Professional Documents
Culture Documents
NEC 3 - When Is The Project Manager Obliged To Notify A Compensation Event, and What Are The Effects of His Failure To Do So
NEC 3 - When Is The Project Manager Obliged To Notify A Compensation Event, and What Are The Effects of His Failure To Do So
NEC 3: when is the project manager obliged to notify a compensation event, and what are the effects of his failure to do so? | MDA Consulting
Home (http://www.mdaconsulting.co.za/) About (http://www.mdaconsulting.co.za/about/) Project Structuring and Procurement Management (http://www.mdaconsulting.co.za/projectstructuring-and-procurement-management/)
Events (http://www.mdaconsulting.co.za/kloof-to-the-crossroads/) Training (http://www.mdaconsulting.co.za/training/) MDA Publications (http://www.mdaconsulting.co.za/articles/) Contact Us (http://www.mdaconsulting.co.za/contact-us/) Links (http://www.mdaconsulting.co.za/links/)
NEC 3: when is the project manager obliged to notify a compensation event, and what are the effects of his failure to do so?
Introduction
Time bar clauses that are found in the standard form construction contracts (almost) always operate against the contractor. Hopefully we are all aware of the consequences of failing to comply with a time bar clause/s in a construction contract. However, the NEC is a change from this norm and it exonerates the contractor in certain circumstance and then shifts some risks onto the shoulders of the project manager for failing to respond to the contractor.
7/9/13
NEC 3: when is the project manager obliged to notify a compensation event, and what are the effects of his failure to do so? | MDA Consulting
to a communication with the period for reply, (7) instructions for objects of value or of historical content, (8) changes a decision, (9) withholds an acceptance, (10) search for a defect and no defect is found, (11) test or inspection done by the supervisor causes an unnecessary delay, (15) the project manager certifies take over or a part of the works before both completion and the completion date, and (17) the project notifies a correction to an assumption stated about a compensation event. Sub-clause 61.3 places a duty on the contractor to notify the project manager of a compensation event which has happened or which he expects to happen as a compensation event if (i) the contractor believes that the event is a compensation event and (ii) the project manager has not notified the contractor of the event. Even if the compensation event does not strictly originate from the project manager, he has an obligation to notify these also, like a weather delay in terms of the early warning procedure and then also a subsequent compensation event as the project manager cannot argue that didnt know that it may or may not have a time and cost impact
7/9/13
NEC 3: when is the project manager obliged to notify a compensation event, and what are the effects of his failure to do so? | MDA Consulting
Conclusion
From the above we note that, where the project manager should have notified a compensation event and did not, the contractor is exonerated from the time bar provisions and it may still claim a change in the prices and/or the completion date. This gives action to the above stated principle function of the compensation events which is to reduce the incidence of the risks by application of collaborative foresight. Where the project manager fails to respond to a quotation for a compensation event from the contractor within two weeks after a further notice from the contractor, it bears the risk that the quotation will be treated as accepted after the expiry of the period and is then be liable to pay the contractors quotation in full.
The General Conditions of Conditions Contract for Civil Engineering Works 2010 (GCC 2010): whats new? (http://www.mdaconsulting.co.za/the-general-conditions-of-conditions-contract-for-civil-engineering-works2010-%e2%80%98gcc-2010%e2%80%99-what%e2%80%99s-new/)
FAFC: Getting over a time bar (http://www.mdaconsulting.co.za/fafc-getting-over-a-time-bar/) Home (?page_id=6) | Terms & Conditions (?page_id=69) | Privacy (?page_id=71) | Site Admin (wpadmin) | (http://www.mdaconsulting.co.za/feed/) RSS (http://www.mdaconsulting.co.za/feed/)
www.mdaconsulting.co.za/nec-3-when-is-the-project-manager-obliged-to-notify-a-compensation-event-and-what-are-the-effects-of-his-failure-to-do-so/
3/3