Value Engineer The Work-Process To Achieve Target Costs

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 11

ROBHRT M.

PATTY AN MlCHAIiL

A. D EN TO N

Value Engineer the Work-Process


Creative an d critical

to Achieve Target Costs

thought tion, seeking to eliminate th e cost of repetitive inefficiency where it can mak e a combined significant tim e an d dollar impact. Kvafuate of process tasks relative to th e tim e an d resources spent doin g it . Wou l d th e client be w illing importance to pa y fo r thi s activity it the y kne w projects wer e doing it ? Is it Is thi s th e first an d onl y tim e th e tea m wil l be doin g it ? value added fro m th e clients or hi s customer's viewpoint, rework, or is it jus t moving things around, correcting mistakes, reviews, internal reporting, justification, setup an d preparation, Label each step as value added, or non-value delays? added Typ e 1 mud a or Typ e 2 muda: Valu e Adde d 10

is applied to eliminate or alter an y actions tha t do no t contribute directly to tas k comple-

Retain (hut tcanot e excessive cycle Wast e tha n be eliminated wittimes) h existing technology. Cont ributo ry work , such as moving mate Typ e 1 Mud a ria l around th e jobsite Consider ho w to eliminate Typ e 1 muda , now ! after it has arrived is typical. Typ e 2 Mud a Consider advancing th e technology to remove it . Requires advancing technology to delete.
and then standardized, by th e wor k team, wit h th e sup an d tools to construct them, need to flo w Al l components in just-in-time; right things, right quantity, right time, right place, right quality Th e pla n should contain al l work-task required inputs, manpower an d system modeling resources, make-ready tasks an d examples of deliverables an d methods. Th e deliveries should be ready to pick, set an d release, already built up , including par t kit s an d too l kit s fo r every task; e.g., palletized, color-coded, lai d ou t at th e point-of-assembly Lis t wor k perforin pre-established ordcr-of-assemb)y. mance standards no w an d desirable ones fo r th e future. Se t internal performance goals fo r speed, cost, usability an d flexibility. Wher e feasible, items should be fixtured using self-aligning an d supporting, reusable devices, so cycle tim e is dramatically shortened fo r final assemblers, Create mor e standard (Se e Chapter 9: Mechanics of Cycle Tim e Reduction,) features. Define options to assure robust installation operations-Teams seek to buil d int o their standards an d work-task plans applicable lessons learned, e.g., field verification, principles of huma n factors, an d design fo r field assembly. (Se c Chapter 8 fo r mor e advanced lea n rules an d tools.) Work needs to be rigorously value engineered to meet target price

por t an d training of industrial an d construction engineers.

on the Quality of Work-Task Packages Definitions - Thi s constitutes a paradigm shift awa y fro m th e accuracy o f estimator-experience based production level task duration estimates an d assurance of sufficient contingency. It e l i m i Focus

tea m wil l rel y instead on verifying everything tha t wil l mak e th e tas k mor e productive, an d eliminating wha t migh t slowdown or hal t a tas k during execution. Sub-team leaders si t dow n wit h each design lead, e.g., exchangers, to define wel l th e process he done, rather tha n fo r their work-tasks, as the y ma y be different fro m others, an d nee d to be represented as the y will assuming the y should be performed th e sam e wa y as other disciplines. The y should engage commitments fro m th e leads themselves, an d rely on frequent updates by th e leads themselves to enable m in i m iz i ng th e impact of change whe n it occurs. Culminate thi s wor k int o th e creation of advanced standardized work-task packages.

nates th e nee d fo r additional layers of management to attempt to impose such estimates on th e team. Ti c

Redesigned

Work-Task

Deployment

Planning
11

& Jones. ) Review an d refine relies heavily o n Womack th e work-design wit h process w a l k t h r o u g h s , Identify points of interface wit h other first-case rehearsals or simulations. subsystem or majo r component teams. or contingent actions. Identity ne w Analyze potential problems, preventative upstream requirements an d downstream challenges. Define a pilot period wit h tim e fo r corrections needed .
Determine how any new work-process

will be tested, (This

section

Explore

transition

management and organizational

impact.

