All cylinders shall be secured when being transported or stored. Acetylene cylinders shall be stored upright when being transported or stored. All cylinders must have an up-to-date hydrostatic test in accordance with Department of Transportation regulations. Leaking cylinders should be immediately reported to a supervisor. Cylinders shall not be taken into confined spaces.

Cylinders shall not be permitted to rest on surfaces that permits moisture to accumulate between the cylinder base and the surface on which it rests. CONFINED SPACE
Confined Space means any space that:

Is large enough and so configured that a person can bodily enter and perform assigned work; and Has limited or restricted means for entry or exit; and Is not designated for continuous personnel occupancy.

Hazard identification, hazard control and atmospheric monitoring are the three mandatory components that precede confined space entry. Do not enter a confined space that has contained, or may contain, a hazardous atmosphere, unless it has been proven safe. A comprehensive work plan shall be made and followed prior to and during entry into a permit space. Entry into a "Permit" confined space, as defined by OSHA, shall be authorized by the issuance of a written permit signed by the supervision in charge and will be conducted in accordance with OSHA regulations. Permit-required confined space (permit space) means a confined space that has one or more of the following characteristics:

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK

3.02ADM001

Page 8 of 26

Contains or has a potential to contain a hazardous atmosphere; "Hazardous atmosphere" means an atmosphere that may expose personnel to the risk of death, incapacitation, impairment of ability to self-rescue (that is, escape unaided from a permit space), injury or acute illness from one or more of the following causes:
Flammable gas, vapor or mist in excess of 10 percent of its lower flammable limit (LFL); Airborne combustible dust at a concentrate that meets or exceeds its LFL; Note: This concentration may be approximated as a condition in which the dust obscures vision at a distance of 5 feet (1.52 m) or less.

Atmosphere oxygen concentration below 19.5 percent or above 23.5 percent; Atmosphere concentration of any substance for which a dose or a permissible exposure limit is published in Subpart G, Occupational Health and Environmental Control, or in Subpart Z, Toxic and Hazardous Substances, of this Part and that could result in personnel exposure in excess of its dose or permissible exposure limit; Note: An atmospheric concentration of any substance that is not capable of causing death, incapacitation, impairment of ability to self-rescue, injury, or acute illness due to its health effects is not covered by this provision.

Any other atmospheric condition that is Immediately Dangerous to Life or Health (IDLH).

Contains a material that has the potential for engulfing an entrant; Has an internal configuration such that an entrant could be trapped or asphyxiated by inwardly converging walls or by a floor which slopes downward and tapers to a smaller cross-section; or Contains any other recognized serious safety or health hazard (e.g. moving parts, moving machinery, electricity, etc.).
Before a person enters a confined space, atmospheric tests for oxygen deficiency and any potentially dangerous air contaminants shall be made with approved and calibrated devices. A written record of all atmospheric testing shall be recorded on the entry permit and kept at the work site for the duration of the work. Confined spaces shall be emptied, flushed or cleared of hazardous substances before entry. Disconnect or block off lines that may contain hazardous substances to prevent these substances from entering the workspace while work is in progress. Attach a warning tag and lock, if possible, to the line or system to notify workers that it shall remain out of service until the responsible person removes or authorizes the removal of the tag and lock. Follow lockout/tagout procedures as required. Personnel entering or working inside a confined space shall use appropriate respiratory protection whenever the breathing atmosphere cannot be rendered safe through implementation of feasible engineering/administrative controls (e.g. mechanical ventilation, purging, use of nontoxic products, etc.). Ensure that the proper safety equipment is available and used for entry and rescue. This may include safety lights, communication equipment, respiratory equipment, retrieval device, safety harness and lifeline, first aid equipment, fire extinguishers, etc. An attendant must remain outside of the permit space during entry operations until relieved by another qualified attendant. Ensure emergency rescue services are in place. Confined space entry must be concluded with entrant debriefing.

ELECTRICAL SAFETY

QUALIFIED PERSONNEL
Only qualified personnel shall be allowed to perform renovation, repair, maintenance or inspection of electrical equipment. Follow lockout/tagout procedures when working on electrical equipment.

