DIRECT AND INDIRECT COST BREAK-UP OF BUILDING

(Considering completed project as on 1st Feb' 1998)


RATE/SQM Approximate rounded (In Rs.)

SR. NO. [A] [B] 1 2 [C] 1 2 3 4 5 6 7 8 9 10 11 12

DESCRIPTION LAND COST DIRECT COST Material expenses Labour expenses INDIRECT COST Sanction Expenses Plot Development Site Development Consultancy Expenses Administrative Expenses Supervision Expenses Site Running Expenses Add 1.50% Contingencies On Total (B)

COST PERCENTAGE

2582.40 936.12 75.32 21.52 107.60 64.56 86.08 64.56 43.04 52.78

64.02% 23.21% 1.87% 0.53% 2.67% 1.60% 2.13% 1.60% 1.07% 1.31%

TOTAL COST ( B + C )

4033.98

100.00%

USER NOTES : 1. Land Cost will be as per Actual cost based on location. 2. You can feed required data in respective cells. 3. You can modify as per your requirements. 4. You can save modified file in your computer. 5. You can take Printout now or from saved file. 6.To get the printout of "Pia-chart", select chart area (given below) and check print preview. 7. If you add new entries, to incarporate in "Pia-chart" please drag the graph range upto the required.

DIRECT & INDIRECT COST BREAK-UP OF BUILDING

23.21% 64.02%

1.87% 0.53% 2.67% 1.31% 1.07% 1.60% 1.60% 2.13%

Material expenses

Labour expenses

Sanction Expenses

Plot Development Administrative Expenses


Add 1.50% Contingencies On Total (B)

Site Development Supervision Expenses

Consultancy Expenses Site Running Expenses

DIRECT AND INDIRECT COST BREAK-UP OF BUILDING


(Considering completed project as on 1st Feb' 1998)
RATE/SFT Approximate rounded (In Rs.)

SR. NO. [A] [B] 1 2 [C] 1 2 3 4 5 6 7 8

DESCRIPTION LAND COST DIRECT COST Material expenses Labour expenses INDIRECT COST Sanction Expenses Plot Development Site Development Consultancy Expenses Administrative Expenses Supervision Expenses Site Running Expenses Add 1.50% Contingencies On Total (B)

COST PERCENTAGE

240.00 87.00 7.00 2.00 10.00 6.00 8.00 6.00 4.00 5.00

64.00% 23.20% 1.87% 0.53% 2.67% 1.60% 2.13% 1.60% 1.07% 1.33%

TOTAL COST ( B + C )

375.00

100.00%

USER NOTES : 1. Land Cost will be as per Actual cost based on location. 2. You can feed required data in respective cells. 3. You can modify as per your requirements. 4. You can save modified file in your computer. 5. You can take Printout now or from saved file. 6.To get the printout of "Pia-chart", select chart area (given below) and check print preview. 7. If you add new entries, to incarporate in "Pia-chart" please drag the graph range upto the required.

DIRECT & INDIRECT COST BREAK-UP OF BUILDING


23.20% 64.00%

1.87%

2.67%

2.13% 1.33% 1.07% 1.60%

Material expenses Plot Development Administrative Expenses Add 1.50% Contingencies On Total (B)

Labour expenses Site Development Supervision Expenses

Sanction Expenses Consultancy Expenses Site Running Expenses

1.87% 0.53% 2.67% 1.60%