SCOPE OF WORK
Contractor is responsible for carrying out all the works mentioned in the contract agreement between himself & the employer with proper planning, quality & highest standards of health and safety. Contractor need to coordinate with all other stake holders of the project in order to complete the works on time. Contractor to arrange all adequate man, material & machinery as required.
Contractor carries out duties by supervising employees and planning how the project is to be carried out. Completion of the project should be coinciding with all rules & regulations which may be in existence and correlate with construction.
Finance Manager
Personn el Manager
QA/QC Manager
Safety Officer
Manager Dwellings & Bungalows/Apartme nt JE-PHE Supr. Bungalow JEElectrical Supr. Bungalow
QC Eng MEP
QC Eng. Civil
Documen t Controller
Procuremen t Officer
Supr. Bungalow Supr. Dwelling Senior Engineer-Civil Senior EngineerInteriors Senior Engineer
Sr Eng. Electrica l
Sr Eng. PHE
Sr Eng. HVAC SP 1
JE
JE
JE 1
JE 2
SP 2
SP 1
SP 2
SP 1
SP 1
SP 1
SP 1
JEElectrica l SP 1 SP 2
JE-PHE
JEHVAC
SP 1 SP 2
SP 1 SP 2
PLANNING MANAGER
Prepare job cost report and work method statement. Issue work method statement for project director approval. Procurement planning and supplier interaction. Prepare project master plan with project schedule. Prepare periodical budget reports. Propose necessary modifications as per project status report. Act as company representative in absence of project lead.
Oversee work in progress and its conformance with QA/QC. Monitor and review subcontract or billing and claims. Internal department co-ordination and procurement follow up.
SAFETY OFFICER
To provide health and safety awareness to all levels of site workforce. To conduct safety inspection before commitment of work. To develop, review and update safety procedure manual. Site representative for fire and safety, police departments, environmental department communication. Preparation of necessary safety related documentations and accident reports. Responsible for proper functioning of First Aid Centre.
QA/QC MANAGER
Serve as contractors quality representative. Prepare project quality control plan. Performance reporting of sub-contractor. Sub-contractor qualification review and vendor selection. Administer and monitor quality control compliance. Co-ordinate resolution of conflicts.
Administer and monitor QC inspection, sampling testing and reporting. Review and rectify work method statement. Documentation of test certification and warrantee items. Necessary co-ordination for third party certifications.
FINANCE MANAGER
Monitor cash balance and requirements. Prepare cash flow forecast. Co-ordinate internal reporting and development of management reporting and analysis of companys financial and operating performance. Implement financial forecast to predict operating result and improve planning results.
Account reconciliation. Lead financial audit process. Oversee accounts payable and purchase and manage risk insurance policy renewals. Administrating all payroll processes and documentation of the same.
QUANTITY SURVEYOR
Preparing tender and contract documents, bill of quantities. Cost control analysis. Subcontract work allocation. Evaluate work in progress, completed in conjunction with material/manpower/machinery utilized and prepare client billing and produce cash flow. Risk and value management.
PROCUREMENT OFFICER
Issue purchase order for procurement and expedition of materials and equipment for jobs. Research market for best suppliers and cost savings. Manage material inventory.
Ensure timely delivery of ordered products with all relevant certificates. Co-ordinate with administration department for site logistics. Maintain material tracker and corresponding payment details.
Prepare daily work progress report. Prepare subcontractor billing. Approve material issue slip for site work to be carried. Prepare material indent sheet. Verification of materials received on site.
DOCUMENT CONTROLLER
Authorized personnel for issuing all approved shop drawing, technical submittals and test certificates. Proper documentation of all project related correspondence letters and documents. Responsible for all front office correspondence.
STORES IN-CHARGE
Responsible for proper stacking of all project materials. Authorized to issue material for construction based on material issue slip. Keep a track of all issued, balance and yet to receive material list. Ensure First in First out concept. Quantification of materials received.
PROJECT DIRECTOR
DEPARMENT CO-ORDINATION
Project Director Requirement Planning Department Instruction Senior Manager Solution Requirement
Senior Engineer
Solution
Requirement
Junior Engineer
Instruction Supervisor
Budget Report
SAFETY COMMUNICATION
PROJECT DIRECTOR
Safety Report
Senior Manager
Incident Report
Safety Advice
PROCUREMENT FLOWCHART
Junior Engineer Prepares MIS Issue Materials
Stores
Senior Engineer
Checks
Procurement Department
Senior Manager
Delivery Schedule
Planning Department
RECCOMENDATIONS
The project consists of executive bungalows, apartments, and supervisor dwellings, labour dwellings with market and entertainment complex. In this exercise we have selected optimum manpower for the project as the projects like dwellings and bungalows are similar in nature and the designs would be identical. In the initial stages of the project a senior engineer would assist a junior engineer to handle all these segments of the project. Once a dwelling or a bungalow gets completed the junior engineer would be able to handle dwelling and bungalow project independently. This would help the contractor to retain same manpower for other areas of project. A senior engineer in all departments would be required in apartment & entertainment complex projects due complexity in design & planning, material and specialized skill labour management would be required to execute the works. A junior engineer who was working for the dwellings can also be utilized for entertainment complex project once the 25% of dwelling project gets completed. A supervisor who was working in the dwelling project can take charge of junior engineers position and can monitor till its completion.
BIBILOGRAPHY