KDL Project
Activity ID
Activity Name
RD
Start
2013
Finish
Sep
14
GENERAL
CONCEPT ENGINEERING
ENGINEERING & MANAGEMENT
ENGINEERING MANAGEMENT
30ECED1090 Vendor Document Requirement List
50
12-Aug-11 A
30-Nov-12
22
12-Aug-11 A
22-Oct-12
22
12-Aug-11 A
22-Oct-12
10
10
12-Aug-11 A
15-Aug-11 A
04-Oct-12
04-Oct-12
Oct
15
Nov
16
12-Aug-11 A
21-Sep-12
10
12-Aug-11 A
04-Oct-12
22
15
15-Aug-11 A
21-Sep-12
22-Oct-12
11-Oct-12
49ECED2010
Escape Route
10
21-Sep-12
04-Oct-12
49ECED2090
22
21-Sep-12
22-Oct-12
C...
49ECED3020
22
15-Aug-11 A
22-Oct-12
W...
29
26-Aug-11 A
31-Oct-12
3...
29
05-Sep-11 A
31-Oct-12
3...
29
29
20
05-Sep-11 A
05-Sep-11 A
16-Sep-11 A
31-Oct-12
31-Oct-12
18-Oct-12
3...
3...
20
10-Oct-11 A
18-Oct-12
41ECED1240
10
31-Jan-12 A
04-Oct-12
41ECED1250
31-Jan-12 A
08-Oct-12
I...
41ECED1260
31-Jan-12 A
08-Oct-12
I...
41ECED1270
31-Jan-12 A
08-Oct-12
I...
41ECED1320
28
19-Sep-11 A
31-Oct-12
41ECED1322
28
05-Sep-11 A
31-Oct-12
15
26-Aug-11 A
11-Oct-12
1...
15
15
10
26-Aug-11 A
26-Aug-11 A
06-Sep-11 A
11-Oct-12
11-Oct-12
04-Oct-12
1...
1...
T...
R...
I...
R...
W...
02-Apr-12 A
11-Oct-12
P...
44EGEN1052
15
26-Aug-11 A
11-Oct-12
W...
25
13-Dec-11 A
25-Oct-12
5
5
5
13-Dec-11 A
13-Dec-11 A
17-Dec-11 A
27-Sep-12
27-Sep-12
27-Sep-12
2...
2...
S...
2...
42ESWI1030
27-Sep-12
S...
42ESWI1040
13-Dec-11 A
27-Sep-12
W...
25
25
10
17-Jul-12 A
17-Jul-12 A
21-Sep-12
25-Oct-12
25-Oct-12
04-Oct-12
F...
F...
10
21-Sep-12
04-Oct-12
42EFFP1040
22
21-Sep-12
22-Oct-12
42EPHS1040
25
17-Jul-12 A
25-Oct-12
42EPHS1050
10
21-Sep-12
04-Oct-12
12
21-Sep-12
08-Oct-12
Actual Work
Milestone
Remaining Work
Summary
Oct
27
I...
44ECED1310
Sep
26
P...
41ECED1200
42EFFP1005
Aug
25
E...
04-Oct-12
Jul
24
2...
27-Jan-12 A
Jun
23
P...
10
UTILITIES PACKAGES
May
22
W...
GENERAL
ARCHITECTURAL
44ECED1070 Technical Specification For Landscaping Works
Apr
21
L...
41ECED1190
BUILDINGS
Mar
20
2...
GENERAL
Feb
19
0...
V...
30ECED1210
DETAIL ENGINEERING
Jan
18
2...
30ECED1200
PROCESS
49ECED1020
Dec
17
3...
2...
2...
W...
W...
S...
0...
Page 1 of 13
PP - Imeco
3 Weeks Look Ahead Schedule 120 MW CCPP
KDL Project
Activity ID
Activity Name
RD
Start
2013
Finish
Sep
14
12
5
21-Sep-12
21-Sep-12
08-Oct-12
27-Sep-12
Oct
15
0...
W...
28-Sep-12
01-Oct-12
W...
02-Oct-12
08-Oct-12
W...
12
21-Sep-12
08-Oct-12
W...
12
12
5
21-Sep-12
21-Sep-12
21-Sep-12
08-Oct-12
08-Oct-12
27-Sep-12
0...
0...
W...
28-Sep-12
01-Oct-12
W...
42EWST1020 Water Storage Tank - Issued for Client Review & Approved
02-Oct-12
08-Oct-12
W...
12
21-Sep-12
08-Oct-12
W...
12
12
10
27-Jun-12 A
27-Jun-12 A
21-Sep-12
08-Oct-12
08-Oct-12
04-Oct-12
CONCRETE
42EWWT1000 WWTP - Plan & Section
Nov
16
21-Sep-12
24-Sep-12
42ENTT1020
10
25-Sep-12
08-Oct-12
N...
42ENTT1040
12
27-Jun-12 A
08-Oct-12
W...
27
07-Dec-11 A
29-Oct-12
2...
27
27
21
07-Dec-11 A
07-Dec-11 A
21-Sep-12
29-Oct-12
29-Oct-12
19-Oct-12
2...
2...
26
07-Dec-11 A
29-Oct-12
25
10-Feb-12 A
25-Oct-12
2...
25
25
25
10-Feb-12 A
10-Feb-12 A
10-Feb-12 A
25-Oct-12
25-Oct-12
25-Oct-12
2...
2...
D...
PIPERACK
STRUCTURAL STEEL
43EPIR1030
Issued for Client Review & Approved
43EPIR1050
EPC CONTRACTOR
GENERAL
GENERAL
00EGEN1010
01-Sep-11 A
30-Nov-12
01-Sep-11 A
18-Oct-12
31
07-Dec-11 A
02-Nov-12
50
24-Apr-12 A
30-Nov-12
46
15-Dec-11 A
25-Nov-12
TRANSFORMER
HYBRID GIS 150KV SWITCHYARD
11
01-Aug-12 A
06-Oct-12
15
09-Apr-12 A
11-Oct-12
BALANCE of PLANT
26
09-Feb-12 A
26-Oct-12
07-Jul-12 A
29-Sep-12
2...
