Professional Documents
Culture Documents
Estimate
Estimate
and Gravel:
A. Continuous Wall Footing:
1. Volume of Wall footing
0.80 m. (0.20m.) (55.8 m.) = 8.93 m3
B. Wall of the Tank with tie beam along the wall :
1. Volume of the wall of the tank
0.15 m. (58.4 m) (3.75 m) = 32.85 m3
C. Beam:
1. Volume of B-1:
0.2 m. (0.3 m.) (53.2 m.) = 3.19 m3
D. Slab:
1. Volume of slab:
0.15 m. ((3.85)(7.85)+(1.85)(7.85) +
(2.85)(7.85) = 10.07 m3
E. Tank Cover:
1. Volume of tank Cover:
8 m. (9 m.) (0.10 m.) = 7.2 m3
F. Total Volume:
1. 62.24 m3
G. Using Class A mixture 40 kg. cement
1. For cement:
62.24 m3 (9) = 560.16 say 561 bags
2. For sand:
62.24 m3 (0.5) = 31.12 m3 say 32 m3
3. For gravel:
62.24 m3 (1.0) = 62.24 m3 say 63 m3
Length of Reinforced Steel Bars
A. Length of 16mm steel bar for manhole
locking mechanism:
1. Length of 16mm STEEL BAR for the
manhole locking mechanism:
Length of bar is each lock:
(.25 x 2)+.2=0.7m
1.
2.
3.
4.
b.
1.
2.
3.
4.
J.
c. TB - 1
1. Straight length of each longitudinal bar:
3.85 m + 0.15 = 4 m.
2. Net length of bar in each beam:
4 (4) = 16 m.
3. Length for 8 beams:
16 (8) = 128 m. 16 mm
d. TB - 2
1. Straight length of each longitudinal bar:
9 m + 0.35 = 9.35 m.
2. Net length of bar in each beam:
9.35 (4) = 37.4 m.
3. Length for 3 beams:
37.4 (3) = 112.2 m. 16 mm
I.
c.
1.
2.
3.
4.
d.
1.
2.
3.
4.
GRAND TOTAL:
1. 10 mm = 437.25 m.
2. 12 mm = 4687.95 m.
3. 16 mm = 454.6 m.
B. Tank
1. Number of Intersection on the 9.0 m face
of the tank:
(61)(21) = 1281
2. For 3 faces = 3843
3. Length of tie wire per intersection = 0.30
4. Total length of Tie wire:
3843 (0.30) = 1152.9 m.
5. Number of Intersection on the 8.0 m face
of the tank:
(53)(21) = 1113
6. For 4 faces = 4452
7. Length of tie wire per intersection = 0.30
8. Total length of Tie wire:
4452 (0.30) = 1335.6 m.
C. Slab
1. Number of Intersection:
(61)(53) = 3233
2. Length of tie wire per intersection = 0.30
3. Total length of Tie wire:
3233 (0.30) = 969.9 m.
D. Tank Cover
1. Number of Intersection on 2.0 x 2.0
detachable slab:
(13)(13) (4) = 676
2. Number of Intersection on 2.0 x 4.0
detachable slab:
(13)(26) (4) = 1352
3. Length of tie wire per intersection = 0.30
4. Total length of Tie wire:
2028 (0.30) = 608.4 m.
E. Beam 1
1. Number of Intersection:
(96)(4) = 384
2. Length of tie wire per intersection = 0.30
3. Total length of Tie wire: 384 (0.30) = 115.2
m
F. Beam 2
1. Number of Intersection:
(125)(4) = 500
2. Length of tie wire per intersection = 0.30
3. Total length of Tie wire: 500 (0.30) = 150
m
G. Tie Beam 1 and 2
1. Number of Intersection:
(236)(4) = 944
2. Length of tie wire per intersection = 0.30
3. Total length of Tie wire: 944 (0.30) = 283.2
m
I.
GRAND TOTAL:
1. Tie wire = 5134.2 m.
J.