Define work-process owners

needs to be documented measure an d maximise an d output straight line, multiple


Document

an d improved.

Assign to work-process

ownership th e responsibility

using those wh o kno w wha t to : maintain documentation,

performance, identify problems an d opportunities, champion improvements, coordinate input communications wit h other work-process owners. Simplify th e work-process, or rearrange it to provide parallel or alternative paths; fo r advantage. Consider f ron t- end decision making, single point of contact or
reusable work-process,

points of contact fo r bottleneck


training

removal
and

.
measurement in the standards with project specifics m each work-

Documentation should direct, jargon-free, clear, anrevisions. d brie f an d include an know d instructions fo r should be hand y an d he hav e a process fo r updates an d Include wha toptions th e tea m s fo r problem emergencies* It . prevention
26 9

task package.

control

CHAPTER

7 - ENGINEERING

TO FULLY UTILIZETHE

CONSTRUCTION

WORKFACE

Huma n Factors of Flo w

Onc e we line up al l th e essential steps needed to ge t a jo b don e int o a steady, continuous flow, wit h no wasted motions, no interruptions, batches or queues, it changes th e huma n factors. Ho w we wor k together, th e kinds of tools we devise to hel p do th e work , th e organizations we create to facilitate th e flow, th e kinds of careers we pursue, th e nature of business firms an d their relation (see Chapter 11 ; Lea n Cultures Tha t Sustain Accelerated Improvement). It wil l require addressing real needs of employees along th e info rm ation an d material stream so tha t it is in their best interest
12

to other firms

to mak e th e value flow. To ignore th e huma n factors is to invite malicious compliance.

Improve Reward Systems


Ideally, lean accounting and reward systems nee d to lin k th e success o f products produced b y a plant through it s productio n lif e wit h th e original efforts of th e FE L an d Execution stage design, fabricators an d construction team. Lea n reward systems lin k to product success, to offset th e existing tendency toward admirable technical features whic h engineers an d sometimes eve n plant operators like, bu t fai l to return profit due to hig h initial cost, startup delays, training an nance expense- Th e reader should consider ho w thi s will be don e fo r th e employees of project teams: Client Employees EP C Employees Level 1 Suppliers Level 2 Suppliers - Module Assemblers - Original Equipment Manufacturers exhibit d mainte-

Make the business environment as inherently rewarding as possible. Th e mos t rewarding business environments, (this section relies heavily on research by psychologist Mihaly Csikzentmihalyi, University of Chicago' );
3

"a permanent creative tension, tha t demands concentration a clear objective a nee d fo r concentration so intense tha t no attention is lef t ove r an d distractions a lac k of interruptions clear an d immediate feedback on progress toward th e objective a sense of challenge - th e perception tha t one's skills are adequate, bu t jus t adequate to cope wit h th e tas k at hand" Unde r these conditions, people experience a highly satisfying state of psychological flow. People lose their self-consciousness an d sense of time. The y fin d th e tas k itself becomes th e en d rather tha n a means to something mor e satisfying like mone y or prestige. Examples of activity wit h psychological flo w include: roc k climbing games interactive writing a boo k
Detractions from psychological jlow include:

batch an d queue wor k worker seeing onl y a small par t of th e tas k little or no feedback, or less immediate feedback wor k requiring onl y small portion of concentration or skills to deal wit h other tasks in one's field of responsibility constant interruptions Th e reader should consider bee n further improved their mos t satisfying jobs, matching an d ho w it relates to thi s research. these criteria ? Ho w could th e job s have

by eve n mor e attributes

Eliminate the Fear of Job Loss from improvement


Taking away the fear of job loss resultingfrom improvement is at the very core of lean conv ersion* Thi s section relies heavily o n

Womack & J o n e s ,

(Fear of Job Los s = Resistance

to Improvement).