07-Jul-12 A
29-Sep-12
2...
6
10
07-Jul-12 A
07-Jul-12 A
29-Sep-12
29-Sep-12
2...
F...
17-Jul-12 A
26-Aug-12 A
STRUCTURAL STEEL
STPGT1058
Fabrication Structural Steel by KE for GTG Power Building
STPGT1059
STPGT1060
TRAIN 1
GAS TURBINE GENERATOR
GTG
CONCRETE
42CGTG1030 GTG 1 Finish foundation
Actual Work
Milestone
Remaining Work
Summary
21-Sep-12
Apr
21
May
22
Jun
23
Jul
24
Aug
25
Sep
26
Oct
27
W...
19
STRUCTURAL STEEL
Mar
20
I...
50
Feb
19
N...
SUPPLY BY KPI
Jan
18
0...
0...
N...
42ENTT1010
Dec
17
3...
1...
0...
3...
2...
0...
1...
2...
F...
R...
56
19-Jun-12 A
08-Dec-12
0...
56
19-Jun-12 A
08-Dec-12
0...
56
19-Jun-12 A
08-Dec-12
6
0
19-Jun-12 A
29-Sep-12
29-Sep-12
0...
2...
G...
Page 2 of 13
PP - Imeco
3 Weeks Look Ahead Schedule 120 MW CCPP
KDL Project
Activity ID
Activity Name
RD
Start
2013
Finish
Sep
14
Oct
15
G...
Nov
16
Dec
17
19-Jun-12 A
25-Sep-12
11
14
26-Sep-12
28-Sep-12
11-Oct-12
11-Oct-12
1...
G...
14
26-Sep-12*
09-Oct-12
I...
56
0
27-Aug-12 A
01-Oct-12
08-Dec-12
10
27-Aug-12 A
29-Sep-12
71
01-Oct-12
08-Dec-12
10
25-Sep-12
09-Oct-12
10
0
25-Sep-12
09-Oct-12
25-Sep-12
F...
26-Sep-12
26-Sep-12
J...
14
26-Sep-12
09-Oct-12
TRANSFORMER GTG
32
29-Jun-12 A
05-Nov-12
0...
TRANSFORMER GTG
32
29-Jun-12 A
05-Nov-12
0...
29-Jun-12 A
21-Sep-12
05-Nov-12
32
0
44
29-Jun-12 A
05-Nov-12
19
14-Jul-12 A
21-Nov-12
2...
19
14-Jul-12 A
21-Nov-12
2...
19
25
14-Jul-12 A
14-Jul-12 A
21-Nov-12
21-Nov-12
2...
H...
WHRB BYPASS
16
04-Sep-12 A
13-Oct-12
BYPASS STACK
16
04-Sep-12 A
13-Oct-12
STRUCTURAL STEEL
43CBYS1000 Installation of Support
3
5
04-Sep-12 A
04-Sep-12 A
25-Sep-12
25-Sep-12
MECHANICAL
45CBYS1000
16
25
10-Sep-12 A
10-Sep-12 A
13-Oct-12
13-Oct-12
45CBYS1030
14-Sep-12 A
22-Sep-12
45CBYS1090
25-Sep-12
25-Sep-12
I...
45CBYS1100
26-Sep-12
26-Sep-12
I...
45CBYS1110
16-Sep-12 A
27-Sep-12
I...
45CBYS1120
Seal Welding
27-Sep-12
29-Sep-12
S...
45CBYS1130
29-Sep-12
02-Oct-12
I...
45CBYS1140
02-Oct-12
03-Oct-12
R...
45CBYS1150
03-Oct-12
04-Oct-12
R...
45CBYS1160
Cleaning
04-Oct-12
04-Oct-12
C...
PIPING
46CBYS1000
11
18
21-Sep-12
21-Sep-12
08-Oct-12
08-Oct-12
ELECTRICAL
47CBYS1000
15
24
21-Sep-12
21-Sep-12
13-Oct-12
13-Oct-12
56
19-Jun-12 A
08-Dec-12
0...
56
19-Jun-12 A
08-Dec-12
0...
56
19-Jun-12 A
08-Dec-12
0...
STRUCTURAL STEEL
43CGTG1000 GTG 1 Main Building Structural Installation
43CGTG1020 Installation of GTG 1 Inlet Duct Supports Structure
MECHANICAL
45CGTG1005 Ready for GTG 1 set on base
CONCRETE
00CGTT1000
42CGTT1010
TRAIN 2
GAS TURBINE GENERATOR
GTG
Actual Work
Milestone
Remaining Work
Summary
Jan
18
Feb
19
Mar
20
Apr
21
May
22
Jun
23
Jul
24
Aug
25
Sep
26
Oct
27
0...
R...
I...
I...
0...
0...
I...
0...
S...
T...
1...
1...
2...
I...
1...
I...
I...
0...
I...
1...
I...
Page 3 of 13
PP - Imeco
3 Weeks Look Ahead Schedule 120 MW CCPP
KDL Project
Activity ID
Activity Name
RD
Start
2013
Finish
Sep
14
Oct
15
2...
G...
Nov
16
Dec
17
6
0
19-Jun-12 A
29-Sep-12
29-Sep-12
19-Jun-12 A
25-Sep-12
7
9
28-Sep-12
28-Sep-12
09-Oct-12
06-Oct-12
0...
G...
10
01-Oct-12
09-Oct-12
I...
