Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

City Center Office Building Addition

Activity ID

Classic Schedule Layout

Activity Name

Original Duration

EC00515 City Center Office

Remaining
Duration

681
Building Addition

EC00515.D&E Design and Engineering


EC1000

Design Building Addition

EC1010

Start Office Building Addition Project

EC1030

Review and Approve Designs

EC1050

Assemble Technical Data for Heat Pump

EC1160

Review Technical Data on Heat Pumps

EC00515.Found Foundation

554

Schedule % Start
Complete

Finish

Total Float
Qtr 4, 2010
Nov

107

16.67% 01-Nov-10 03-Jul-13


A
100% 01-Nov-10 A 06-Apr-11 A

55

100% 01-Nov-10 A 19-Jan-11 A

100% 01-Nov-10 A

22

100% 17-Jan-11 A 17-Feb-11 A

100% 16-Feb-11 A 25-Feb-11 A

27

100% 24-Feb-11 A 06-Apr-11 A

146

98

22.02% 23-Feb-11 A 19-Sep-11

Assemble Technical Data for Heat Pump


175

Site Preparation

43

Excavation

24

24

41.67% 02-May-11

06-Jun-11

127

EC1320

Install Underground Water Lines

12

12

0% 03-Jun-11

21-Jun-11

127

EC1330

Install Underground Electric Conduit

12

12

0% 03-Jun-11

21-Jun-11

127

EC1340

Form/Pour Concrete Footings

24

24

0% 21-Jun-11

26-Jul-11

127

EC1350

Concrete Foundation Walls

24

24

0% 25-Jul-11

26-Aug-11

127

EC1360

Form and Pour Slab

12

12

0% 26-Aug-11

14-Sep-11

127

EC1370

Backfill and Compact Walls

0% 13-Sep-11

19-Sep-11

127

EC1380

Foundation Phase Complete

100% 28-Feb-11 A

Begin Building Construction, 28-Feb-11 A

100% 23-Feb-11 A 18-Apr-11 A

0%

19-Sep-11

178

151

151

0% 19-Sep-11

20-Apr-12

306

25-Nov-11

127

EC1390

Erect Structural Frame

48

48

0% 19-Sep-11

EC1410

Begin Structural Phase

0% 25-Nov-11

EC1420

Floor Decking

34

34

0% 25-Nov-11

13-Jan-12

127

EC1430

Concrete First Floor

36

36

0% 11-Jan-12

01-Mar-12

127

EC1460

Erect Stairwell and Elevator Walls

24

24

0% 01-Mar-12

04-Apr-12

139

EC1470

Concrete Basement Slab

24

24

0% 01-Mar-12

04-Apr-12

139

EC1480

Concrete Second Floor

36

36

0% 01-Mar-12

20-Apr-12

127

EC1540

Structure Complete

0%

20-Apr-12

127

2.63% 14-Apr-11 A 26-Jun-13

418

EC1490

Rough-In Phase Begins

0% 12-Mar-12

EC1690

Rough In Complete

0%

05-Feb-13

218

218

0% 04-Apr-12

12-Feb-13

90

0% 04-Apr-12

06-Apr-12

217

0% 05-Feb-13

EC1520

Install Elevator Rails and Equipment

EC1710

Install Elevator Cab and Finishes

EC00515.Mechanicals.HVAC HVAC

234

12-Feb-13

91

562

549

3.85% 14-Apr-11 A 26-Jun-13

100% 14-Apr-11 A 04-May-11

EC1190

Prepare and Solicit Bids for Heat Pump

15

EC1240

Review Bids for Heat Pump

10

10

79.17% 04-May-11

17-May-11

EC1270

Award Contract for Heat Pump

0% 17-May-11

25-May-11

EC1290

Fabricate and Deliver Heat Pump and Controls


422

422

0% 25-May-11

23-Jan-13

EC1500

Install HVAC Ducts

24

24

0% 12-Mar-12

13-Apr-12

186

EC1630

Insulate Ducts

0% 18-Jun-12

25-Jun-12

140

EC1650

Set Heat Pump

12

12

0% 04-Jan-13

22-Jan-13

EC1670

Relocate HVAC Chiller

0% 22-Jan-13

01-Feb-13

EC1680

Startup and Test HVAC

0% 01-Feb-13

05-Feb-13

EC1770

Install AC Grills and Registers

0% 08-Apr-13

15-Apr-13

23

EC1830

Test and Balance HVAC Equipment

0% 21-Jun-13

26-Jun-13

258

0% 20-Jan-12

23-Jan-13

36

36

0% 20-Jan-12

12-Mar-12

186

0% 24-Aug-12

29-Aug-12

72

36

36

0% 31-Aug-12

23-Oct-12

72

258
EC00515.Mechanicals.Systems Plumbing and Electrical
EC1440

Set Mechanical and Electrical Equipment

EC1510

Rough-In Plumbing/Piping

EC1640

Install Wiring and Cable