Resistance

to improvement

an d relentless unless employers guarantee workers will no t be ou t of a job , eve n if their

will be underground specific jo b is eliminated. Th e

270

ROBERT M . PATTY AN D MICHAEL A. DUNTO N

"wor k force wil l have a ver y har d rim e differentia rin g layoffs du e to wea k demand an d those du e to kaizen" (improvemen t sessions). Therefore, jo b guarantees, in return th e goa l is to layoff people early to th e level sustainable under lea n management. The n offer fo r cooperation an d working in a ne w way. Th e reader should consider ho w th e resources of th e employees will no t be lai d of f fro m improvement ?

lean enterprise will be marshaled to guarantee


Lines of defense before laying ojj people, include:

"Reduce

overtime

Pu t extra people o n kaizen improvement workshops t o g e t a future payback" In-source mor e pre-assembly, or eve n site fabrication "Cu t th e workweek across th e board Gro w th e business"

Dealing with Unions


15

flow an d continuous improvement i n Problems with Union Rules - Unio n rules ma y mak e i t impossible t o introduce every activity. Thi s is because unions usually have narrow job assignmentsskilling, an d no tea m structures. jo formal b rotation, multi-equipment operaFormally or Informally, Unions Must Accept the Concepts o f multi-craft If engaged in wha t the y clearly see as competitive tion , an d continuous movement of job s an d wor k between groups. advantage, unio n workers will .
16 17

n ignore oncaan massive scale to get jo b done O n a project It is interesting tha t lea n caseofte studies detailtechnical thi s sor t contract of thing- details Unions usually be dealt wit th h e effectively. at Syncrude, in N o r t he r n Alberta, Canada, th e unions ben t ove r backwards to contribute to th e lea n process. The y too k ownership of it as a wa y to prove the y could provide a competitive edge. Although th e United Aut o Workers Unio n keeps trying, the y hav e nott venture bee n able to interest a Japanese majority an of d workers in unionizing hav aney bee of Toyota's new plants in th e Som e join plants between U,S , manufacturers n unionized, To achieve United States, active unio n cooperation consider th e f ollow ing: Train Them Involve th e unio n people an d their stewards an d managers and Then in th e lea n training. The nTake a Lean "Walk of Shame" of shame" through every par t of th e engineertak e th e unio n hea d an d managers on a"walk in g department an d construction areas. Ther e is mud a an d onc e trained, the y wil l be able to see it , Th e
13

mud a include; 'correction


1

everywhere,

of mistakes whic h should never hav e taken place" (see Chapter 9 (Se section on Mistake Proofing) e Chapter 9 section on Micr o Pla n "movement to Workface fin d parts Tasks an d tools whic hCycle should be )immediately at hand " Construction to Reduce Time "wasteful motions through a lack of careful analysis of ho w to do th e job " (see Chapter 9 section on Cycle Tim e Reduction) Chapter machines or other cre w members whic h could be taught to monitor themselves (see

wasted tim e watching

9 section on Loa d Leveling an d Lin e Balancing) waiting materials waiting fo fo r r missing poorly coordinated equipment, or other crews inventories everywhere

Help Union PeopleTha Understand tha t job s an d living cannot be of maintained by bargainingfo rtomutual extract benefit the m witht ol d process is irrelevant tostandards th e current culture superior performance . ou tHelp mutual benefit. Unions to See the Need for Market Differentiating Performance anticipate problems in a tea m context an d Proactively prevent the m whil e constantly rethinking th e organization of wor k an d flo w of information an d material to remove muda , Thi s will hav e th e craft itself doing man y activities o f the Union in Problem Improvement lea Involve n management, improving fa rSolving, mor e rapidly tha n Activities th e rest -of management could do alone. Construction teams ar e already highly skilled in traditional construction operations . jo b rotation, roo t cause analysis, preventative maintenance. Thi s Provide unions training fo r kaizen, involved, multi-skilling, strategies of rapid, profound, an d hcontinuous improvement. wit their u n i o n s,
20

If unions ar e

wil l allow the m to com e up wit h ingenious

th e reader should derive a union action plan, fo r ho w the y will dea l

27 1

CHAPTER

7 - ENGINEERING

TO FULLY UTILIZE TH E CONSTRUCTION

WORKFAC E
1

^
P

t '

Lean Teams Become Broadly Skilled Cross-Function


Ihis is necessary to achieve the higher levels o f savings an d results fro m on-the-job

training. Team s ar e trained to perform";


21

multiple functions to enable continuous flo w of mor e tha n a fe w minutes.

