REF (i)
DESCRIPTION Option Modules : a. b. c. Bills of Quantities Unused Materials or Goods Not Delivered to Site Nominated Subcontractors
CLAUSE 1.1(c)
DETAILS
Not Applicable Applicable Not Applicable 1.1(k) See ref (xii) of this Appendix
(ii)
(iii)
1.1(ac)
The Managing Directors, deputy Managing Directors, Project Directors, Vice Presidents or Qualified Persons of Surbana International Consultants Pte. Ltd.. The powers vested in the Superintending Officer under Clause 31 of the Conditions of Contract shall only be exercised by the Managing Directors of Surbana International Consultants Pte. Ltd..
(iv) (v)
Limitations on The Authority of the Superintending Officer Security Deposit : a. Number of days to deposit after Letter of Acceptance (14 days if none stated) b. Quantum
2.1 4.5(1)
Nil
14 days
5% 14.1
(vi)
(vii)
16.1 See ref (xii) of this Appendix The cumulative amount of liquidated damages payable by the contractor for all occasions of delay under the contract shall not exceed $50 million or the Contract Sum, whichever is lower.
APPENDIX TO PUBLIC SECTOR STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION WORKS REF (viii) Insurance a. Limitation on extent of Insurer's liability Percentage for Professional Fees 27.1 $2 million for any one accident and unlimited for the period of insurance. Nil 21 days 7 percent DESCRIPTION CLAUSE DETAILS
b. (ix) (x)
Period for Honouring Certificate (21 days if none stated) Rate of Interest upon Unpaid Sums (5 percent if none stated) Fluctuations
(xi)
33
APPENDIX TO PUBLIC SECTOR STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION WORKS Ref (xii) PART A: BUILDING WORKS AND OTHER INSTALLATIONS AT WOODLANDS N7 C34 (TOTAL 194 DWELLING UNITS)
TIME FOR COMPLETION Within twenty (20) months and fifteen (15) days RATE OF LIQUIDATED DAMAGES Dollars One Thousand Eight Hundred only ($1,800) per day for every day the Works in this Phase remain incomplete Dollars Five Hundred only ($500) per day for every day the Works in this Phase remain incomplete Dollars Six Hundred and Thirty only ($ 630 ) per day for every day the Works in this Phase remain incomplete Dollars Two Thousand and Nine Hundred only ($2,900) per day for every day the Works in this Phase remain incomplete Dollars Three Thousand and Thirty only ($3,030) per day for every day the Works in this Phase remain incomplete Dollars Five Hundred only ($ 500) per day for every day the Works in this Phase remain incomplete Dollars Three Hundred and Sixty only ($360) per day for every day the Works in this Phase remain incomplete DEFECTS LIABILITY PERIOD Twelve ( 12 ) months from Date of Substantial Completion of this Phase Twelve ( 12 ) months from Date of Substantial Completion of this Phase Twelve ( 12 ) months from Date of Substantial Completion of this Phase Twelve ( 12 ) monthsfrom Date of Substantial Completion of this Phase Twelve ( 12 ) months from Date of Substantial Completion of this Phase Twelve ( 12 ) months from Date of Substantial Completion of this Phase Twelve ( 12 ) months from Date of Substantial Completion of this Phase
PHASE/PART OF THE WORKS Phase 1 ESS near to Block 717B Phase 2 Minor Sewer
Within twenty-five (25) months and fifteen (15) days Within twenty-six (26) months and fifteen (15) days Within twenty-seven (27) months and fifteen (15) days Within twenty-eight (28) months and zero (0) days
Phase 6 Driveway, Service Road and CE Drain Phase 7 Remaining Site Structures, Site works, Precinct Pavilion Block 717, EDeck including Plaza, Adult Fitness Corner, Elderly Fitness Corner, Playground, Shelters
Within thirty (30) months and zero (0) days Within thirty (30) months and zero (0) days
PART B:
CONTINGENCY WORKS
TIME FOR COMPLETION As stated in Works Order(s) RATE OF LIQUIDATED DAMAGES
Refer to Section 76 of the Specifications, Clause 76.8
DEFECTS LIABILITY PERIOD Twelve ( 12 ) months from Date of Substantial Completion of the Works Order(s)