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK

3.02ADM001

Page 9 of 26

GENERAL
Electrical vault rooms are not to be used for storage. Only authorized personnel shall work in electrical panels, alter existing wiring or install electrical wiring. No fuse may be installed in an electrical circuit that carries more amperage than the rating of the wiring for the circuit. For purposes of this manual, any systems operating at voltages above 480 volts shall be considered high voltage systems. All 120-volt, single-phase 15 and 20-ampere receptacle outlets on construction sites must have approved ground-fault circuit interrupters, if the outlets are used by personnel and are not part of the permanent wiring of the building. Keep access to disconnects, panels and junction boxes clear. Know the locations of disconnects. Insulated gloves, rubber soles and/or protective coverings should be used where necessary while repairing or installing electrical circuits. These devices must be maintained in accordance with manufacturers recommendations and regulatory requirements. No electrical panel, switch or wiring shall be left open without protection. Workers shall red-tag, close and/or seal these items when not working in the immediate vicinity. Move flammable materials away from electrical heat sources and lights. Use approved C or ABC rated fire extinguishers for electrical fires. Never use water. The Companys Representative, location supervision, Contractor Supervision and all other affected personnel shall be notified when a lockout/tagout condition exists in their work areas. Report all unsafe conditions such as the following to your supervision and/or the Company Inspector or Representative:

Shocking, sparking, overheating or smoking machinery Corroded outlets, switches and junction boxes Extension cords in permanent use Exposed wiring, broken plugs or outlets, missing box covers or faceplates
Outlets in damp areas without ground fault circuit interrupt devices When adjusting, lubricating, moving or cleaning electrical equipment, always disconnect it from the electric outlet or circuits. Equipment being serviced or under testing shall be properly locked and tagged. Do not work alone. Whenever working where electrical hazards exist, always maintain communication with fellow personnel. Personnel must use a GFCI (ground fault circuit indicator) when cords are used or an assured electric grounding program in effect. Daily documentation must be maintained.

FIRE PROTECTION AND PREVENTION

Contractors shall be responsible for developing and maintaining an effective fire protection and prevention program at the job site throughout all phases of construction and maintenance. Contractors shall become familiar with the classified area designations and requirements within the working area and shall incorporate this information into the safety program including the following:

Know where the nearest fire extinguisher is located. Only use a fire extinguisher if you are properly trained. Use the proper type of fire extinguisher for the type of fire encountered. Be aware that certain toxic fumes may be generated by fire. Use of gasoline or other flammable liquids for cleaning is prohibited. Gasoline powered equipment, non-explosion-proof electrical equipment, matches, lighters or any other sources of ignition

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK

3.02ADM001

Page 10 of 26

are not allowed within a classified area without a work permit.


Contractors required to perform hot work on or near facilities where flammable gas mixtures may exist shall supply a calibrated combustible gas indicator approved for use in Class I atmospheres and shall perform atmospheric tests to ensure that flammable vapors are not present. (Note: A hot work permit is required). Contract personnel required to perform atmospheric tests shall be knowledgeable in the use of such combustible gas detectors and perform calibration checks before each use. When performing hot work where flammable gas mixtures may exist, an adequate number of 20 or 30 lb. dry chemical fire extinguishers (tested and inspected) must be located on the upwind side of the work. A qualified individual (firewatch) must attend each fire extinguisher upwind from the hot work until all work is finished. When applicable, a firewatch should remain in the area for at least 30 minutes after the welding and cutting operations are done to detect and extinguish smoldering fires. Hot work signs must be attached to unattended completed work that has not cooled enough to be safe to touch. Contractor must supply fire extinguishers for hot work. All fires must be reported to Company personnel.

FLAMMABLE AND COMBUSTIBLE LIQUIDS HANDLING AND STORAGE OF FLAMMABLE AND COMBUSTIBLE LIQUIDS
Use only approved containers that are properly labeled. Keep flammable/combustible liquids away from fire and sparks. Flammable or combustible liquids shall be stored in approved locations only. Use only in well-ventilated areas. Use available fans, hoods and ventilation equipment that are properly rated for the hazardous location classification. Do not mix chemicals unless instructions call for mixing. Use bonding wires to prevent static electricity while transferring flammable liquids from one container to another. Both containers should be bonded together and have at least one ground wire. Approved hazardous material transfer pumps or self-closing spigots shall be used for dispensing flammable liquids.

HAZARDOUS MATERIAL SAFETY AND SPILL CONTROL


All chemicals used by Contractors shall be listed and shall be accompanied by a Material Safety Data Sheet (MSDS). This list shall be given to the Companys Inspector or Representative. The Companys Inspector or Representative shall inform the Contractor Supervision of the location and accessibility of the Companys MSDSs. All containers shall be labeled with contents and appropriate hazard warning(s). At no time shall improperly labeled containers be used. Particularly hazardous materials (e.g., radioactive, extremely toxic, noxious, explosive or highly reactive chemicals) shall always be brought to the attention of the Companys Inspector or Representative prior to use on Company property. Hazardous materials, chemicals, fuels, lubricating oils, etc. shall be properly handled, stored and disposed of as directed by Companys Inspector or Representative. All personnel involved with a response to an uncontrolled release of hazardous substances shall be trained to the hazardous material technician level under OSHA HAZWOPER response criteria (refer to 29 CFR 19 10.120). Any soil or other material contaminated by hazardous materials shall be handled in accordance with applicable regulations and Company policies. The Contractor shall consult with the Companys Area Environmental Specialist to determine proper disposal.