Machines an d people need to be mor e generally; quantity o f engineers wit h

capable, ideally to handle a ver y wid e variety of tasks. Thi s section relics heavily on th e wor k of W o mac k am i Jones.
Hire and train diversified design team members, wit h specialist where needed, bu t a significant

experience to function wel l ove r a variety of anticipated tasks. Thi s is to facilitate rapid resource shifting. Tea m members should be trained to perform tasks before an d after their ow n traditional trade or engineering specialty. Eventually, mos t wil l nee d to become cross-skilled at man y tasks. Onc e cross-trained, crews nee d to be created tha t are sufficiently flexible tha t the y ca n handle a wid e variety of tasks well. Team s integrated wit h several technologies /trades, are le d by th e crew or tea m member mos t qualified specialists. Mos t marketing, by virtue of th e tas k at hand. requiring fewer, narrowly skilled
Lean teams are smaller due to cross training and love the variety. Lea n teams ar c smaller,

engineering, procurement an d construction professionals hav e broader skills tha n the y realize, or hav e ever bee n allowed to use, e.g., du e to th e cross-training received as engineering undergraduates, Whe n small lea n teams ar e appropriately tasked, the y successfully accomplish allowed to do before, an d the y enjoy it , a muc h broader range of tasks tha n the y hav e ever been

Logistics of Flo w

Work Faces and Takt Time for Flow and Pull


Availability of a Workface Should Pull - A completed task frees u p a workface an d visibility o r triggers should hav e kept th e nex t tas k lead appraised. Ti e tas k lead ca n the n pul l th e nex t tas k wit h it s cre w int o action. Pul l fro m an available workface needs to control wha t happens nex t above th e need to prioritize keeping crews busy. A workface should no t be

unused mor e tha n th e tak t time. Cross training creates flexibility to keep crews busy ,
Consider Options for Use of Takt Time - T o simplify

operations,

pla n al l activities
l

i n multiples

o f tak t time, e.g., A


l

day. Tliis is to say tha t th e in f o r m at i on mus t flo w at multiples of A day, i.e., fo r triggers on th e workface map . Th e reader should consider ho w can an available FEL- 3 workface be lai d visible by tas k planning an d mapping an d select an appropriate FEL-3 multiple of tak t tim e fo r example, tw o times or Vz day- Whe n a recent majo r industrial tea m wa s introduced to tak t tim e an d asked ho w frequently th e four-week sequence of workface tas k pla n needed to be updated, a foreman replied/'Well, ho w lon g do yo u wan t my cre w to be standing around waiting?" Every A da y wa s selected.
l

Simplify Flow Logistics


Not e in Figure 7-5 tha t traditional supply an d assembly required 18 support facilities, Atlas V Lea n Sit e Flow, following th e conversion lea n manufacturing flo w applied to th e traditional Not e tha t prior to the introduction of flow at Boeing, using lea n flow, Boeing-Lockheed
23 22

Figure 7-6 displays th e Boeing


24

Another Martin

example in Figure 7. 7 shows th e impact of Delt a IV supply an d assembly operations,

man y additional buildings wer e required to store al l th e parts to assure the y woul d be there whe n needed. Thi s is muc h lik e current project use of shakeout/laydown yards an d tempoan d on th e final assembly site. Material rar y parts warehousing. Further, materials move d fa r greater distances bot h of f movement is inherently non-value added. Whil e teams wil l never eliminate al l of it , significant reduction ca n ofte n save substantial tim e an d cost. Boeing wa s able to eliminate th e nee d fo r mos t of their support facilities wit h their attendant cost. Further, lean flo w on Atlas V reduced factory assembly tim e fro m 36 to 10 months, a 72 % reduction.
2 5

