Professional Documents
Culture Documents
Planned Value (PV) : PMBOK Guide
Planned Value (PV) : PMBOK Guide
Planned Value (PV) : PMBOK Guide
The definition of Planned Value says that Planned Value is the value of the work that should have been completed so far (as per the schedule). Therefore, in this case we should have completed 50% of the total work. Hence, Planned Value = 50% of value of the total work = 50% of BAC = 50% of $100,000 = (50/100)X $100,000 = $50,000 Therefore, Planned Value (PV) is $50,000
Actual Cost is also known as the Actual Cost of Work Performed (ACWP).
Example: You have a project to be completed in 12 months and the total cost of the project is $100,000. Six months have passed and $60,000 is spent, but on closer review you find that only 40% of the work is completed so far. What is the Actual Cost (AC)? Finding the Actual Cost (AC) is simplest of all. As per the definition of Actual Cost, it is the amount of money that you have been spent so far. And in our question, you have spent $60,000 on the project so far. Hence, Actual Cost is $60,000
If SPI is greater than one, this means more work has been completed than the planned work. If SPI is less than one, this means less work is completed than the planned work. If SPI is equal to one, this means the work completed is equal to the planned work.
CPI = EV/AC The Cost Performance Index informs us how much we are earning for each dollar spent on the project. Note:
If CPI is less than one, this means we are earning less than the spending. If CPI is greater than one, this means we are earning more than the spending. If CPI is equal to one, this means earning and spending is equal.
Network analysis Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects. One definition of a project (from the Project Management Institute) is A project is a temporary endeavour undertaken to create a "unique" product or service This definition serves to highlight some essential features of a project
With regard to the use of the word unique I personally prefer to use the idea of "non-repetitive" or "non-routine", e.g. building the very first Boeing Jumbo jet was a project - building them now is a repetitive/routine manufacturing process, not a project. Two different techniques for network analysis were developed independently in the late 1950's these were:
PERT (for Program Evaluation and Review Technique); and CPM (for Critical Path Management).
Network analysis is a vital technique in PROJECT MANAGEMENT. It enables us to take a systematic quantitative structured approach to the problem of managing a project through to successful completion. Moreover, as will become clear below, it has a graphical representation which means it can be understood and used by those with a less technical background.
activities are represented by arrows.[1] ADM is also known as the activity-on-arrow (AOA) method. ADM is used for scheduling activities in a project plan. Precedence relationships between activities are represented by circles connected by one or more arrows. The length of the arrow represents the duration of the relevant activity. ADM only shows finish-to-start relationships, meaning that each activity is completed before the successor activity starts. Sometimes a "dummy task" is added, to represent a dependency between tasks, which does not represent any actual activity. The dummy task is added to indicate precedence that can't be expressed using only the actual activities. Such a dummy task often has a completion time of 0.
Use of ADM as a common project management practice has declined with the adoption of computer-based scheduling tools. In addition, the precedence diagram method (PDM), or activity-on-node, is often favored over ADM.
[2]
ADM network drawing technique the start and end of each node or event is connected to an arrow. The start of the arrow comes out of a node while the tip of the arrow goes into a node. Between the two nodes lies an arrow that represents the activity. The event represented by the circular node consumes neither time nor resources.
A node is a specific, definable achievement in the project. It has zero duration and consumes nil resources. All activities that lead into a node must be completed before the activity lies following this node can start.
The precedence diagram method is a tool for scheduling activities in a project plan. It is a method of constructing a project schedule network diagram that uses boxes, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.
Critical tasks, noncritical tasks, and slack time Shows the relationship of the tasks to each other Allows for what-if, worst-case, best-case and most likely scenario
early start date late start date early finish date late finish date duration WBS reference
When performing project planning activities, the manager will attempt to schedule certain tasks simultaneously. When more resources such as machines or people are needed than are available, or perhaps a specific person is needed in both tasks, the tasks will have to be rescheduled concurrently or even sequentially to manage the constraint. Project planning resource leveling is the process of resolving these conflicts. It can also be used to balance the workload of primary resources over the course of the project[s], usually at the expense of one of the traditional triple constraints (time, cost, scope). When using specially designed project software, leveling typically means resolving conflicts or over allocations in the project plan by allowing the software to calculate delays and update tasks automatically. Project management software leveling requires delaying tasks until resources are available. In more complex environments, resources could be allocated across multiple, concurrent projects thus requiring the process of resource leveling to be performed at company level. In either definition, leveling could result in a later project finish date if the tasks affected are in the critical path. Resource leveling is also useful in the world of maintenance management. Many organizations have maintenance backlogs. These backlogs consist of work orders. In a "planned state" these work orders have estimates such as 2 electricians for 8 hours. These work orders have other attributes such as report date, priority, asset operational requirements, and safety concerns. These same organizations have a need to create weekly schedules. Resource-leveling can take the "work demand" and balance it against the resource pool availability for the given week. The goal is to create this weekly schedule in advance of performing the work. Without resource-leveling the organization
(planner, scheduler, supervisor) is most likely performing subjective selection. For the most part, when it comes to maintenance scheduling, there is less, if any, task interdependence, and therefore less need to calculate critical path and total float.