56
0
30-Aug-12 A
01-Oct-12
08-Dec-12
10
30-Aug-12 A
29-Sep-12
71
01-Oct-12
08-Dec-12
10
25-Sep-12
09-Oct-12
10
0
25-Sep-12
09-Oct-12
25-Sep-12
F...
26-Sep-12
26-Sep-12
J...
14
26-Sep-12
09-Oct-12
TRANSFORMER GTG
32
02-Jul-12 A
05-Nov-12
0...
TRANSFORMER GTG
32
02-Jul-12 A
05-Nov-12
0...
02-Jul-12 A
21-Sep-12
05-Nov-12
32
0
44
02-Jul-12 A
05-Nov-12
43
14-Jul-12 A
21-Nov-12
2...
43
14-Jul-12 A
21-Nov-12
2...
14-Jul-12 A
21-Sep-12
21-Nov-12
43
0
CONCRETE
42CGTG2030 GTG 2 Finish Foundation
42CGTG2040 GTG 2 Foundation Misc Equipment
STRUCTURAL STEEL
43CGTG2000 GTG 2 Main Building Structural Installation
43CGTG2020 Installation of GTG 2 Inlet Duct Supports Structure
MECHANICAL
45CGTG2005 Ready for GTG 2 set on base
CONCRETE
00CGTT2000
42CGTT2010
14-Jul-12 A
21-Nov-12
08-Sep-12 A
06-Nov-12
BYPASS STACK
Aug
25
Sep
26
Oct
27
I...
0...
0...
I...
0...
T...
2...
H...
0...
08-Sep-12 A
06-Nov-12
08-Sep-12 A
08-Sep-12 A
25-Sep-12
25-Sep-12
MECHANICAL
45CBYS2000
16
25
14-Sep-12 A
21-Sep-12
13-Oct-12
13-Oct-12
45CBYS2030
14-Sep-12 A
25-Sep-12
I...
45CBYS2090
25-Sep-12
25-Sep-12
I...
45CBYS2100
26-Sep-12
26-Sep-12
I...
45CBYS2110
16-Sep-12 A
27-Sep-12
I...
45CBYS2120
Seal Welding
27-Sep-12
29-Sep-12
S...
45CBYS2130
29-Sep-12
02-Oct-12
I...
45CBYS2140
02-Oct-12
03-Oct-12
R...
45CBYS2150
03-Oct-12
04-Oct-12
R...
45CBYS2160
Cleaning
04-Oct-12
04-Oct-12
C...
PIPING
46CBYS2000
25
36
02-Oct-12
02-Oct-12
06-Nov-12
06-Nov-12
ELECTRICAL
47CBYS2000
16
24
02-Oct-12
02-Oct-12
24-Oct-12
24-Oct-12
69
27-May-12 A
27-Dec-12
Summary
Jul
24
I...
3
5
Remaining Work
Jun
23
0...
32
Milestone
May
22
G...
STRUCTURAL STEEL
43CBYS2000 Installation of Support Structure
Apr
21
S...
32
Actual Work
Mar
20
S...
25
Feb
19
R...
WHRB BYPASS
Jan
18
0...
2...
I...
1...
I...
0...
I...
2...
I...
2...
Page 4 of 13
PP - Imeco
3 Weeks Look Ahead Schedule 120 MW CCPP
KDL Project
Activity ID
Activity Name
RD
Start
2013
Finish
Sep
14
69
27-May-12 A
27-Dec-12
Jan
18
2...
69
27-May-12 A
27-Dec-12
2...
69
31
27-May-12 A
27-Jun-12 A
27-Dec-12
06-Dec-12
42CSTG1010
50
27-May-12 A
27-Dec-12
42CSTG1014
20
26-Sep-12
11-Oct-12
42CSTG1016
Oct
15
Nov
16
Dec
17
28-Sep-12
17-Oct-12
17-Oct-12
TRANSFORMER STG
32
14-Jul-12 A
05-Nov-12
0...
TRANSFORMER STG
32
14-Jul-12 A
05-Nov-12
0...
14-Jul-12 A
21-Sep-12
05-Nov-12
32
0
44
14-Jul-12 A
05-Nov-12
47
05-Jun-12 A
27-Nov-12
2...
PIPE RACK
47
05-Jun-12 A
27-Nov-12
2...
Pipe Rack
47
05-Jun-12 A
27-Nov-12
05-Jun-12 A
05-Jun-12 A
03-Oct-12
03-Oct-12
27-Nov-12
21-Sep-12
T...
2...
47
0
05-Sep-12 A
42CHRS1050
20
05-Sep-12 A
27-Nov-12
42CHRS2050
24
03-Oct-12
25-Oct-12
42CPIR1010
39
03-Oct-12
09-Nov-12
42CSTG1030
34
03-Oct-12
05-Nov-12
18
10-Sep-12 A
17-Oct-12
1...
14
10-Sep-12 A
17-Oct-12
1...
14
0
10-Sep-12 A
27-Sep-12
17-Oct-12
20
10-Sep-12 A
16-Oct-12
20
10-Sep-12 A
17-Oct-12
16
21-Sep-12
13-Oct-12
0...
P...
2...
P...
F...
F...
F...
F...
1...
S...
F...
F...
1...
CIVIL
41CVST1000
1
2
21-Sep-12
21-Sep-12
22-Sep-12
22-Sep-12
CONCRETE
42CVST1000
15
10
22-Sep-12
04-Oct-12
13-Oct-12
13-Oct-12
12
22-Sep-12*
04-Oct-12
7
10
04-Oct-12
04-Oct-12
13-Oct-12
13-Oct-12
23
27-Sep-12
30-Oct-12
3...
23
27-Sep-12
30-Oct-12
3...
Earthworks - excavation
23
30
27-Sep-12
28-Sep-12*
30-Oct-12
25-Oct-12
3...
E...