Consider Co-Locating Facility Design, Manufacture and Assembly to Simplify Flow


Design ca n usually best serve th e customer in th e sho p or ou t in th e field, where designers ca n observe th e current design, manufacturing or construction status, where the y ca n see firsthand th e results of their actions. Bes t practice on majo r projects is to provide al lconstruction sites a field engineering office. EPC s maintain large hom e offices wit h th e infrastructure needed to support th e prim e engineering an d procurement activities. Plants are frequently in undesirable international locations an d of short enough duration logical place fo r concurrent engineering is an d locate
27 2

tha t engineers don't wan t to mov e there. Consider where th e mos t as man y skill an d stakeholders there as possible (note: the y might

ROBERT
CENTAUR VFHlCt E

M PATTY AN D MICHAEL A. DENTO N

f-RS SOLID ROCKET BOOST

Payload

II / HI Traditional Processing Flo w Figure 7.5 Ada s

Processing Facility no t shown

CENTAUR VEHICLE

N
Receiviny A frtSp&clion Launch Con!A'][ CtmutT A RA Ccrti*f Saliery L;it> AriminfciraLEVt? OHuTCS Cnmir)UEni;iUioji-, Antii(ffl\ Slur us CENTAU R

ADAPTERS

Vf P Viewin g JL3 O t t o s Mission D# nMor Cw\\ a Coiiln>! f ^ o om ITAR Facilit y S^cocriifl CottfurGncfi BOOSTERS SOLID ROCKET Ccnta r

BOOSTER VEHICLE

L V RT S\ia<:HC(<ii\ Mala 1ST SRB STAGING

-Payload -1 2 launches / vear Processing Facility not shown Capacity


MOBILE LAUNCH PLATFORM

V Lea n Processing Flo w 36 Atlas II , II I an d Titan I V Facilities into 3 Ada s V Facilities


27 3

Figure 7.6

Ada s

Consolidated approximately

CHAPTER 7 - ENGINEERiNGTO

FULLY UTILIZETHE CONSTRUCTION

WORKFACE

* Heavy structural parts travel 6,257 miles to final assembly point an d the n 1,917 miles to th e Cap e vi a escorted truc k *
Figure 7. 7 Decatur Lea n Flo w Optimised fo r Cycle Tim e

Heavy structural parts travel 2, 1 miles through th e factory an d the n 1.5 miles to RD/RO

be located at a supplier fo r som e complex subsystems.) Th e balance will engineers an d managers on th e jobsite fo r final material procurement, fo r jobsite erection. Place die m in offices nex t to th e preassembly space, if noise levels ca n be controlled.

. Large or expensive-to-store materials an d equipment nee d final erection workface, confirmed ready fo r th e nex t task* .

doc k for environmentally controlled shipment via Delta Manner vessel


Pre-Plan Near-Instant Work Setups by preassembltes coming to be pre-engineered, an d Throughput vs. Traditional
Often lean implementation Delta IV s in

Fab to launch rate: 23 months

Fab to launch rate: 15 months


Manufacturing
0

Flo w on

mated systems. complicated, higher speed ones.


7

nee d to travel where needed. Consider

adding

preassembly an d kitting per se and Select simple, accurate and robust equipment - Systems an d equipment whic h ar e simpler, accurate, consistent an d Equipment selected fo r use repeatable ar e preferred ove r one s tha t are simply faster. in th e sho p or field needs to be quiet machinery. During construction, people nee d to tal k frequently to coordinate an d Improving construction wor k process machinery ma y be challenging, solve construction problems an d implement improvements, no t jus t focusing on getting th e current tas k done, bu t on ho w to improve it fo r th e nex t go-around

Mistake Proofing -

to flo w ont o th e jobsite, directly

to th e final preassembly

or

Othe r items should be triggered fo r shipment

as needed an d

temporarily stored unti l required Employees mus t be taught to monitor their ow n wor k an d us e machines, jigs, fixtures or visual techniques to prevent mistakes (see Chapter 9 section