HOISTING AND CRANE OPERATION


Operators of cranes shall be trained in their safe operation. The last monthly inspection shall be maintained in the vehicle cab and be available for inspection upon request. The operator at the start of each shift shall make a thorough visual check of the entire machine. Deficiencies affecting the safe operation of the machine shall be corrected before operation begins. Boom sections, cables, swivels, hooks and controls shall be inspected prior to

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK making a pick.

3.02ADM001

Page 11 of 26

The crane operator shall not operate the crane until persons involved in the operation have been instructed as to the work to be performed. All personnel involved in hoisting and crane operation shall wear the appropriate personal protective equipment, e.g. hard hats. Personnel shall be clear of loads before the loads are picked up or landed and shall remain clear at all times. Personnel shall not stand/pass under suspended loads. The use of a crane or derrick to hoist personnel on a personnel platform is prohibited, except when the erection, use and dismantling of conventional means of reaching the worksite, such as a personnel hoist, ladder, stairway, aerial lift, elevating work platform or scaffold, would be more hazardous, or when it is not possible because of structural design or worksite conditions. The use of personnel platforms shall comply with the OSHA requirements specified in 29 CFR 1926, Section (g). Slings, fittings and fastenings, when in use, shall be inspected daily. Slings found to be damaged or defective shall be removed from service and destroyed. Chains used for lifting shall be approved with documentation tags attached. Never exceed the rated capacity of the crane. Flag off the counter weight swing radius of the crane. Fully extend outriggers, where provided. Check the operation of the controls before making the first pick. Replace any cable that has been kinked or has visible damage. Replace cables if the wear on outer wires is 25% of the wire diameter or if three wires are broken in one strand or six wires in one lay. Never use a boom with bent cord members. Do not stand in the boom lattice or under the boom when disassembling or assembling the boom. Ensure that the automatic boom hoist kickouts are operational and positive boom stops are correctly installed. Ensure crane is equipped with anti-two block where required. Ensure the operating ground base is stable and level. Designate one person as the signal person prior to any picks being made. Check and maintain the required clearances from power lines. Except where electrical distribution and transmission lines have been de-energized and visibly grounded at point of work or where insulating barriers, not a part of or an attachment to the equipment or machinery, have been erected to prevent physical contact with the lines, equipment or machines shall be operated proximate to power lines only in accordance with the following:

For lines rated 50 kV or below, minimum clearance between the lines and any part of the crane or load shall be 10 feet. For lines rated over 50 kV, minimum clearance between the line and any part of the crane or load shall be 10 feet plus 4 inches for each 10kV above 50kV, or twice the length of the line insulator, but never less than 10 feet. In transit with no load and boom lowered, the equipment clearance shall be a minimum of 4 feet for voltages less than 50 kV and 10 feet for voltages over 50 kV, up to and including 345 kV, and 16 feet for voltages up to and including 750 kV. A person shall be designated to observe clearance of the equipment and give timely warning for all operations where it is difficult for the operator to maintain the desired clearance by visual means. Cage-type boom guards, insulating links or proximity warning devices may be used on cranes, but the use of such devices shall not alter the requirements of any other regulation of this part even if such device is required by law or regulation. Any overhead wire shall be considered to be an energized line unless and until the person owning such line or the electrical utility authorities indicates that it is not an energized line and it has been visibly grounded.

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK

3.02ADM001

Page 12 of 26

Use tag lines to control loads unless their use creates an unsafe condition.