27-Sep-12
04-Oct-12
42CVST1020
MECHANICAL
45CVST1000
COOLING WATER
SEA WATER INTAKE & DISCHARGE
CIVIL
41CSWI1000
41CSWI1005
Actual Work
Milestone
Remaining Work
Summary
Oct
27
0...
VENT STACK
Sep
26
S...
CONCRETE
00CPIR1000
CONCRETE
00CGCM1000 Start Concrete Foundation of Compressor Package
Aug
25
1...
I...
8
13
Jul
24
P...
CIVIL
41CPIR1000
Jun
23
S...
01-Oct-12
01-Oct-12
42CSTT1020
May
22
P...
20-Jul-12 A
BALANCE OF PLANT
Apr
21
2...
CONCRETE
42CSTT1000
Mar
20
S...
13
18
STRUCTURAL STEEL
43CSTG1000 Installation of Structural Steel STG Building
Feb
19
2...
V...
1...
C...
C...
1...
I...
P...
Page 5 of 13
PP - Imeco
3 Weeks Look Ahead Schedule 120 MW CCPP
KDL Project
Activity ID
Activity Name
RD
Start
2013
Finish
Sep
14
41CSWI1010
CONCRETE
42CSWI1020
42CSWI1024
Oct
15
Nov
16
S...
Dec
17
Sand Bedding
30
01-Oct-12
30-Oct-12
15
22
04-Oct-12
04-Oct-12
24-Oct-12
24-Oct-12
2...
F...
22
04-Oct-12
24-Oct-12
F...
46
21-Sep-12
23-Nov-12
42
21-Sep-12
19-Nov-12
1...
42
60
21-Sep-12
21-Sep-12*
19-Nov-12
19-Nov-12
1...
F...
45
21-Sep-12
22-Nov-12
20
0
21-Sep-12
21-Sep-12
18-Oct-12
30
21-Sep-12*
18-Oct-12
45
45
21-Sep-12
21-Sep-12
22-Nov-12
22-Nov-12*
2...
F...
41
27-Sep-12
23-Nov-12
2...
41
0
27-Sep-12
27-Sep-12
23-Nov-12
41
27-Sep-12
23-Nov-12
27-Sep-12
09-Oct-12
0...
8
10
27-Sep-12
27-Sep-12
09-Oct-12
06-Oct-12
0...
E...
PROCESS WATER
SERVICE WATER & FIRE FIGHTING PACKAGE
CONCRETE
42CPSW1020 Foundation for Tank
04-Oct-12
15
21-Sep-12
04-Oct-12
15
27-Sep-12
18-Oct-12
1...
COMPRESSED AIR
15
27-Sep-12
18-Oct-12
1...
CONCRETE
00CCAP1000
27-Sep-12
27-Sep-12
18-Oct-12
15
0
42CCAP1005
22
27-Sep-12
18-Oct-12
42CCAP1010
22
27-Sep-12
18-Oct-12
15
21-Sep-12
11-Oct-12
1...
W...
0...
S...
F...
1...
S...
F...
F...
15
21-Sep-12
11-Oct-12
1...
10
15
27-Sep-12
27-Sep-12*
11-Oct-12
11-Oct-12
1...
C...
PIPING
46CTWS1000 Installation of Turbine Washing Skid Pipe
10
15
21-Sep-12
21-Sep-12
04-Oct-12
04-Oct-12
51
06-Sep-12 A
03-Dec-12
0...
51
06-Sep-12 A
03-Dec-12
0...
51
06-Sep-12 A
03-Dec-12
0...
06-Sep-12 A
04-Oct-12
03-Dec-12
51
0
Switchyard - Piling
06-Sep-12 A
03-Oct-12
CONCRETE
00CSIY1002
42CSIY1000
Actual Work
Milestone
Remaining Work
Summary
Oct
27
0...
CONCRETE
42CTWS1000 Concrete Foundation Turbine Washing Skid
Sep
26
F...
21-Sep-12
21-Sep-12
150KV SWITCHYARD
Aug
25
2...
10
0
SWITCHYARD
Jul
24
S...
04-Oct-12
Jun
23
F...
09-Oct-12
RECOVERY PITS
May
22
S...
21-Sep-12
Apr
21
2...
03-Oct-12
Mar
20
1...
CONCRETE
00CCWT1000 Start Concrete Foundation of Condensate Make Up Water Tank
Feb
19
2...
10
Jan
18
0...
I...
0...
S...
S...
Page 6 of 13
PP - Imeco
3 Weeks Look Ahead Schedule 120 MW CCPP
KDL Project
Activity ID
Activity Name
RD
Start
2013
Finish
Sep
14
Oct
15
Nov
16
C...
Dec
17
42CSIY1010
45
22-Sep-12
05-Nov-12
42CSIY1020
60
04-Oct-12
03-Dec-12
51
14-Nov-11 A
03-Dec-12
SITE FACILITIES
29
14-Nov-11 A
31-Oct-12
3...
SITE FACILITIES
29
14-Nov-11 A
31-Oct-12
3...
29
7
14-Nov-11 A
27-Dec-11 A
31-Oct-12
27-Sep-12
20
14-Nov-11 A
09-Oct-12
33
21-Sep-12
20-Oct-12
41CSIT1010
10
15-Mar-12 A
31-Oct-12
29
01-Jun-12 A
03-Dec-12
0...
29
01-Jun-12 A
03-Dec-12
0...
29
40
01-Jun-12 A
01-Jun-12 A
03-Dec-12
03-Dec-12
0...
D...
31
30-Aug-12 A
03-Nov-12
22
30-Aug-12 A
23-Oct-12
2...
22
34
30-Aug-12 A
30-Aug-12 A
23-Oct-12
23-Oct-12
2...
I...
21
13-Sep-12 A
24-Oct-12
2...