Reduce Setup Time


27 4

Crew s nee d t o avoid lengthy setups, especially setups consuming to th e final construction of hourly workface in combination wit h a transportable
2

workface

time, e.g,,

setup. Cre w setups need

an d mad e ready so tha t the y are almost instant. Establish a process to deal wit h th e ebb an d flo w needs to implement setup improvement schemes on th e site bu t of f th e workface.
manufacturing has led to the elimination rather than the addition of high speed, hard auto-

Th e cost savings is i n reduced setup time, lowe r maintenance automated machines However, an d software.
2

an d coordination companies

o f simpler

systems over t

eventually,

lea n manufacturing

sport som e highly flexible, sof

bu t should metrics ca n be identified. See section on Setup Reduction in Chapter 9.

be considered

where improved

user

Poka Yoke
titled Consider Visual Tas k Engineering to Enhance Worker Productivity). Th e concept

ROBERT M PATIT AN D MICHAEL

A.

DENTON

fo r an error to be is to mak e it impossible passed on to th e Examples include nex t task. ji g or scanner-based dimensional verificatio n an d visual controls suc h as matching signs on bea m alignment fixtures or pip e an d Chapter 9 color codes (see Figure 7. 8 section on Mistake Proofing) .

Total Productive ) (TPM

Maintenance

Whil e a discussion of total productive maintenance (TPM ) techniques is beyond recommended readth e scope of thi s book , in g on di e subject includes publications fro m th e Productivity Press , especially an d Suzuki, To Robinson an d Ginder , 5S principles (see Definitions get started, an d Ke y Concepts) should be applied to al l
28 30 2y

equipment, leading to a clean an d manageable wor k area organization, tidiness, purity, cleanliness an d discipline to maintain it .

Al l debris an d unnecessary items should be removed an d every too l should hav e a clearly marked storage place visible from th e wor k area. (Als o see Chapter 8 section Wor k (5S ) a Foundation fo r Visual Control). Place Organisation
31

Color Coding Pipes is a for m of Mistake Proofing

7-8 Preparing Execution Stage Figure Information

Flo w Control

As described in Chapter 4, an in for mat ion an d material stream fo r th e facility delivery process during th e Execution and Material phase, ca n be described fro m a macro vie w as show n in Figure 7.9- TTiis is no t an ideal lea n state, primarily because it contains multiple uni t buffers. (i.e., fro m detailed design through startup), Not e tha t th e process is controlled fro m tw o activities. First, th e FJzL-3 Team But , it is a th e Final buffers as tea m familiarity aninventory d robustness enables doin g th so. Installation, By including buffers between e sets e overall ca tasnk be sequence according to difficulties are worked out , th e rate o f th installation increased by reducth e chain wit to perform each function to achieve th e required delivery Th actual in g critical cycle tim e at th e h resources initially established Ho we suc h a process spee d da y to day, is controlled by th e actual . pace of tasks, onc e th e project is lean project is controlled started, an d ix\itU\ final erection tio n on a project, whic h could reduce an d finally remove goo d starting poin t fo r lea n implementa-

Erection Construction is described and in thi s section


final erectio n-Jlow

workfaces

an d th e resources adjusted up an d dow n th e lin e to support it. By doin g so,

no rma lly be man y final workfaces on a project available at an y on e time. Thi s graphic shows wha t ma y be necessary to control an d Th e intent flo w during EP will C is be tha t every available fina l erection/construction workface is full th y eutilized. support one of . Similar setups necessary fo r each of them . (Note: To continuously support displayed workface, control board is show n i n Figure 7 ,10 . Not e tha t there Eac wilhl suc h lin e is thi s hypothetical tea m expected to maintain on e an d onl y three kitting/preassembly an d on e e information line,)should balance their Th e kitting/p re aslines sem bly/modul assembly crews on e preassembly, ki t or module ready to erect/construct (shown waiting in th e grey . Thu s whe n th e current tas k at th e workface is complete, th e nex t on e ca n be waiting as nea r as possible to erect it, an d waiting fro m each line
27 5

project e is minimized, A Final tim Installation,

has established

inventory efforts

buffer).