HOT WORK PERMITS


Hot Work permits are issued to authorize work involving any source of potential ignition near flammable or combustible materials. Welding, cutting, the use of non-spark-proof tools and/or non-explosion-proof equipment and other work involving open flames shall be controlled so as not to cause a fire or explosion hazard. The Hot Work Permit issued shall include the area, time and type of work to be completed. A Company person/Inspector is assigned to monitor any work being performed by the Contractor to ensure that conditions of the permit are being followed. The Hot Work Permit issued covers only the work approved under the permit. If any other work is required in the area for which the Hot Work Permit was issued, a separate permit shall be issued for the work not covered under the original permit. A Hot Work Permit shall not be issued and hot work shall not proceed when flammable gas or vapor is present in excess of 10% LEL and/or 0.5% by volume of natural gas (methane), unless such flammable gas or vapor is necessary for safe performance of the work and its rate of emission is controlled. Hot Work Permits are valid for the time specified on the permit and must be reissued if work is to continue beyond the permitted time period. Permits need to be reissued if contractor leaves the site. Permits shall also be reissued in the event the emergency alarm is sounded. A fire extinguisher shall be present and in a fully charged condition throughout the hot works duration and for a minimum of thirty minutes afterwards to verify no incipient fires occur. A properly calibrated combustible gas detector shall be used to continuously monitor the surrounding atmosphere for flammable gas. The Company may require personnel to wear flame retardant coveralls if the work involves significant risk of sudden exposure to flammable gas or vapor. Restrict personnel in the area of hot work to only those who are authorized and necessary to perform the work. When welding or cutting in the vicinity of a building or facility that is protected with an Ultraviolet Flame Detection System, the UV radiation emitted by the arc may activate the UV detection system. The Contractor shall be aware of these conditions to ensure that necessary fire detection monitors are bypassed. Operations personnel shall remain on site during this period of time when the fire detection systems are bypassed. An installation of a shield may be required to keep sparks from escaping from the controlled area of the work in progress. All holes, cracks or opening in walls and floor shall be protected to prevent sparks from passing through to another area.

LADDERS

Only OSHA-approved ladders of commercial grade with a load weight rating of 250 pounds or more shall be used. Inspect before use. Ladders shall be in good condition, without loose or cracked rungs or side rails. No box, chair, carton, shelves or anything handy is to be used as a ladder. Only use ladders in good repair that are equipped with feet. Be sure the ladder is long enough to do the job safely. It should be at least three feet above the working surface. Never attempt to use a ladder in a strong wind. Ladders should be secured at the bottom to prevent kick-out and secured at the top with non-conductive material if they are tall or unsafe. Do not paint ladders except for numbering purposes. Ladders must be maintained free of oil, grease and other slipping hazards. Do not use a ladder for skids, braces, workbenches or any purpose other than climbing. Do not place a ladder in or over a doorway, unless the door is barricaded and a warning sign(s) is posted.

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK

3.02ADM001

Page 13 of 26

Ladders may be used on scaffolds only if secured and the user ties off with a safety body harness. Face a ladder when ascending, descending and working from it. Do not carry anything that will prevent holding on with both hands while ascending or descending a ladder. Use a handline. Carry tools on belt or raise and lower materials with a rope to leave both hands free while climbing. Keep both feet on the ladder rungs. Do not reach out too far, or place one foot on a line or piece of equipment. Change the position of the ladder as often as necessary. No attempt should be made to reach beyond a normal arms length while standing on the ladder, especially to the side. Do not climb on a ladder that is occupied by someone else. Do not use metal ladders around electrical activities or near any electric lines or services. Fiberglass ladders are required when working around electrical equipment. Observe all warning tags. Straight and extension ladders shall be tied off during use. Folding ladders must be locked open. Never stand or step on either the top step or the top of a ladder. Place extension ladder so the base is out one-fourth the vertical distance from the ground to the object against which the ladder is leaning. Do not take extension ladders apart to use either section separately. When using a stepladder, make sure that it is fully spread and locked. Check for unsafe hinges as well as steps and uprights. Stepladders should not be walked when someone is on them. Always read and understand the manufacturers warning and follow the instructions.

LOCKOUT AND TAGOUT

A written lockout/tagout procedure is required to prevent accidental startup or release of energy sources (electrical, mechanical, hydraulic, pneumatic, chemical, thermal and others). All Contractor personnel affected by lockout/tagout must be trained in appropriate lockout/tagout procedures. Before beginning service or maintenance work, a work plan shall be constructed. Personnel performing work within the plan shall have a review of the plan that covers the lockout/tagout measures and requirements. The most effective means of preventing personnel injury or property damage from an unanticipated movement of machinery, or release of stored energy, is to isolate and dissipate the residual energy and/or use a restraining device to prevent movement. This action shall be followed by the placement of a safeguard lock and tag to prevent the reactivation of the source. The Contractor Supervision and Company Inspector or Representative shall verify that the equipment and process has been thoroughly isolated and appropriately locked and tagged. Each person including contractor personnel should actively participate in lockout/tagout to assure equal protection. The Company Representative shall always be present whenever Contractors padlocks are attached or removed from the lockout device. In addition, Contractors shall not touch start/stop devices unless a Company Representative is present. Following completion of the activity, all guards and other safety devices shall be reinstalled before authorized persons remove locking devices and/or tags. If a padlock is mistakenly left on and there is a need to reactivate the equipment or process, it shall be the responsibility of the Company Inspector or Representative and Contractor Supervision to conduct a thorough investigation to verify that it is safe to remove the lock(s) and/or tag(s) and to reactivate the equipment or process. Only then may the lock and/or tag be removed by the responsible Company Inspector or Representative and/or Contractor Supervision.

