Wastewater Treatment

(Selected Case Studies)

JOHANNES ANDIGAN SINAGA 10/296550/TK/36165

JTSL FT-UGM 2012/2013

1. Singapore
Location : Singapore Water Reclamation Study (NEWater Study), Singapore

Flow diagram process :

The main process : Secondary effluent pumping combined with chlorine dosing and equalization tank; Microfiltration: 6 units of 480S10T CMF-S cells; Filtered water storage combined with chlorine dosing; 5 units of two-stage (49 vessels 1st stage, 24 vessels 2nd stage, 7 elements/vessel) RO trains; 3 units of UV irradiation for disinfection; and Product water storage and pumping combined with pH and chlorine control.

2. Tokyo, Japan
Location :Ochiai Water Reclamation Center for Meguro River Restoration, Tokyo (by Tokyo Metropolitan Government)

Sequence of Treatment Units :

The main process :


Preliminary and primary treatment : Grit Chamber and Primary Sedimentation Tank Secondary treatment : Activated Sludge Process (ASP) Tertiary treatment : A2O process for nutrient removal, sand and Membrane Filtration and UV Radiation

3. Berlin, Germany
Location : Nordkanal Wastewater Treatment Plant, Willich, in North Rhine Westphalia Integrated Water Cycle Management :

The flow diagram below shows this cycle which proceeds in the following order: water intake - drinking water supply sewage and stormwater purification dilution and self purification in the remaining waters - bank filtration and groundwater replenishment - water intake.

Process flow (Membran Bioreactors MBRs ) :

4. Balikpapan, Indonesia
Location : WWTP Margasari Balikpapan

Process flow: The treatment is based on an activated sludge process.Before the wastewater enters the aeration tank a screen removes solid waste from the wastewater. The wastewater is pumped into an equalization tank which serves probably as well as sand trap. The bacteria mass is separated in a clarifier and recycled back to the aeration tank. The treated water flows into a control tank. A chlorination installation is not used. The sludge is pumped to a sludge tank. Up to now the sludge is then pumped direct into the river . By discharging the sludge to the river the whole treatment process becomes obsolete and the river is almost as polluted as without treatment.

Source:
Mediterranean Wastewater Reuse Report, Annex B: Case Studies by MEDITERRANEAN WASTEWATER REUSE WORKING GROUP (MED WWR WG), November 2007 Review of Wastewater Reuse Projects Worldwide, IIT Kanpur, December 2011 Nordkanal Wastewater Treatment Plant, General Electric Company, 2008 COMPARATIVE STUDY CENTRALIZED WASTEWATER TREATMENT PLANTS IN INDONESIA, Development Alternatives, Inc. for the United States Agency for International Development, September 2006