an d th e cre w can proceed immediately to maintain

on e (an d onl y one ) finished

CHAPTER 7 - ENGINEERING TO FULLY UTILIZE TH E CONSTRUCTION WORKFACE

FEL- 3 Wor k & Tea m Breakdown

Inde x
* * * Pac e Pull azj * Plant * Pus h * Inventory * > i

Q BulTe i

Medium Lon g Lea d F abricator

Len d

* Activity Controller

D e t a i l ed D e s i gn Figure 7. 9 Sample Lea n Valu e Scream

Fabricator y

& Kit

FlowInstal Control l Boards

Final

Start o p Fab . Info Transfer Material Tnimlc

Planned Srate

Lxeeution

Fabrication Programming
1

& s

Suppl

FEL-3 P reassemble Wor k &

Commissio

Map , Project Delivery,

Detailed Desi n

& Ki t

Tea m

B reakdow n s

Lon g Lea d Fabricator ;

Labor

Tas k

Citrmtt Status

Pulle
ll>ijv
V.-.h j-a - n j nr-i i

Medium Lea d Fabricators


nilioii I inn
1

Tas k
_

^
:

>-

Curri'ii f Status

i ^ T J u i

,NCHIOU^

Detcrip'li< m d

Tul a 2 K

P u l U P u sh

Aiuton Ujiht
X
i

^ On Schedule Execution ! mmin .Current SriSin Progra

32
Unvid Dodge, Orgil flussit, Joel Sonbe r Buffer

J t

Kitting

Tas k

Fabrication & Supply


^

Preassernblc

Commission

y
1

Index

Scak'i! linn' u u l M ' IJ I U ' IH '* ' rcijuirctl m i C i i c l i side Component (Voni Final Installation I
i :

Chili iro Sinii/u, l\mi;eij Lon^s, Sobe Fckk r Mi d lead [Sutler no>;enplioi i d

a* ,

* Tiuu -Se;jk'<l l U i of 1 on^lh r t i n i i ml each v * Ki t / s


Tim e SciLct

Progress Ahea d

B e hi nd

Set s th e Pac

Hum* c urt

^il l/Li ft

On

V - phmmICits or pr e roiitlv tin- fimit erection r n


;

Lolly Oat-

VVorkfuee ^ Foreman Crow \

iik >

Truck / Preussemhh Final E rection waitin g

y
Ciirri-ti

Install Buffer

Final Erection

/ Constructio e
Lon g lead Item

Figure 7.1 0

3 Kitting & Pr ca ss em b ly

an d 1 Information

Lin e

Feeding ] Final Erection / Construction Workfncc

time, (e.g., 2 - 4 his)

oa^^o

to r proiUiscJi iblv Miumtrteluver Supplier lursiddin^ component to Pmiwinblv Tnn^portei assemblies p i v as su uM LebersForminj;toi], Final Krcctkm

c o ns tr uc ti o

Kitting & Preassembi

n at on e w o r k f a e

Flo w Control T Inventory

Board, Scaled in Multiples oftakr

ROBERT M. PATTY D MICHAEL A,

AN DEMO N

Ac tak t tim e intervals, cre w chief an d th e final erection foreman considers hi s progress an d each preassembiy line whe n changes to hi s commitments are anticipated, calls hi s manager to shift resources to maintain or update th e control board. In addition to th e other assemblies (preassembled of f site) ar e assemblies an d kit s coming of f th e three site lines, added to th e lineup. Som e ma y items ordered during th e 90-day loo k ahead or before, Not e tha t th e lineup be lonare g lea d fo r a ful l da y of preassembiy items waiting in th e queue an d th e system upstream is resourced so tha t ne w ones replace those erected as fas t as tha t occurs . Wha t woul d upstream tea m members do if the y are ahead of schedule? on th e floor an d sec if anyone needs hel p an d go len d in g in tota! cost reduction. The y woul d loo k at th e andon (signal) lights