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK

3.02ADM001

Page 14 of 26

PERSONAL HEALTH AND SAFETY PROTECTION INTRODUCTION


Personal protective equipment includes devices and clothing designed to place an effective barrier between the person and harmful objects, substances, conditions or radiation. Contractor management is responsible for ensuring that personnel wear proper personal protective equipment based upon a documented hazard workplace assessment for the worksite. Our Companies provide the documented hazard assessment to the contractors upon request. Some areas within the Company require specific personal protective equipment to be worn. Contractors are required to abide by the locations personal protective equipment requirements.

CLOTHING

Conventional clothing requirements may vary by project and location. Consult with local Workplace Hazard Assesment. In addition, special fire-resistant clothing may be required for job conditions or work activities (e.g., line repairs, hot taps, etc.) where the potential for flash fire exists. Check with the Company Inspector or Representative for specific requirements.

HEARING PROTECTION

Where engineering controls are not feasible to eliminate noise hazards, hearing protection (earplugs or earmuffs) that will attenuate the noise to meet code requirements shall be worn. Caution and danger signs identify some areas where hearing protection is required.

HEAD PROTECTION

Hard hats meeting ANSI Z89.1 (most recent edition) shall be worn at the sites where an electrical hazard is present, where overhead work is in process and/or overhead structures present a hazard to the workers head. Hard hats shall be worn at all construction sites. Appropriately rated hard hats shall be worn for the type of job task being performed.

FOOT PROTECTION

Footwear with safety-toed (steel or fiberglass) protection may be required to be worn. Footwear shall be predominantly over-ankle sturdy leather shoes or boots with soles that minimize slipping. Protective footwear must meet or exceed the ANSI Z41-1991 (most recent edition) standard (Personal Protective Footwear), with an impact rating of I-75 and compression rating of C-75. Check with the Companys inspector or facility supervisor for specific requirements. Safety shoes are required while engaged in maintenance and construction activities and at all other times in work areas where potential foot hazards exist. Safety shoes must be made of leather or a leather-type material, have a defined heel, and must cover the entire foot.

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK

3.02ADM001

Page 15 of 26

Absorptive material shoes, such as canvas or cloth tennis or jogging style shoes, are not allowed while engaged in maintenance or construction activities. When the possibility of working in water, oil or petroleum products exists, rubber boots should be worn. Shoes that offer electrical protection may be required.

HAND PROTECTION

Appropriate hand protection shall be worn when handling hazardous substances (e.g., chemicals, abrasive materials, hot surfaces, etc.). The appropriate hand protection must be selected for the work being performed. A short, tight fitting canvas or leather glove should be worn during most construction and heavy maintenance work. Certain electrical work requires the wearing of approved rubber gloves. Chemical resistant rubber or plastic gloves shall be worn when handling chemicals, as specified by the chemicals MSDS.

EYE AND FACE PROTECTION

Appropriate safety eyewear with side shields (meeting most recent edition ANSI Z87.1, Occupational and Educational Eye and Face Protection requirements) shall be worn whenever working near activities where particles or chemicals can enter the eyes. Impact goggles or full face shields are required, in addition to safety glasses, for most chipping, grinding, drilling or sawing activities. Chemical goggles are required for handling acids, caustics, corrosives and other eye damaging chemicals. In addition to the goggles, a full face shield may be required to protect the workers face when exposure to splashing of these chemicals exists. Special purpose protection (hoods, welding, lenses, etc.) is required when sandblasting, painting and welding. A face shield shall be worn whenever exposure to the face exists due to flying particles, sprayed liquids, etc. Safety glasses or goggles must also be worn when using face shields. Chemical goggles are designed to protect the wearers eyes against spray or splash of liquid or of chemicals in powder form. Chemical goggles must be worn whenever spray or splash hazards exist.