21
0
13-Sep-12 A
25-Sep-12
24-Oct-12
31
13-Sep-12 A
24-Oct-12
31
21-Sep-12
03-Nov-12
21-Sep-12
21-Sep-12
03-Nov-12
31
0
46
21-Sep-12
03-Nov-12
52
08-May-12 A
03-Dec-12
30
29-Jun-12 A
01-Nov-12
0...
30
29-Jun-12 A
01-Nov-12
0...
30
30
20
29-Jun-12 A
29-Jun-12 A
29-Jun-12 A
01-Nov-12
01-Nov-12
13-Oct-12
0...
0...
20
23-Jul-12 A
01-Nov-12
F...
29
21-Sep-12
31-Oct-12
3...
29
29
7
21-Sep-12
21-Sep-12
21-Sep-12
31-Oct-12
31-Oct-12
28-Sep-12
3...
3...
KE-42CHRS1070
F ormwork
29-Sep-12
03-Oct-12
F...
KE-42CHRS1080
Pouring Concrete K-450
02-Oct-12
03-Oct-12
P...
KE-42CHRS1090
Q A/QC Check List (t Reinforcement, Formwork, elevation, centre line)
02-Oct-12
03-Oct-12
Q...
02-Oct-12
03-Oct-12
W...
KE-42CHRS1110Curring Time
28
04-Oct-12
31-Oct-12
C...
30
02-Jul-12 A
01-Nov-12
0...
30
02-Jul-12 A
01-Nov-12
0...
SITE INFRASTRUCTURE
CIVIL
41CGEN1015 Soil Improvement by Owner
BUILDINGS
EB, AD MIN & CCB BUILD ING
STRUCTURAL STEEL
43CCCB1000 Installation of Structural Steel for Electrical & Control Building
Analyzer Building
CONCRETE
00CANB1001
42CANB1020
OWNER SCOPE
TRAIN 1
TRANSFORMER
TRANSFORMER GTG
CONCRETE
KE-42GTT1140 Reinforcement pedetal+ wall
KE-42GTT1150 Formwork pedestal+wall
TRAIN 2
TRANSFORMER
Actual Work
Milestone
Remaining Work
Summary
Jan
18
Feb
19
Mar
20
Apr
21
May
22
Jun
23
Jul
24
Aug
25
Sep
26
Oct
27
C...
0...
3...
S...
T...
T...
I...
0...
2...
S...
C...
0...
0...
S...
C...
0...
R...
R...
Page 7 of 13
PP - Imeco
3 Weeks Look Ahead Schedule 120 MW CCPP
KDL Project
Activity ID
Activity Name
RD
Start
2013
Finish
Sep
14
Oct
15
Nov
16
0...
0...
Dec
17
TRANSFORMER GTG
CONCRETE
KE-42GTT2140 Reinforce pedestal+wall
30
30
20
02-Jul-12 A
02-Jul-12 A
02-Jul-12 A
01-Nov-12
01-Nov-12
13-Oct-12
20
27-Jul-12 A
01-Nov-12
F...
29
21-Sep-12
31-Oct-12
3...
29
29
7
21-Sep-12
21-Sep-12
21-Sep-12
31-Oct-12
31-Oct-12
28-Sep-12
3...
3...
KE-42CHRS2070
F ormwork
29-Sep-12
03-Oct-12
F...
KE-42CHRS2080
Q A/QC Check List (t Reinforcement, Formwork, elevation, centre line)
02-Oct-12
03-Oct-12
Q...
KE-42CHRS2090
W ork permit
02-Oct-12
03-Oct-12
W...
KE-42CHRS2100
Pouring Concrete K-450
02-Oct-12
03-Oct-12
P...
KE-42CHRS2110Curring Time
28
04-Oct-12
31-Oct-12
41
27-Jun-12 A
17-Nov-12
1...
41
27-Jun-12 A
17-Nov-12
1...
41
21
27-Jun-12 A
02-Jul-12 A
17-Nov-12
15-Oct-12
24
03-Jul-12 A
18-Oct-12
23
27-Jun-12 A
17-Nov-12
52
16-Jul-12 A
03-Dec-12
29
20-Jul-12 A
31-Oct-12
DRAWING
GENERAL
KE-00CGCM0000
Shop drawing
25
25
30
21-Sep-12
21-Sep-12
21-Sep-12
25-Oct-12
25-Oct-12
25-Oct-12
PREPARATION
CONCRETE
KE-42CGCM0020
backfill
1
1
1
20-Jul-12 A
20-Jul-12 A
20-Jul-12 A
21-Sep-12
21-Sep-12
21-Sep-12
29
29
34
10-Sep-12 A
10-Sep-12 A
21-Sep-12
31-Oct-12
31-Oct-12
31-Oct-12
KE-42CGCM1030
Reinforcement footing
13
11-Sep-12 A
05-Oct-12
R...
KE-42CGCM1040
Formworks footing
13
10-Sep-12 A
05-Oct-12
F...
38
21-Sep-12
13-Nov-12
1...
38
38
45
21-Sep-12
21-Sep-12
21-Sep-12
13-Nov-12
13-Nov-12
13-Nov-12
1...
1...
S...
30
03-Oct-12
08-Nov-12
52
21-Sep-12
03-Dec-12
0...
52
52
60
21-Sep-12
21-Sep-12
21-Sep-12
03-Dec-12
03-Dec-12
03-Dec-12
0...
0...
S...
42
29-Sep-12
28-Nov-12
2...
42
42
48
29-Sep-12
29-Sep-12
29-Sep-12
28-Nov-12
28-Nov-12
28-Nov-12
2...
2...
S...
