National Wind Energy Conference
National Wind Energy Conference
Presentation Contents
Introduction to ESBI Engineering Services Provided Total Solution Need for Project Management Case Studies Project Delivery Model Questions
ESBI Engineering
ESBs largest engineering resource Working in a diverse range of Disciplines
Engineering Design Project management Asset Management Support Commissioning Construction Management Safety Management Overhaul Management Etc.
c a r t
ec r k
d or
in r ve i l e d n
l h hig
o c y
ex l p
ity l i ut
ts c je o pr
Services Provided
Wind Farm Concept - Wind Farm Optimisation - EIA and Planning Support - Grid Connections Wind Farm Development Support Programme & Financial Model Tendering & Procurement Financial Close Wind Farm Construction Project Execution Wind Farm O&M Technical Services to operator/owner
Curryfree 15 MW Tullynahaw 22 MW Carrickatane 22.5 MW Crokahenny 5MW West Durham 24 MW Garvagh Glebe 26 MW Black Banks 10.2MW Hunters Hill 20 MW Crockagarran 15 MW
Fullabrook 66 MW
Lessons Learned
Meeting fixed schedules can cost a lot of money Scope M anagement and definition of the scope and WBS has to be undertaken as early as possible Massive failure of stakeholder management
Lesson Learned
Identify key stakeholders. Ignore them at your peril
Avoid Big Bang launches if at all possible; trial days had 2,000; opening day 40,000 passengers If it can go wrong, it will who was m anaging the risk log? Wer e staff, baggage handling, security & car parks on it?
Interfaces
Challenges
Planning Grid Connection 110kV & 20kV Ground Conditions Stakeholder Management Programme & Cost
Planning
GG Received Planning in August 2003 / TW in June 2004 CER Grid Moratorium both required extensions Area of GG was designated NHA post Planning Bird Breeding Season different in Roscommon & Leitrim 110kV OHL and Substation were 1st Project to SIA Micro Siting not allowed flexibility Corderry 110kV Substation
Grid Connection
Critical Path Contestable Connection 5.7km of 110kV OHL SC First SIA Minor Modification Major Risk WTGs erected with no Grid 6.7km 20kV OHL NHA Fibre Wrap Material Issues poles & hardware Weather
January Weather
20kV Interconnector
Designed for radial ice & high wind but. Greater snow, ice and wind than expected
20kV Interconnector
Designed for radial ice & high wind but. Greater snow, ice and wind than expected New design More material problems FO & Construction Crew
Ground Conditions
Deep Peat with 5-7 Deg slope - unusual Peat Slip Completely new approach to Peat Sites Developed a Zonal Peat Stability Assessment (ZPSA) Manage Peat
Lease Agreements Planning Long Term
Stakeholder Management
Public Client
is s i r C in t us
Manage
rm o nf I Expectations ke a M
Know what your options are Know the consequences of each Know the cost of each
Still a Success
Despite the Challenges 3rd Party Issues Project Delivered to revised Schedule & Budget Good news Met Every Challenge Restored Confidence
The Foundation
Combines the vast project delivery experiences of the organisation and our people, with international best practice
Supports our strategy to continue to invest in large scale generation capital projects
Lifecycles
Business Lifecycle Phases
Project Lifecycle
Concept Concept
Development
Develop the the Project Project Develop
Construction Construction
Implement Implement the the Project Project
Operations Operations
plan
plan
initiate
clo se
initiate
clo se
plan
clo se
plan
plan
Multiple Projects
In Conclusion
Spend as much time Planning as Doing Know who your Stakeholders are manage them Understand the Commercial Context of Decisions Keep the Project Moving Forward Dont Panic!