RESPIRATORY PROTECTION

There are areas or tasks that may require respiratory protection. Only authorized personnel necessary to complete the work should be allowed in these areas. If work requires Contractor personnel to become involved in a task where respiratory protection shall be used, the Company Inspector or Representative and Contractor Supervision shall identify the risks. Contractor Supervision shall obtain the appropriate medical clearance, fit testing and training for personnel and provide the proper respiratory protective equipment.

FALL PROTECTION

Personnel shall be protected from fall hazards and falling objects whenever working six (6) feet or more above a lower level. Protection shall also be provided for personnel who are exposed to the hazard of falling onto dangerous equipment, regardless of the height. The fall protection method(s) selected shall be compatible with the type of work being done. Fall protection can generally be provided through the

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK

3.02ADM001

Page 16 of 26

use of guardrail systems, safety net systems, personal fall arrest systems, positioning device systems, warning line systems, controlled access zones, safety monitor systems and covers. Selection of fall protection systems shall be based on a site inspection and evaluation of fall hazards, and shall comply with established rules and regulations.

POWER-ACTIVATED HAND TOOLS


Contractor shall not issue or permit the use of defective tools. A Hot Work Permit is required for power-activated tools used where hazardous atmospheres may be present. Only properly trained and qualified operators shall use power-activated tools. All power-activated tools and extension cords shall contain the three prong type plugs where one is the ground. Extension cords should be free from damage and taped fixes on them. Extension cords must be used with a GFCI (ground fault circuit indicator). All power-activated tools shall be double insulated.

SCAFFOLDS

A scaffold is any temporary elevated platform and its supporting structure used for supporting workers or materials or both. Scaffolds shall be erected on sound, rigid footing and their components shall comply with OSHA requirements for the use intended. The following are general rules and safety practices for scaffolds:

When space permits, all scaffold platforms shall be equipped with standard 42-inch high handrails (rigidly secured; not wired), and standard 21-inch high midrails (completely decked with safety plank or manufactured scaffold decking). Toeboards must be rigidly secured and have a vertical height of 4 inches from its top edge to the level of the floor, platform, runway or ramp along all four sides. Scaffolds shall be designed, constructed and maintained in accordance with the manufacturers instructions and applicable industry standards. Impose loads on the scaffold gently and without impact. Two or more scaffolds must not be combined into one except for multi-point scaffolding. Scaffolds must be assembled and used by trained personnel. Do not install the scaffold in the vicinity of power lines; avoid electrical contact. Personnel shall wear a safety body harness properly tied off on any scaffold platform not equipped with standard handrails, midrails or complete deck. Do not alter any scaffold member by welding, burning, cutting, drilling or bending. No one is allowed to ride on a rolling scaffold when it is being moved. Remove or secure all tools and material on the deck before moving. Rolling scaffolds shall be used only on level, smooth surfaces, or the wheels shall be contained in wooden or channel iron runners. Watch for overhead clearance when moving. Casters shall be pinned. Adjusting or leveling screws shall not be used on scaffolds equipped with wheels. Adjusting screws shall not be extended more than 12-inches of thread. Scaffolds should be removed promptly after completion of the job.

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK

3.02ADM001

Page 17 of 26

TRENCHING AND EXCAVATION

The Occupational Safety and Health Administrations (OSHA) Excavation Standard requires that the excavation site shall be continually checked for potential hazards by a "Competent Person." Contractors are required to designate one of their personnel as the "Competent Person" who meets the requirements set forth in OSHA excavation and trenching standard. Prior to opening an excavation, determine whether underground installations, e.g., sewer, telephone, water, fuel, electric lines, etc., will be encountered. Utility companies or owners shall be contacted (via one-call system, if available) within established or customary local response times, advised of the proposed work, and asked to establish the location of their underground installations. Utility Companies will not locate private utilities; therefore, the contractor shall arrange for private utility locations. When excavation operations approach the estimated location of the underground installations, the exact location of the installation shall be determined by safe and acceptable means. This may involve probing the ground by hand or hand digging to ensure that any underground installation will not be damaged. A soil determination shall be made and documented as to soil type and class. Also, the following items must be addressed:

Excavations that are 5 feet or more in depth into which workers will enter, shall be sloped or shored sufficiently to prevent cave-ins. When an excavation can not be sufficiently sloped, adequate protective systems shall be provided and used. The overburden of excavated materials shall be located at least 2 feet from the edge of any excavation that is 4 feet or more in depth. When personnel are required to be in trenches 4 feet deep or more, ladders or steps shall be provided and located as to require no more than 25 feet of lateral travel to exit. Contractors shall furnish and place around excavations and trenches the proper guards, barricades, lights, fences, etc., that may be necessary for the safety of the public. A registered professional engineer shall design sloping, benching and shoring systems for excavations greater than 20 feet deep. The competent person prior to the start of work shall conduct a documented inspection of the excavation and as needed throughout the shift. Documented inspections shall also be made after every rainstorm or other hazard-increasing occurrence. These inspections are required when personnel exposure can be reasonably anticipated. The Competent Person may be over several excavations at the same site. If any changes occur at the excavation the Competent Person must review the site before work can be continued. VEHICLE SAFETY