a hand- Not e th e advantage of cross training an d everyone benefitteams at th e subsystem, stream an d project level hav e By viewing multiple such flo w boards, a workface visible to shift resources as needed to maintain th e flow, Ik e tim e so th e cre w members or management ca n easily see unit s ar e sequenced an d th e tasks scaled in tak e th e .status ando n light is no t onl y on th e control board, bu t also on th e site an d relative needs of eac h line. Th e nea r eac h workface, Since th e item s ar e delivered in order, wha t should be don e nex t is obvious to everyone. So, crews se t th e module, preassembiy o r d o construction wit h th e kit . Th e Flow Control Board is tim e scaled accordin g to estimated tas k durations. However, variance fro m planned durations is rendered visible to th e tea m an d Not e tha t majo r variances hav e bee n eliminated using lea n methods previsystems designed to accommodate it. ously described. Hence, tha t whic h is accommodated b y thejlow control boards is hu e tune d t o assure performance an d facilitate p r i o r i t i z i n g an d balancing resources an d imp rov ement . Thi s is in contrast to th e continual slippage typical of non-lean control systems. at every workface to erect as fas t as the y can it , teams wil l eliminate mos t of th e current 30 % resource consumption in handling) moving materials around on site after the y wai t tim e an d muc h of another 30 % in re-transport tim e (double have bee n delivered, Further cycle tim e reduction at th e workface will become th e focus, because, if teams ca n decrease that, everything else wil l be set up to be ready to go faster, We wil l describe th e necessary supporting systems backwards critical chain, an d the n tak e a loo k at flo w control fo r commissioning an d startup, (upstream) to di e safely go? By figuring it ou t an d implementing Wha t wil l it tak e to support suc h a lineup of kit s an d preassemblies

Preassembiy and Kitting


create stoppage at th e final construction workface. Conversely, jo b sites wil l no t be inundated wit h a lo t of stuf f tha t is no t needed, Improvemen t ca n be quickly implemented without having to change a lo t of completed materials. on wha t materials Focus first are needed, the n mak e sure th e in f o r m at i on flo w keeps th e material flowing. The n assure resources to are to bebalanced focused at maintain th e sequence an d avoid an y wasted tim e in th e system. Thi s wil l enable further improvement th e final erection workface using fixturing an d other cycle tim e reduction techniques (see Chapter 8) , Moving lin e preassembiy, module build-up an d or kitting fo r each workface could largely be fro m time-scaled . sequenced material an d equipment line-ups on each side of th e module path Preassembiy processes mus t be resourced according to actual progress so there will b e n o gaps co

Moving Module Assembly


Figure 7,1 1 of aircraft modules, an example of world-class manufacturing excellence. shows a moving assembly line Observe wha t is an d is no t happening. Slowly moving aircraft modules (a fe w inches per hour ) pass sequenced an d timescaled lineups of material an d equipment on bot h sides, The Module Work Process Embraces Variation. Thi s execution planning an d production layout is simple com Moving pared to th e usual construction control systems. It easily an d economically accommodates hundreds of variations on each module, (e.g., craft or process unit), ) (Se e Chapter 9 section on Wor k Process Layout, Cells an d Flexible Assembly, fo r Visual, Easily Discerned Scheduling is Achieved. Th e tea m can visually assess readiness as a schedule-oivthe'floor exactly wha t the y an d where the y nee d it - Everyone ca n discern an d actively manage it , need, whe n Th e intent is to mimi c thi s process where feasible on an d of f th e project site. Imagine if preassemblies an d components cam e to th e jobsite an d wer e further preassembled int o modules tha t wer e to o large to economically ship, bu t could Oft e n plants are ver y be built up to a size fo r ne t total cost reduction, at ground level near th e constricted at th e final workfaces. utilization of suc h a final erection workface. constricted workface. Sequenced an d fixtured Moving lin e preassembiy could ver y economically facilitate full . pipes an d structural steel on safety skids (see Figure 7,12) could be placed in th e tim e scaled lineups fo r th e modules. Thi s could avoid significant traditional handling 27 7

You might also like