16-Jul-12 A
27-Sep-12
BALANCE OF PLANT
GAS COMPRESSOR & METERING
COOLING WATER
SEA WATER INTAKE & DISCHARGE
PIPING
KE-46CSWI1001Shop Drawing Auxiliary Cooling water
KE-46CSWI1011Shop Drawing Main Cooling water
PROCESS WATER
SERVICE WATER PACKAGE
PIPING
KE-46CPSW0000
Shop Drawing
Actual Work
Milestone
Remaining Work
Summary
Jan
18
Feb
19
Mar
20
Apr
21
May
22
Jun
23
Jul
24
Aug
25
Sep
26
Oct
27
R...
R...
C...
1...
F...
R...
F...
0...
3...
2...
2...
S...
2...
2...
b...
3...
3...
F...
S...
2...
Page 8 of 13
PP - Imeco
3 Weeks Look Ahead Schedule 120 MW CCPP
KDL Project
Activity ID
Activity Name
RD
Start
2013
Finish
Sep
14
Oct
15
FLOOR
CONCRETE
KE-42WORP1150
Install Water Proofin g
1
1
1
18-Jul-12 A
18-Jul-12 A
18-Jul-12 A
21-Sep-12
21-Sep-12
21-Sep-12
2...
2...
I...
WALL
CONCRETE
KE-42WORP1220
Formwork
5
5
2
16-Jul-12 A
16-Jul-12 A
16-Jul-12 A
27-Sep-12
27-Sep-12
22-Sep-12
2...
2...
F...
KE-42WORP1230
QA/QC check list ( Reinforcement, Formwork, elevation, centre line)
20-Jul-12 A
22-Sep-12
Q...
KE-42WORP1240
Pouring Concrete Fc-35
20-Jul-12 A
24-Sep-12
P...
KE-42WORP1250
Install Water Proofin g
26-Sep-12
27-Sep-12
I...
2
2
2
19-Jul-12 A
19-Jul-12 A
19-Jul-12 A
25-Sep-12
25-Sep-12
24-Sep-12
2...
2...
R...
KE-42WORP1330
Formwork
19-Jul-12 A
24-Sep-12
F...
KE-42WORP1340
QA/QC check list ( Reinforcement, Formwork, elevation,centre line)
20-Jul-12 A
25-Sep-12
Q...
KE-42WORP1350
Pouring Concrete Fc-35
20-Jul-12 A
25-Sep-12
P...
17
06-Sep-12 A
15-Oct-12
17
06-Sep-12 A
15-Oct-12
TRANSMISION TOWER
GENERAL
KE-00TTSY0000Shop Drawing
11
11
14
21-Sep-12
21-Sep-12
21-Sep-12*
06-Oct-12
06-Oct-12
06-Oct-12
CIVIL
KE-41TTSY0020cutting pile
4
2
21-Sep-12
21-Sep-12
26-Sep-12
22-Sep-12
2...
c...
KE-41TTSY0030backfill / digging
24-Sep-12
26-Sep-12
b...
KE-41TTSY0040manual compaction
25-Sep-12
26-Sep-12
m...
26-Sep-12
26-Sep-12
b...
6
1
27-Sep-12
27-Sep-12
04-Oct-12
27-Sep-12
0...
p...
28-Sep-12
04-Oct-12
R...
KE-42TTSY1030formwork footing
28-Sep-12
04-Oct-12
f...
12
12
6
06-Sep-12 A
06-Sep-12 A
06-Sep-12 A
15-Oct-12
15-Oct-12
03-Oct-12
P...
03-Oct-12
04-Oct-12
p...
11
04-Oct-12
15-Oct-12
52
08-May-12 A
03-Dec-12
15
07-Jul-12 A
11-Oct-12
1...
15
15
6
07-Jul-12 A
07-Jul-12 A
07-Jul-12 A
11-Oct-12
11-Oct-12
27-Sep-12
1...
1...
F...
KE-43PBGT3120Install Column
28-Sep-12*
30-Sep-12
I...
KE-43PBGT3130Install I Beam
28-Sep-12
30-Sep-12
I...
10
01-Oct-12
11-Oct-12
11
11
6
07-Jul-12 A
07-Jul-12 A
07-Jul-12 A
06-Oct-12
06-Oct-12
27-Sep-12
0...
0...
F...
21-Sep-12*
25-Sep-12
I...
COVER
CONCRETE
KE-42WORP1310
Reinforcement
SWITCHYARD
150KV SWITCHYARD
CONCRETE
KE-42TTSY1010pouring lean concrete k-125
FEEDER BAY
CONCRETE
KE-42FBSY1000Piling
SITE INFRASTRUCTURE
GTG POWER BUILDING
Steel Structure PB 1
STRUCTURAL STEEL
KE-43PBGT3110Fabrication
Steel Structure PB 2
STRUCTURAL STEEL
KE-43PBGT3210F abrication
KE-43PBGT3220Install Column
Actual Work
Milestone
Remaining Work
Summary
Nov
16
Dec
17
Jan
18
Feb
19
Mar
20
Apr
21
May
22
Jun
23
Jul
24
Aug
25
Sep
26
Oct
27
1...
1...
0...
0...
S...
1...
1...
R...
0...
I...
Page 9 of 13
PP - Imeco
3 Weeks Look Ahead Schedule 120 MW CCPP
KDL Project
Activity ID
Activity Name
RD
Start
2013
Finish
Sep
14
KE-43PBGT3230Install I Beam
21-Sep-12
25-Sep-12
10
26-Sep-12
06-Oct-12*
15
07-Jul-12 A
11-Oct-12
6
6
1
20-Sep-12 A
20-Sep-12 A
20-Sep-12 A
28-Sep-12
28-Sep-12
21-Sep-12*
Oct
15
Nov
16
28-Sep-12
11-Oct-12
11-Oct-12
26-Sep-12
F...
27-Sep-12
27-Sep-12
P...
27-Sep-12
27-Sep-12
Q...