GENERAL
Obey all traffic and parking regulations. All motor vehicles and portable power equipment shall be in good working order. All motor vehicle and equipment operators shall be properly trained and licensed and/or certified in accordance with applicable regulatory requirements.

MOTOR VEHICLE OPERATING SAFETY PROCEDURES


Spotters shall be used for backing when visibility is limited or in difficult situations. Operators shall yield to emergency vehicles. Seat belts shall be worn.

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK All Rules of the Road shall be observed. Passengers shall ride in approved seating areas only.

3.02ADM001

Page 18 of 26

All motor vehicle accidents shall be reported to the Company Representative. Parking is permitted in designated areas only. Park to avoid backing. Walk around vehicle just prior to backing. Check front-end clearance when backing.

TRANSPORTATION
All vehicles transporting hazardous materials shall display the appropriate Department of Transportation placards, if required, and shall contain the proper shipping papers. Loads shall be properly tied down and secured prior to moving. Oversized loads shall have the proper warning flags or reflectors and escorts.

REFUELING
Gasoline and diesel powered vehicles or equipment shall not be refueled inside buildings, but moved to a safe outside location. Refueling shall be attended at all times. In case of a fuel spill, cease operation until area is made safe, then report spill to your supervision and the Company Representative. Ignition system shall be turned off before refueling.

WELDING AND CUTTING


Caution shall be exercised when welding or cutting on or near operating pipelines and processing equipment. Company personnel and Contractor Supervision shall develop work plans and requirements for all hot work, hot taps and tie-ins.

GENERAL
Adequate ventilation shall be provided if necessary. A Hot Work Permit is required in all Class I, Division 1 and Division 2 areas before striking an arc or lighting a torch. All exposed combustible materials below welding and burning areas shall be removed to a safe location or covered with fire-retardant material. An appropriately rated 20 or 30 lb. ABC or larger dry chemical fire extinguisher shall be manned within 30 feet of any welding, burning or open-flame work. Ensure personnel know how to operate the fire extinguisher. No welding or cutting is to be done on a closed vessel or tank or on any vessel previously in use unless it has been decontaminated and rendered safe. The user shall inspect all leads, grounds, clamps, welding machines, hoses, gauges, torches and cylinders before they are put into operation. Keep oil and grease away from oxygen regulators, hoses and fittings. Do not store wrenches, dies, cutters or other grease-covered tools in the same compartment with oxygen equipment. When welding or cutting torches are left unattended, shut off the oxygen and fuel supply at the cylinders and bleed pressure off the hoses. All cylinders shall be properly secured. Welding requires that goggles, shields, proper clothing and approved gloves be worn while performing the operation.

WELDINGELECTRICAL
Electrical ground connections shall be fastened securely to the work and fit in a manner to prevent arc burns. Remove the rod from the electrode holder when laying it down. Discard used rods in a proper container. All arcs are to be shielded in operating areas.

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK

3.02ADM001

Page 19 of 26

The machine shall be turned off at the end of each shift or when not in use for extended periods.

OTHER PRACTICES ASBESTOS-CONTAINING MATERIAL (ACM) HANDLING

Contractors performing abatement work associated with the removal, encapsulation or other disturbance of asbestos-containing material (ACM) must be properly licensed to operate in the state where the work is to be performed. Compliance with all state and federal regulations related to the handling, removal, storage, transportation and disposal of ACM is required. Personnel involved in ACM disturbance/abatement activities shall be trained according to the OSHA Classification Levels applications to their assignments (refer to OSHA CFR 1926.1101).

LEAD IN CONSTRUCTION
Contractors, when exposed or working around removing lead-based materials via abrasive blasting methods, are required to implement the provision of OSHAs Lead in Construction Standard (1926.62) and OSHAs General Industry Standards. OSHAs Lead in Construction Standard and OSHAs General Industry Standards apply to all construction work where personnel may be occupationally exposed to lead. All work related to construction, alteration or repair - including painting and decorating - is included. Under this standard, construction includes, but is not limited to, the following:

Demolition or salvage of structures where lead or materials containing lead are present; Removal or encapsulation of materials containing lead; New construction, alteration, repair or renovation of structures, substrates or portions containing lead, or materials containing lead; Installation of products containing lead; Lead contamination from emergency cleanup; Transportation, disposal, storage or containment of lead or materials containing lead on the site or location at which construction activities are performed; and
Maintenance operations associated with the construction activities described above.

