Ove Arup & Partners Hong Kong Ltd.

Job No.

214807

Sheet No.

Rev.

ARUP

Calculation Sheet Member / Location Drg. Ref. Made by NT Tower 6 - Top layer

Job Title Residential Development At Ho Man Tin Transfer plate - Moment Design Design Information: Flange width, bf Web width, bw Section depth, D Flange depth, hf Top clear cover Bottom clear cover Concrete strength Rebar strength Design Moment
Tensile Reinfrocement

Date

13-Jul-13

Chd.

ME

= = = = = = = = =

1000 1000 1200 0 80 80 30 460 2500

mm mm mm mm mm mm Mpa MPa kNm


Compression Reinforcement (Not required)

As, req.

6448.7728 sq.mm

> As, min < As, max

48000 sq.mm Provide

Provide 1st Layer Spacing 2nd Layer Spacing 3rd Layer Spacing 4th Layer Spacing = T = = T = = T = = T = 25 200 32 200 0 200 0 200 5 mm 5 mm 5 mm 5 mm

1st Layer Spacing 2nd Layer Spacing 3rd Layer Spacing As, prov.

= T = = T = = T =

0 5 200 mm 0 5 200 mm 0 5 200 mm sq. mm % > As, req.

= 0 = 0 ==> OK

As, prov.

= 6475.6079 sq. mm = 0.539634 % ==> OK

> As, req.

Ove Arup & Partners Hong Kong Ltd.

Job No.

214807

Sheet No.

Rev.

ARUP

Calculation Sheet Member / Location Drg. Ref. Made by NT Tower 6 - Top layer

Job Title Residential Development At Ho Man Tin Transfer plate - Moment Design Design Information: Flange width, bf Web width, bw Section depth, D Flange depth, hf Top clear cover Bottom clear cover Concrete strength Rebar strength Design Moment
Tensile Reinfrocement

Date

13-Jul-13

Chd.

ME

= = = = = = = = =

1000 1000 1200 0 80 80 30 460 2200

mm mm mm mm mm mm Mpa MPa kNm


Compression Reinforcement (Not required)

As, req.

5499.6634 sq.mm

> As, min < As, max

48000 sq.mm Provide

Provide 1st Layer Spacing 2nd Layer Spacing 3rd Layer Spacing 4th Layer Spacing = T = = T = = T = = T = 32 200 20 200 0 200 0 200 5 mm 5 mm 5 mm 5 mm

1st Layer Spacing 2nd Layer Spacing 3rd Layer Spacing As, prov.

= T = = T = = T =

0 5 200 mm 0 5 200 mm 0 5 200 mm sq. mm % > As, req.

= 0 = 0 ==> OK

As, prov.

= 5592.0349 sq. mm = 0.4660029 % ==> OK

> As, req.

Ove Arup & Partners Hong Kong Ltd.

Job No.

214807

Sheet No.

Rev.

ARUP

Calculation Sheet Member / Location Drg. Ref. Made by NT Tower 6 - Bottom layer

Job Title Residential Development At Ho Man Tin Transfer plate - Moment Design Design Information: Flange width, bf Web width, bw Section depth, D Flange depth, hf Top clear cover Bottom clear cover Concrete strength Rebar strength Design Moment
Tensile Reinfrocement

Date

13-Jul-13

Chd.

ME

= = = = = = = = =

1000 1000 1200 0 80 80 30 460 2500

mm mm mm mm mm mm Mpa MPa kNm


Compression Reinforcement (Not required)

As, req.

6264.7812 sq.mm

> As, min < As, max

48000 sq.mm Provide

Provide 1st Layer Spacing 2nd Layer Spacing 3rd Layer Spacing 4th Layer Spacing = T = = T = = T = = T = 40 200 0 0 0 200 0 200 5 mm 0 mm 5 mm 5 mm

1st Layer Spacing 2nd Layer Spacing 3rd Layer Spacing As, prov.

= T = = T = = T =

0 5 200 mm 0 5 200 mm 0 5 200 mm sq. mm % > As, req.

= 0 = 0 ==> OK

As, prov.

= 6283.1853 sq. mm = 0.5235988 % ==> OK

> As, req.