Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 5

Document No.

: MEP-MS-54

METHOD STATEMENT FOR LIGHTING CONTROL SYSTEM

Rev.: 0.0 Date of Issue: Page No.: Page 2 of 7

TABLE OF CONTENTS
1. Scope 2. Reference Documents/Drawings 3. Access /Egress 4. Health and Safety Hazards 4.1 Safety Rules During Testing 4.2 Safety Lighting 4.3 Task Lighting 4.4 Emergency Arrangements 4.5 Risk and Controls 5. Abbreviations & Definitions 6. Roles/ Responsibilities / Competence 7. Testing & Commissioning Procedures 7.1 Pre-Commissioning 7.2 Start up procedure 7.3 System Programming 7.4 Final Testing 8. Training 9. Working Hrs. 10. Manpower Requirement & Supervision 11. Test Instruments Requirements 12. Personnel Equipment 13. Distribution 14. Attachments 14.1Commissioning Check List 14.2Risk Assessment.

Document No.: MEP-MS-54

METHOD STATEMENT FOR LIGHTING CONTROL SYSTEM

Rev.: 0.0 Date of Issue: Page No.: Page 3 of 7

1. Scope:
The method statement aims to provide necessary information for Testing and Commissioning of SIEMENS Lighting Control System installed in Ducab Extension. The system consists of Lighting Control Panels Power Supply, Relay Module, Timer and Push button in different areas to provide effective energy management as per the requirement.

2. Reference Documents/Drawings:
Lighting Control system Drawings Schematic Diagram Commissioning Checklist

3. Access /Egress: The Commissioning of the System will commence only when Main Contractor clearance is given for access to conduct Testing and Commissioning. 4. Health and Safety Hazards: Health and Safety procedures by Main Contractor and MACAIR/BMTS will be implemented for this job. A routine safety check will be done by the Safety Officer In-charge as per MACAIR Safety Procedure. 4.1Safety Rules during Testing & Commissioning: In order to ensure safe conditions during testing the following rules have to be followed: Persons engaged with this commissioning are experienced and have received proper and adequate training related to procedures and test equipment utilized for the particular testing activity. Test instruments and test leads should be maintained in a safe condition and the test methods not to create danger either for the operator or for other persons. 4.2Safety Lighting: Safety Lights will be used in case of power failure ensuring good illumination at the working area to aid evacuation if necessary. 4.3Task Lighting: Adequate lighting shall be provided to ensure good illumination at the working area. 4.4Emergency Arrangements: General : Site Safety procedures will be followed and in case of any emergency, Safety Officer will administer the emergency arrangements as per the system, stop work and report to nearest Assembly Point, etc. Safety Officer Name: Mr. Reghupathy Contact No. 055-9262923

Document No.: MEP-MS-54

METHOD STATEMENT FOR LIGHTING CONTROL SYSTEM

Rev.: 0.0 Date of Issue: Page No.: Page 4 of 7

Fire Precautions: No significant fire risks associated with this activity but general fire precaution measures will be taken. Communications: Via mobile phones issued to all Engineers. 4.5Risk and Controls: Please refer to the attached Risk Assessment. 5. Abbreviations & Definitions: MC PM PE SCE SO - Main Contractor (KCE) - Project Manager (MACAIR) - Project Engineer (MACAIR) - Site Commissioning Engineer (BMTS) - Safety Officer (MACAIR)

QA/QC - Quality Assurance/Quality Control (MACAIR) 6. Roles/ Responsibilities / Competence: PM - will have the overall responsibility of the Project for execution, quality and safety; maintain the planning and progress and coordination with Main Contractor. PE - will be responsible for day to day activities in the Site for System Testing and Commissioning, report preparation and demonstration of System Commissioning. SCE - will be directly responsible for the System installation. SO - will be responsible for Health and Safety aspects in the Site in line with Main Contractor Safety requirements. QA/QC - will oversee the quality requirements and quality control measures for the Project. 7. Testing & Commissioning Procedures : 7.1 Pre-Commissioning 7.1.1 Check the panel & batteries for any exterior damages. 7.1.2 Check the devices arrangement and wiring terminations in the panel 7.1.3 Check the tightness of the cable terminations. 7.1.4 Check the EIB cabling loop and panel to panel. 7.1.5 Labels & identifications. 7.1.6 The incoming power supply cable and all out going wires from the system must be meggered before terminating on the system or the light fixtures and the value noted down by the installer.

Document No.: MEP-MS-54

METHOD STATEMENT FOR LIGHTING CONTROL SYSTEM

Rev.: 0.0 Date of Issue: Page No.: Page 5 of 7

7.2 Prerequisites to Procedure Following are the prerequisites to the commissioning procedure 7.2.1 Installation of Lighting Control Panels (By MEP contractor) All the Lighting control Panels need to be installed in electrical room near to the respective DB in accordance with shop drawings. Cabling for panel to panel has to be completed. 7.2.2 7.2.3 Power Requirement (By MEP contractor) The Power supply module needs, 1-, 230V, 50 Hz. Installation of Batteries (By MEP contractor) All the lighting control devices have to be installed as shown in schematic drawing. The Line in and Line out cable terminated in the relay modules are properly labeled. The EIB cable termination on the every module has to be looped properly as per manufacture instruction. . 7.3 Start up procedure 7.3.1 Check the power supply module.. 7.3.2 Power test the all lighting control devices. 7.3.3 Check the polarity of EIB cable termination. 7.3.4 Check no short circuit is found in the panel. 7.4 System Programming 7.4.1 The system is programmed for the all the devices and circuits connected with the lighting control system. 7.4.2 The no. of devices and type of the devices are entered. 7.4.3 Address all the EIB devices as required. 7.4.4 Download the application program for the respective devices. 7.4.5 Group the devices as per the site requirement 7.4.6 Carry out the functional programming test manually from the ETS software 7.4.7 Program devices as per the application required as the site 7.5 Final Testing 7.5.1 7.5.2 8. 8. 8. Training: Remove EIB power supply and check all circuits are fail of safe mode Function test is conducted and demonstrated

Document No.: MEP-MS-54

METHOD STATEMENT FOR LIGHTING CONTROL SYSTEM

Rev.: 0.0 Date of Issue: Page No.: Page 6 of 7

Commissioning Engineers who will conduct the Commissioning shall have the experience in Lighting Control System Commissioning. Tool Box talks will provide general training and awareness for each activity and also undergo further training by the Quality Assurance Department 9. Working Hours : Site Normal Working Hours. 10. Manpower Requirement & Supervision PE SCE SO - Project Engineer (MACAIR) - Site Commissioning Engineer (BMTS) - Safety Officer (MACAIR)

11. Test Instruments Requirements General Tool box Digital Multimeter 12. Personnel Equipment All Commissioning Engineers and Technicians shall have the necessary Personnel Protective Equipment such as Safety Shoes and Helmet. 13. Distribution Main Contractor Consultant MEP Senior Mechanical Engineer Health and Safety Officer 14. Attachments 14.1 Commissioning Check List 14.2 Risk Assessment.

You might also like