NATURALLY OCCURRING RADIOACTIVE MATERIAL (NORM)


It is the responsibility of the Company Inspector or Representative to inform Contractors of any known hazardous levels of NORM that may be present in the Contractors work area. It is the Contractors responsibility to ensure only qualified workers are used when NORM is present. A worker protection plan may be required for work activities that may involve potential NORM exposures. The Contractor shall be aware of, and comply with, applicable regulations.

RADIATION SAFETY

INDUSTRIAL RADIOGRAPHY
Industrial radiography is sometimes used to inspect various process equipment and piping. This procedure is carefully controlled and

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK

3.02ADM001

Page 20 of 26

conducted in accordance with the U.S. Nuclear Regulatory Commission requirements. To ensure that personnel are aware of the presence of radiation emitting devices, special warning signs shall be posted. Radiation areas shall be barricaded and controlled to prevent entry by unauthorized personnel. When radiography work is being conducted in the vicinity of a building or facility protected with an Ultraviolet Flame (UV) Detection System, the radiation emitted may activate the UV detection system. The Contractor shall be aware of these conditions to ensure that the Company personnel bypass the necessary fire detection monitors. Company Operations personnel shall remain on site during this period of time when the fire detection systems are bypassed. Contractor shall not perform any work while fire detection systems are bypassed unless Company personnel are onsite.

WASTE MANAGEMENT

A waste is considered to be anything which is no longer fit for its intended use, or is spilled, abandoned, discarded, burned, disposed or applied to the land in a manner that constitutes disposal. In addition to the obvious types of waste (e.g., trash, process wastes, etc.), this includes the following:

Spills or releases Unknown/unidentifiable materials A material that is no longer fit for its intended use, e.g., inventory damaged by cold temperatures or which has an expired shelf life.
Batteries that are not returned to the vendor or recycled Chlorinated solvents, e.g., chlorothene, carburetor cleaners, etc. Standard solvents or mineral spirits, e.g., cleaners solvent, Safety Kleen 105 Paint wastes Used oil that is not recycled Waste fuels and methanol that are not recycled Fluorescent light bulbs

Examples of hazardous wastes are:

Contractors must obtain authorization from the Companys Representative or Companys Environmental Specialist before disposing of any waste into sumps, dumpsters and drums at Company facilities. Contractors must comply with all regulations and polices regarding waste management. Contractor must not wash or spray down equipment without adequate containment. No liquids may be placed in dumpsters. Cautions about mixing wastes: Realize where the waste is going and how the mixture shall be handled there. Will it cost more money to dispose of the mixture? Do not mix: Solids with liquids Hazardous with non-hazardous wastes Incompatible materials (e.g. acids and flammables) Unknown materials

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK

3.02ADM001

Page 21 of 26

Keep an inventory of exactly what goes in any dedicated hazardous waste drums. Perform weekly container inspections as required. How to store waste properly: Store in approved locations. Label contents and appropriate hazard warnings. Keep bungs closed. Use drum covers for long term storage. Use only structurally sound containers; i.e., shippable containers that do not have any corrosion, rust, bulges, dents, etc. Never dump wastes on the ground for storage, even temporarily. Store empty drums on their side to prevent rainwater accumulations. Asbestos waste must be double bagged, labeled and placed inside a rigid container for transportation or long term storage.

Maintain records of waste shipments. How to ship waste properly: Contact the District Environmental Specialist (ES) with the name and amount of waste

WORK SHEETS
SITE SPECIFIC PERSONNEL/EMERGENCY INFORMATION Project Scope: Location: KEY COMPANY PERSONNEL: Title Company Supervision or Representative Company Inspector Company Safety Representative Name Phone Number Work/Home

OTHER PERSONNEL

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK


CONTRACTOR Title Contractor Supervision Contractor Safety Representative Competent Person Name

3.02ADM001

Page 22 of 26

Phone Number Work/Home

EMERGENCY INFORMATION Police Fire Sheriff State Police Ambulance Hospital OTHER

NOTES

CONTRACTOR ENVIRONMENTAL, HEALTH & SAFETY REFERENCE HANDBOOK

3.02ADM001

Page 23 of 26

You might also like