Enafor Rig 08

PRIDE, OWNERSHIP AND EXCELLENCE

Tg-360 12-1/4in Hole Section Leak-Off Test at 13-3/8in Casing Shoe Revision No. 1 Operational Objectives: No accidents, no harm to people and no damage to the environment Obtain Leak-Off Test data at 13-3/8in casing shoe Operational Hazards: Formation fracture Manual handling rigging up Dowell lines High pressure Mud losses Well Status: 3m of new formation has been drilled Bottom is at 740m. 13-3/8in casing shoe at 733m MD TVD Mud weight in hole 1.15sg Casing has been tested to 2000psi (bumped plug) Important Notes: Have LCM materials close to mixing hopper and ready to mix Have 30bbls LCM pill mixed and ready to pump. Ensure chemicals are available for thixotropic cement plug Have radios at Dowell unit and on rig floor Operations Circulate at least 1 X BU o Ensure Mud Weight in = Mud Weight out o Take SCRs Pull bit into casing o Space out for annular preventer Install Circulating swage, lo torque valve and chiksans. Line up cement unit to annulus via choke line and to drill string

Flush through cement lines with 5bbls WBM. o Cementer to record hydrostatic pressure on his gauge after flushing lines o Sperry Sun to record depth of PWD tool (MD and TVD) o Break circulation down drill pipe and choke o Pressure test lines to 200/2000 psi for 5/10 mins o When bleeding off do not drain lines o Zero pressure gauges on cement unit to account for hydrostatic between rig floor and cement unit o Close annular preventer Perform LOT pumping at 0.25 bbls/min continuously o Expected volume versus pressure:
500psi 0.5bbls. 750psi 0.7bbls. 1000psi 0.9bbls. 1250psi 1.2bbls. 1500psi 1.4bbls. 1750psi 1.6bbls.

o Monitor flowline to ensure no returns during LOT o Do not exceed 2000 psi (Casing Pressure Test) o Shut down pumps when pressure breakover occurs. o Record (graph) pressures every 0.25 bbls pumped o Record total volume pumped o Record initial shut in pressure and continue monitoring pressure for 10 minutes, and until pressure is relatively stable for 2 mins o Bleed back mud on drill pipe and annular sides (there is a float in the string). o Record volume returned Open BOP, close the choke line o Do not move drill pipe until PWD data has been pumped up to surface. o Line up to rig pumps and pump up MWD PWD data at 700gpm Once data received, line cement unit up to wellbore and pump WBM into well to empty displacement tanks. Continue to drill ahead as per programme. Thanks JV Team 3rd October 2010 2

You might also like