KE-42PBST2180work permit
27-Sep-12
27-Sep-12
w...
KE-42PBST2190Curing Time
14
28-Sep-12
11-Oct-12
C...
8
8
2
28-Sep-12
28-Sep-12
28-Sep-12
09-Oct-12
09-Oct-12
29-Sep-12
0...
0...
s...
28-Sep-12
29-Sep-12
M...
01-Oct-12
01-Oct-12
P...
02-Oct-12
09-Oct-12
11
11
6
07-Jul-12 A
07-Jul-12 A
07-Jul-12 A
05-Oct-12
05-Oct-12
27-Sep-12
0...
0...
F...
KE-43PBST3020Install Column
01-Oct-12*
05-Oct-12
I...
KE-43PBST3030Install I Beam
01-Oct-12
05-Oct-12
I...
52
08-May-12 A
03-Dec-12
DRAWING
GENERAL
KE-00CWWS0000
Shop Drawing
1
1
2
08-May-12 A
08-May-12 A
08-May-12 A
22-Sep-12
22-Sep-12
22-Sep-12
52
52
60
13-Sep-12 A
13-Sep-12 A
21-Sep-12
03-Dec-12
03-Dec-12
03-Dec-12
KE-42CWWS1030
Reinforcement footing
13-Sep-12 A
30-Sep-12
R...
KE-42CWWS1040
Formworks footing
13-Sep-12 A
30-Sep-12
F...
KE-42CWWS1050
Pouring concrete Fc' 35 footing foundation
01-Oct-12*
01-Oct-12
P...
KE-42CWWS1060
Reinforcement T-Beam
13-Sep-12 A
06-Oct-12
R...
KE-42CWWS1070
Formwork T-Beam
13
13-Sep-12 A
06-Oct-12
F...
KE-42CWWS1080
Installation anchor bolt
29-Sep-12
08-Oct-12
I...
T-BEAM
CONCRETE
KE-42CWWS2010
Backfill inside
2
2
3
04-Oct-12
04-Oct-12
04-Oct-12
06-Oct-12
06-Oct-12
06-Oct-12
0...
0...
B...
STRUCTURAL STEEL
STRUCTURAL STEEL
KE-43CWWS3010
Fabrication
5
5
5
24-Sep-12
24-Sep-12
24-Sep-12
28-Sep-12
28-Sep-12
28-Sep-12
26
14-Sep-12 A
26-Oct-12
21
21-Sep-12
20-Oct-12
Actual Work
Milestone
Remaining Work
Summary
Apr
21
May
22
Jun
23
Jul
24
Aug
25
Sep
26
Oct
27
1...
21-Sep-12
21-Sep-12
21-Sep-12
Mar
20
2...
2...
P...
28-Sep-12
Steel Structure
STRUCTURAL STEEL
KE-43PBST3010Fabrication
Feb
19
I...
Floor
CONCRETE
KE-42PBST2360soil backfill inside
Jan
18
I...
15
15
5
Console
CONCRETE
KE-42PBST2150Formwork
Dec
17
F...
1...
1...
R...
0...
2...
2...
S...
0...
0...
F...
2...
2...
F...
2...
2...
Page 10 of 13
PP - Imeco
3 Weeks Look Ahead Schedule 120 MW CCPP
KDL Project
Activity ID
Activity Name
RD
Start
2013
Finish
Sep
14
Oct
15
Nov
16
21
30
21-Sep-12
21-Sep-12*
20-Oct-12
20-Oct-12
2...
S...
26
26
30
14-Sep-12 A
14-Sep-12 A
21-Sep-12
26-Oct-12
26-Oct-12
20-Oct-12
2...
2...
F...
KE-42CESB1020Reinforcement Pedestal
15
14-Sep-12 A
05-Oct-12
R...
15
15-Sep-12 A
07-Oct-12
F...
KE-42CESB1060Reinforcement T-Beam
15
14-Sep-12 A
24-Oct-12
KE-42CESB1080Formwork T-Beam
15
14-Sep-12 A
26-Oct-12
15
28-Aug-12 A
11-Oct-12
1...
15
12-Sep-12 A
11-Oct-12
1...
15
12-Sep-12 A
11-Oct-12
1...
15
15
1
12-Sep-12 A
12-Sep-12 A
12-Sep-12 A
11-Oct-12
11-Oct-12
21-Sep-12
1...
1...
I...
45CGTG-B1020Grouting Work
16-Sep-12 A
22-Sep-12
G...
45CGTG-B1025Curring Time
23-Sep-12
28-Sep-12
C...
29-Sep-12
29-Sep-12
I...
30-Sep-12
30-Sep-12
C...
01-Oct-12
01-Oct-12
T...
02-Oct-12
02-Oct-12
C...
03-Oct-12
11-Oct-12
C...
5
15
30-Sep-12
12-Sep-12 A
05-Oct-12
11-Oct-12
0...
1...
15
15
1
12-Sep-12 A
12-Sep-12 A
12-Sep-12 A
11-Oct-12
11-Oct-12
21-Sep-12
1...
1...
I...
45CGTG-B2020Grouting Work
16-Sep-12 A
22-Sep-12
G...
45CGTG-B2025Curring Time
23-Sep-12
28-Sep-12
C...
29-Sep-12
29-Sep-12
I...
30-Sep-12
30-Sep-12
C...
01-Oct-12
01-Oct-12
T...
02-Oct-12
02-Oct-12
C...
03-Oct-12
11-Oct-12
MAIN EQUIPMENT
MECHANICAL
45CGTG-E2000Centering GT, Generator & Load Gear
5
5
3
30-Sep-12
30-Sep-12
30-Sep-12
05-Oct-12
05-Oct-12
02-Oct-12
0...
0...
C...
03-Oct-12
05-Oct-12
A...
03-Oct-12
05-Oct-12
I...