Actual Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

summary

Mar

Review and Approve Designs

EC1230

EC00515.Mechanicals.Lifts Elevator

Feb

Design Building Addition

EC1100

549

Jan

Start Office Building Addition Project, 01-Nov-10 A

Begin Building Construction

562Systems
EC00515.Mechanicals Mechanical/Electrical

Qtr 1, 2011
Dec

EC1090

EC00515.Structure Structure

21-Jun-13 11:11

Page 1 of 2

TASK filter: All Activities


Oracle Corporation

City Center Office Building Addition


Activity ID

Classic Schedule Layout

Activity Name
EC1660

Original Duration

Connect Equipment

EC00515.Ex-Finish Exterior Finishes

Remaining
Duration

336

289

Schedule % Start
Complete
0% 22-Jan-13

Total Float
Qtr 4, 2010
Nov

23-Jan-13

43.02% 17-Feb-11 A 19-Jun-12

266

EC1590

Close-In Phase Begins

0% 15-May-12

EC1620

Building Enclosed

0%

312

265

100% 17-Feb-11 A

EC00515.Ex-Finish.Brick Brick

Finish

127

59.15% 17-Feb-11 A 15-May-12

124

Assemble Brick Samples

EC1070

Review and Approve Brick Samples

30

100% 28-Feb-11 A 13-Apr-11 A

EC1180

Prepare and Solicit Bids for Brick Exterior

15

100% 18-Mar-11 A 13-Apr-11 A

EC1220

Review Bids for Brick

15

100% 08-Apr-11 A 28-Apr-11 A

EC1260

Award Contract for Brick

8.33% 21-Apr-11 A 05-May-11

EC1280

Deliver Brick

0% 05-May-11

06-May-11

377

EC1550

Brick Exterior Walls

17

17

0% 20-Apr-12

15-May-12

127

24

24

0% 15-May-12

19-Jun-12

124

24

24

0% 15-May-12

19-Jun-12

127

0% 27-Apr-12

08-May-12

152

0% 27-Apr-12

01-May-12

156

0% 01-May-12

08-May-12

156

EC1600

Insulation and Built-up Roofing

EC00515.Ex-Finish.Win Doors and Windows


EC1560

Install Door and Window Frames

EC1580

Install Exterior Doors and Windows

EC00515.Int-Finish Interior Finishes

601

554

10.68% 25-Feb-11 A 03-Jul-13

36

36

0% 05-Feb-13

27-Mar-13

Touch-up and Clean-up

0% 19-Jun-13

24-Jun-13

EC1840

Finishes Complete

0%

26-Jun-13

EC1850

Punch List

0% 26-Jun-13

03-Jul-13

EC1860

Building Addition Complete

0%

03-Jul-13

44

0% 08-Apr-13

10-Jun-13

EC1760

Install Lighting Fixtures

0% 08-Apr-13

17-Apr-13

21

EC1810

Install Plumbing Fixtures

0% 03-Jun-13

10-Jun-13

581
EC00515.Int-Finish.Coverings Floor and Carpeting

534

20.72% 25-Feb-11 A 04-Jun-13

EC1080

100% 25-Feb-11 A

Review and Approve Flooring

28

100% 25-Feb-11 A 11-Apr-11 A

EC1170

Prepare and Solicit Bids for Flooring

24

100% 04-Apr-11 A 06-May-11

EC1250

Review Bids for Flooring

15

15

36.11% 06-May-11

27-May-11

231

EC1300

Award Contract for Flooring

0% 27-May-11

06-Jun-11

231

EC1310

Fabricate and Deliver Flooring

279

279

0% 03-Jun-11

06-Jul-12

231

EC1790

Install Floor and Carpeting

12

12

0% 16-May-13

04-Jun-13

Assemble and Submit Flooring Samples, 25-Feb


231

59

59

0% 27-Mar-13

19-Jun-13

EC1740

Install Ceiling Grid

36

36

0% 27-Mar-13

16-May-13

EC1800

Finish Carpentry and Millwork

12

12

0% 03-Jun-13

19-Jun-13

12

12

0% 14-Feb-13

04-Mar-13

76

12

12

0% 14-Feb-13

04-Mar-13

77

EC00515.Int-Finish.Carp Carpentry

EC00515.Int-Finish.Paint Paint
EC1720

Paint Building Interior

Actual Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

summary

Mar

Drywall in Offices

Assemble and Submit Flooring Samples

Feb

377

EC1820

EC1060

Jan

Assemble Brick Samples, 17-Feb-11 A

EC1700

EC00515.Int-Finish.Fixtures Plumbing and Lighting44Fixtures

Qtr 1, 2011
Dec

296
18-Jun-12

EC1040

EC00515.Ex-Finish.Roof Roof

21-Jun-13 11:11

Page 2 of 2

TASK filter: All Activities


Oracle Corporation

You might also like