15
28-Aug-12 A
11-Oct-12
21-Sep-12
01-Oct-12
0...
7
0
21-Sep-12
Metal Deck
01-Oct-12
21-Sep-12
0...
M...
ECCB0040
21-Sep-12
R...
ECCB0050
Acessories
21-Sep-12
A...
GENERAL
CESB0000
Shop Drawing
FOUNDATION
CONCRETE
KE-42CESB1015Fabrication Reinforcement
KPI
GTG
GTG 1
SUBSOLE PLATE
MECHANICAL
45CGTG-B1015Inspection of Sub Sole Plate & Packer Plate
MAIN EQUIPMENT
GTG 2
SUBSOLE PLATE
MECHANICAL
45CGTG-B2015Inspection of Sub Sole Plate & Packer Plate
Actual Work
Milestone
Remaining Work
Summary
Dec
17
Jan
18
Feb
19
Mar
20
Apr
21
May
22
Jun
23
Jul
24
Aug
25
Sep
26
Oct
27
R...
F...
C...
1...
Page 11 of 13
PP - Imeco
3 Weeks Look Ahead Schedule 120 MW CCPP
KDL Project
Activity ID
Activity Name
RD
Start
2013
Finish
Sep
14
Oct
15
ECCB0060
Plumbing
24-Sep-12
ECCB0070
Electrical
01-Oct-12
E...
ECCB0080
Cable Tray
29-Sep-12
C...
Procurement
15
28-Aug-12 A
11-Oct-12
1...
28-Aug-12 A
28-Aug-12 A
21-Sep-12
11-Oct-12
11-Oct-12
26-Sep-12
1...
1...
R...
M...
PCBO0020
Metal Deck
21-Sep-12
26-Sep-12
PCBO0030
21-Sep-12
26-Sep-12
PCBO0040
28-Aug-12 A
22-Sep-12
R...
PCBO0050
Brick Wall
21-Sep-12
21-Sep-12
B...
PCBO0060
Painting
22-Sep-12
24-Sep-12
PCBO0070
25-Sep-12
29-Sep-12
PCBO0080
Electrical
10
01-Oct-12
11-Oct-12
11
08-Sep-12 A
06-Oct-12
0...
11
11
3
21-Sep-12
21-Sep-12
21-Sep-12
06-Oct-12
06-Oct-12
24-Sep-12
0...
0...
C...
Construction
Zona 1 ( Axis 4C' - 5B / Raw A1 - B1)
STRUCTURAL STEEL
CESS1060
Column Axis 4C' - 5A / Raw A1
26-Sep-12
B...
CESS1080
27-Sep-12
28-Sep-12
B...
CESS1090
29-Sep-12
01-Oct-12
B...
CESS1100
Alignment Column
11
21-Sep-12
03-Oct-12
A...
CESS1110
Bolt Tightening
10
26-Sep-12
06-Oct-12
7
7
4
08-Sep-12 A
08-Sep-12 A
10-Sep-12 A
01-Oct-12
01-Oct-12
25-Sep-12
0...
0...
A...
B...
Bolt Tightening
08-Sep-12 A
25-Sep-12
CESS2120
26-Sep-12
01-Oct-12
G...
10
10
2
20-Sep-12 A
20-Sep-12 A
20-Sep-12 A
04-Oct-12
04-Oct-12
22-Sep-12
0...
0...
C...
B...
CETR1020
Beam
21-Sep-12 A
25-Sep-12
CETR1030
Roof Trust
28-Sep-12
02-Oct-12
CETR1040
Alignment Column
03-Oct-12
04-Oct-12
2
2
2
26-Sep-12
26-Sep-12
26-Sep-12
27-Sep-12
27-Sep-12
27-Sep-12
8
8
4
26-Sep-12
26-Sep-12
26-Sep-12
05-Oct-12
05-Oct-12
29-Sep-12
0...
0...
S...
01-Oct-12
05-Oct-12
M...
8
8
5
26-Sep-12
26-Sep-12
26-Sep-12
06-Oct-12
06-Oct-12
01-Oct-12
0...
0...
Z...
02-Oct-12
06-Oct-12
21-Sep-12
28-Sep-12
CPSS2020
Actual Work
Milestone
Remaining Work
Summary
May
22
Jun
23
Jul
24
Aug
25
Sep
26
Oct
27
B...
CESS2110
Metal Deck
Apr
21
E...
25-Sep-12
CONW1020
Mar
20
P...
Painting Steel
ARCHITECTURAL
CPSS2010
Zone 2 Elevation +11.700
Feb
19
P...
Jan
18
A...
CESS1070
Dec
17
P...
15
15
5
Other
GENERAL
PCBO0010
Nov
16
R...
A...
2...
2...
E...
Z...
2...
Page 12 of 13
PP - Imeco
3 Weeks Look Ahead Schedule 120 MW CCPP
KDL Project
Activity ID
Activity Name
RD
Start
2013
Finish
Sep
14
Oct
15
21-Sep-12
21-Sep-12
2...
0
0
21-Sep-12
21-Sep-12
21-Sep-12
2...
C...
21-Sep-12
28-Sep-12
2...
6
7
21-Sep-12
21-Sep-12
28-Sep-12
28-Sep-12
2...
R...
PESB0030
Anchor
21-Sep-12
26-Sep-12
A...
PESB0040
Brick Wall
24-Sep-12
24-Sep-12
B...
Engineering
GENERAL
EESB0020
Concrete
Procurement
GENERAL
PESB0020
Actual Work
Milestone
Remaining Work
Summary
Nov
16
Dec
17
Jan
18
Feb
19
Mar
20
Apr
21
May
22
Jun
23
Jul
24
Aug
25
Sep
26
Oct
27
Page 13 of 13
PP - Imeco
3 Weeks Look Ahead Schedule 120 MW CCPP